Kompresi Waktu Pelaksanaan Proyek dengan Analisis

Metode RPM (Repetitive Project Modeling) pada Proyek RS


Tipe-36 Perumahan Griya Mitra Karya Bandung

by Shodik Mujahid
thesis paper for presented to Magister Management Program
Gadjah Mada University, 2002

Many project, such as construction of roadways, pipilines,


housing unit, and high rise buildings, involve considerable
repetitive construction activities that performed at all stage of
the project. Many researcher recognized the disadvantages of
using traditional network technique for planning, schedulling,
and monitoring such projects. Alternate approaches based on
graphical, or on analytical techniques have been proposed to
model repetitives project.
This paper present a new approach called the repetitives
project model (RPM) that models repetitive construction project.
Its model incorporates a network, a graphical, and a analytical
technique in a unified approach to model repetitive project.
The selection of a specific quantity of resources for a
construction activity determines the duration for the activity
and associated direct cost. Allocating more resources at
additional direct cost can decrease the duration of activity. As
the output of this paper, the activity time cost curve is presented
and the Linear Schedulling Method is illustrated by applying it to
an actual 100 units of land housing project. The RPM finds the
schedule for each activity will finish the project at a feasible
duration and at a minimum project direct cost.