You are on page 1of 3

Ground Grid Integrity

Tech Tips
by Jeff Jowett
Megger

T
he testing of grounding electrodes…grids, meshes, and the like…is most The grounding electrode typically is
often considered in terms of a resistance test. That is to say, the resistance carrying only noise, but must be able
to accommodate worst case conditions
of the surrounding environment to current flow to some arbitrary or of high current flow when called on
carefully plotted point typically referred to as remote earth or infinite earth. The line during an event. Therefore, to test
ground grid is intended to serve the dual purpose of carrying currents into the grid integrity, the tester must be able
to produce high current. A grid tester
earth without exceeding the operating tolerances of any protected equipment works similarly to a ground tester in
while assuring that personnel in the vicinity are not exposed to electric shock as that it supplies current and measures
would result from excessive step or touch potentials. Resistance tests indicate voltage drop across the test item. In
this case, the test item is the grid,
the overall capability of the grid in this regard: its electrical relationship to its
whereas in a ground test, it includes
environment. But there remains the question of the internal condition of the the surrounding soil. It is dissimilar in
grid itself. that the grid tester typically employs
an industry standard of 300 amperes,
Out of sight, out of mind? Buried under ground, the grounding electrode
whereas a ground tester operates on
doesn’t call attention by mere visual inspection, which is the first step in most
the milliampere level. Rather than
electrical maintenance. Though they may seem inert, grounding electrodes are
calculating and displaying resistance,
subject to their own unique set of stresses, just like other electrical equipment.
the grid tester evaluates the change in
Fault clearance and lightning protection can severely damage a grid or mesh,
current flow.
separating individual elements, interrupting continuity, and introducing high
Test equipment consists of a vari-
resistance across bonds. But in the meantime, the electrode may have cleared the
able current source requiring on the
fault perfectly well, leaving no obvious indication that it has been compromised.
order of a 10.5 kVA capability, oper-
A subsequent event may not be afforded the same level of protection.
ated from a 50 ampere, 240 Vac source.
Furthermore, a less dramatic but more persistent force of deterioration is
Test leads can range anywhere from
the incessant process of corrosion and weather. Freezing and expansion exert
10 to 100 feet of 2/0 welding cable. A
pressures that can break apart a grid. Ironically, the best grounding soils are also
reference ground is first established,
the most corrosive. Low resistivity soil that facilitates the flow of fault current
preferably a transformer neutral. The
also promotes electrolytic current that eats away at the metallic structure of a
leads are connected, one to the test
grounding electrode. Use of dissimilar metals hastens the process. Rods have been
ground and the other to the reference
known to last as little as two years, with typically a risk of at least some corrosion
ground below any bonding connec-
effects being present after four.1 A standard ground resistance test just looks at
tions (Fig. 1). The tester is then ener-
voltage drop across the surrounding soil and gives no measure of the physical
gized and adjusted to pass 300 amperes
condition of the electrode itself.
via the reference ground through the
grid under test for a duration of three
minutes.

www.netaworld.org Fall 2008 NETA WORLD 


account for all the current that is injected into the system.
By injecting a substantial amount of current, it becomes
comparatively easy to note its division along stress lines. It
is expected that most of the current will follow the short-
est, straightest path (least resistance) between the two test
points. The ammeter readings indicate to what extent this
is occurring. Discontinuity or high resistance connections
anywhere between the test points will divert proportionate
amounts of current through the rest of the system.
A C Substations are multiply-bonded into a Faraday cage
configuration, and other facilities with complex or extensive
D grids are also typically connected to the electrical system
B
at multiple points. Therefore, it cannot be presumed that
all current is flowing in a particular path. Current flowing
from the tester must first be measured for any diversion into
the system (point A, Fig. 1), and to determine the amount
flowing into the grid (B). This value is then compared to
the amount returning through the test ground (D), and
that which is diverted through parallel paths into the rest
Measurements after Test Hook-Up of the system (C).
To illustrate, an example of an acceptable test is shown
Figure 1 in Fig. 2. Pretest conditions indicate typical values of cur-
rent flowing on the system. The distance between the test
A clamp-on ammeter is then used to measure current connections is measured, and the voltage drop across the
at critical points around this system: through the reference leads is taken from the tester. Performance of the test then
ground above (A) and below (B) the attachment of the test indicates 270 amperes flowing into the grid, with some
lead and on the opposite side of the system through the test diversion through the reference ground back into the elec-
ground both above (C) and below (D) the lead connection. trical system. The ground connection being measured then
Current readings are recorded, and the tester indicates shows 280 amperes returning (test current enhanced by
voltage drop across the system. Voltage drop of the leads some “noise” on system). Since this is a grid, the industry
themselves is also measured. This is done by disconnecting standard calls for at least a 150 ampere return, so this is well
from the test item, shorting the leads together, and passing exceeded. Voltage drop across the test was measured at 7.9,
300 amperes for three minutes, noting the voltage. This value but as 7.5 of this was lead resistance, only 0.4 volt is across
is then subtracted from the voltage drop taken during the the tested path. This falls within the allowance for 1.5 volts
test to isolate voltage drop across the grid from the lead per 50 feet (1.5/50 x 15 = 0.45). The tested ground path
contribution. For an indication of acceptable continuity, a passes both criteria with acceptable values.
value of no more than 1.5 volts per 50 feet of straight line A failed test is outlined in Fig. 3. Here, only a negligible
ground path should be measured. The straight line ground amount of current returns through the tested ground con-
path is the distance between the two lead connections. nection, while 280 amperes flow through building structure
Though valuable, this method is not rigorously precise, via a parallel connection. Voltage drop calculates to 8.1 (15.6
and so a redundant system of evaluation exists based on – 7.5), which fails the requisite criterion (100 feet allows 2
current return. For single driven electrodes, at least 200 x 1.5 = 3 volts). If the test setup were switched to the other
amperes should return to the source via the ground path. leg of the structure, results would be essentially reversed, so
For mats and grids, at least half of the current must return the ground connection on the left would have to be dug up
via the ground path. If not, it indicates a potentially bad and inspected for a fault in continuity.
connection and should be dug up for repair. Similarly, ground cables, clamps and ferrules can be
What is the method that makes this procedure success- tested prior to installation using the same equipment and
ful? What happened to Kirchhoff ’s laws? Kirchhoff ’s first parameters. Cable manufacturer’s specifications should
law states that the sum of the currents flowing from a point provide proper voltage drop. For instance, 300 amperes
in a circuit equals the current flowing to that point, i.e., on 100 feet of cable yields 30,000 ampere-feet. For 4/0
current is a precisely measurable quantity that doesn’t just bare copper, the voltage drop should be 4.1 volts. For a 10
“disappear into thin air.” Operation of the high-current grid foot section, therefore, the voltage drop would be 0.41. If
tester is based on an application of Kirchhoff ’s first law to manufacturer’s guidelines are not available, the following

 NETA WORLD Fall 2008 www.netaworld.org


Measurements before Test Hook-Up Hook-Up and Connections

Figure 2 Figure 3
Measurements before Test Hook-Up Measurement before Test Hook-Up
1. Current in transformer neutral (reference) = 82 amperes 1. Current in transformer neutral (reference) = 82 amperes
2. Current in the post ground wire = 6 amperes 2. Current in frame ground = none
3. Distance between reference ground and post ground = 15 feet 3. Distance between reference ground and frame ground = 100 feet
4. Voltage drop in test leads with 300 amperes = 7.5 volts 4. Voltage drop of the test leads with 300 amperes = 7.5 volts

Measurements after Test Hook-Up and with 300 Amperes Flowing Measurement after Test Hook-Up and with 300 Amperes Flowing
in the Test Circuit (i.e., test set meter reading) in the Test Circuit (i.e., test set meter reading)
1. Current flow in reference ground to grid = 270 amperes 1. Current flow in reference ground to grid = 270 amperes
2. Current flow in reference ground to T(X) = 50 amperes 2. Current flow in reference ground to T(X) = 50 amperes
3. Current flow from grid to post ground = 280 amperes 3. Current in frame ground from grid = 2.5 amperes
4. Current flow from the structure to post ground = 1 ampere 4. Current flow in frame ground from the structure = 280 amperes
5. Voltage reading at the test set meter = 7.9 volts 5. Voltage reading at the test set meter = 15.6 volts

formula can be used to get an approximation of voltage a faulty current path, the work of excavation and repair is
drop, bearing in mind that manufacturer’s specifications markedly reduced.
are always preferable:
1
Lyncole XIT Grounding
V = (2 x I x L x R)/1000 where, Electrical Equipment Testing and Maintenance, A. S. Gill, Prentice
I = test current Hall

L = length
Jeffrey R. Jowett is Senior Applications Engineer for Megger in Valley
R = resistance per 1000 feet Forge, Pennsylvania, serving the manufacturing lines of Biddle®, Meg-
ger®, and Multi-Amp® for electrical test and measurement instrumenta-
Specific code requirements are not in effect, but stan- tion. He holds a BS in Biology and Chemistry from Ursinus College.
He was employed for 22 years with James G. Biddle Co. which became
dards exist that provide guidelines for grid testing. Notably, Biddle Instruments and is now Megger.
NFPA70E-1983, Part I, Chapter 2, Section F, Item 4 out-
lines low-impedance continuity, and Part III, Chapter I,
Section B, Item 1 calls for continuous maintenance. OSHA
has adopted this as a safety requirement, and IEEE 81
references testing of grid structure. By this method, each
ground connection around a substation or other facility can
be tested. Faults are not precisely pinpointed, but by isolating

www.netaworld.org Fall 2008 NETA WORLD 

You might also like