You are on page 1of 10

70 ■ Transportation Research Record 1732

Paper No. 00 - 0328

Estimating Road User Costs Associated with


Highway Construction Projects
Simplified Method

Ginger Daniels, William R. Stockton, and Robert Hundley

Road user costs (RUC) are defined as the estimated incremental daily paper has been performed to develop simplified methods to estimate
costs to the traveling public resulting from the construction work being RUC for a variety of project types.
performed. Those costs are primarily time lost because of conditions such The A portion of an A+B bid is the contractor’s construction cost,
as detours/rerouting that add to travel time, reduced roadway capacity and the B portion of the bid is the product of the contractor’s estimated
that slows travel speed and increases travel time, or a delay in the open- construction days and the daily RUC. The contract is awarded to the
ing of a new or improved facility that prevents users from gaining travel lowest sum of the two components. The concept behind RUC and
time benefits. In Texas, RUC analyses and associated liquidated dam- A+B bidding is represented in Figure 1 (3). This graphic shows the
ages have been applied predominantly to high-profile urban freeway relationship between cost and time for a theoretical construction proj-
reconstruction projects, which are ideal candidates for RUC application ect. The curve labeled Construction Cost shows that the project has
because of the potential for very high motorist delay costs. A much wider an optimum duration of C working days. For a contractor to complete
range of projects involving the addition of capacity can be considered for the project in less than this time may require additional resources
RUC. Not all potential projects, however, are as complicated as urban (labor, equipment, and subcontracts), more expensive materials (fast-
freeway reconstruction efforts that require detailed simulation modeling setting concrete, precast bridge components, etc.), or both. If the dura-
to determine the value of RUC. The results of a research study that devel- tion of the project extends past the optimum point, time-related costs
oped a manual technique for determining RUC are documented, along such as project overhead (portable office trailers, project supervisory
with associated liquidated damages for typical added-capacity and high- personnel, etc.) can increase the cost of the project. This curve may
way rehabilitation projects. The technique involves a series of look-up differ from contractor to contractor.
tables that provide RUC values on the basis of project type and a minimal The straight lines at the bottom of the graph represent road user and
number of project attributes. Two different approaches were employed:
contract administration costs. These costs are time-related. The longer
a before-and-after approach for added capacity projects and a during-
the project continues, the higher these costs. Therefore, the total cost
versus-after-construction approach for rehabilitation projects.
of the project is the total of the construction, road user, and con-
tract administration costs. In this example, the lowest total project cost
According to the recently published NCHRP Synthesis of Highway occurs at B working days.
Practice 269: Road User and Mitigation Costs in Highway Pavement As illustrated in Figure 1, RUC is an integral part of the total cost
Projects, over 60 percent of respondents in a national survey consider equation. Therefore, a methodology for determining RUC that uses
road user costs (RUC) in planning mitigation strategies for new con- sound traffic engineering and economic principles is needed so that
struction and maintenance, but the vast majority does not perform RUC can be appropriately considered in the bidding process.
any quantitative analysis (1). The study concluded that user costs
would be more widely considered with enhancements in the user-
friendliness of computer-assisted user cost estimation tools. PROJECT TYPES
For at least 10 years in Texas, RUC has been included in the cal-
Before a manual technique for estimating RUC can be devised, an
culation of contract liquidated damages, or the daily penalty to the
assessment must be made of the types of projects that lend themselves
contractor for delayed completion of a project. More recently, daily
to a simplified method. It is desirable to cover as many different proj-
RUC values have been used in bonus/penalty contracts that incorpo-
ect types as possible with a simplified technique, understanding that
rate the contractor’s expected completion time as a bidding com-
(a) certain projects will be unique or too complicated for a generalized
ponent, also known as A+B contracts. The majority of these RUC
approach, and (b) an infinite number of combinations of capacity-
studies have been performed in the Houston and Dallas districts. The
upgrade projects exists.
Houston experience has led to the development of a short course to
The first step in this process is to define general categories of proj-
provide instruction on the techniques for determining construction-
ects and the suggested analysis technique for estimating RUC. The
related RUC (2). The course focuses primarily on the use of com-
project categories are provided in Table 1 (1, 2). Each of the pertinent
puter simulation models for construction on major freeways and
column headings is described below:
signalized arterial roadways. Additional research documented in this
• Category. Project types and attributes are divided into four
G. Daniels and W. R. Stockton, Texas Transportation Institute, 7715 Chevy
Chase Drive, Suite 4.160, Austin, TX 78752. R. Hundley, Texas Department of broad categories on the basis of the differences in analysis approach
Transportation, 125 East 11th Street, Austin, TX 78701-2483. and technique.
Daniels et al. Paper No. 00 - 0328 71

FIGURE 1 Project costs by type, related to duration (3).

• Description of projects. Projects and project attributes are tions of each phase or selected phases of the project. This approach
described. is most applicable to those projects with severe capacity restric-
• Setting. Categories of projects are classified as urban, rural, or tions during construction, for which phase completion time is
a combination of both. critical.
• General analysis approach. Several different approaches to –Before-and-after approach. As opposed to a phase-by-phase
determining RUC exist, depending on the project attributes: approach, a before-and-after comparison of user costs focuses on
–Phase-by-phase approach. The calculated user costs can be the delay in final completion of a new or improved facility. Each
used as the basis for liquidated damages for milestone comple- day that the final improved facility is delayed is another day that

TABLE 1 Categories of Candidate Projects for Application of RUC


72 Paper No. 00 - 0328 Transportation Research Record 1732

users are unable to realize travel time savings and other benefits • To the extent possible, the roadway classifications, average
from the additional roadway capacity. daily traffic (ADT) ranges, and design features selected are consis-
–During-construction-and-after approach. This approach is a tent with Texas Department of Transportation (TxDOT) terminology
combination of the two described above, and is applicable to and design standards.
projects in which the final improvements do not result in an • Roadways in highly urbanized areas are typically characterized
increase in capacity (i.e., rehabilitation projects). The during-con- by operational features such as closely spaced signals on arterials
struction-versus-after approach compares the user costs associ- and closely spaced ramps and interchanges on freeways. Roadways
ated with lane restrictions during construction with the user with these attributes are not candidates for simplified manual tech-
costs after construction is completed. niques for estimating RUC because of wide variations in operational
• Analysis technique. RUC can be estimated using a number of conditions. For this reason, the basic urban cross sections for which
different techniques. These techniques are classified as either simu- RUC values have been estimated are characterized as follows:
lation models [such as the FREQ and PASSER series of macroscopic –Urban arterials. The urban arterials selected for this project
traffic simulation models (2)] or by manual technique, such as tables, are consistent with the description in the Highway Capacity Man-
graphs, or hand calculations. ual for typical suburban arterials (5). They are characterized by
• Reference guide. Guidelines and procedures have previously low driveway density, separate left-turn lanes, one to five signals
been developed for projects that fall into Categories I and II (2, 4). per mile, little pedestrian activity, and low-to-medium-density
roadside development. For arterial roadways, the unit of length
Also included are procedures for calculating by hand projects such as
used for applying RUC values is 0.5 mi, meaning the table values
bypasses and detours. The projects that are described in Categories III
represent RUC per day per 0.5 mi (0.8 km).
and IV lend themselves to the use of the simplified manual techniques
–Urban freeways. The four-lane and six-lane urban freeway sec-
developed in this study.
tions included in this analysis do not include interchanges or ramps.
The unit of length used for applying RUC values is 1 mi (1.61 km),
Tables 2 and 3 show the different project types selected for devel-
meaning the table values represent RUC per day per mile.
opment of RUC tables, as well as general assumptions for calculat-
ing RUC values. Table 2 includes the projects that correspond with
SELECTION OF MANUAL TECHNIQUE
Category III, added-capacity projects. Table 3 shows the project
types that correspond with Category IV, rehabilitation projects. A Approaches
complete listing of input variables can be found in the full research
report (4). Additional items of note about selection of project types After review of several possible manual techniques, the decision
are provided below: was made to construct look-up tables that provide RUC values on

TABLE 2 Project Types and Variables—Added Capacity


Daniels et al. Paper No. 00 - 0328 73

TABLE 3 Project Types and Variables—Rehabilitation

the basis of project type and a minimal number of project attri- In order that the greatest possible range of added-capacity project
butes. Two different approaches were employed: a before-and-after types could be covered, separate tables were developed for ten dif-
approach for added-capacity projects, and a during-construction- ferent project types. Each table provides the values of daily RUC per
versus-after approach for rehabilitation projects. The tables for these unit length of an individual facility for a range of ADT volumes and
two approaches are constructed in different ways and require different percentage of trucks. The value selected from the table that repre-
procedures for using the values. sents the after condition is subtracted from the value selected from
table for the before condition. The difference between the two values
represents the daily benefits that the users are unable to accrue until
Format for RUC Tables the project is substantially complete and open to traffic. An example
of the procedure is presented in Table 4.
Added-Capacity Projects Using
Before-and-After Comparison
Rehabilitation Projects Using During-Versus-
Every roadway section that is traveled has motorist costs associated After-Construction Comparison
with it. To drive a given length of roadway, motorists will experi-
ence costs: the value of the motorists’ time to travel that section, the For rehabilitation projects that do not result in the addition of capac-
expenses to operate the vehicle over that section, and in the aggregate, ity, separate tables were developed for seven different project types
accident costs for the roadway section based on a rate of accident type under two different lane restriction scenarios. The values provided
per vehicle-kilometers (vehicle-miles) of travel. The absolute differ- in the tables are the estimated daily user benefits that are being lost
ence between the total motorist costs in the before condition and total during the time rehabilitation work is under way. Table 5 provides
motorist costs in the after condition is the total daily excess cost, an example of the procedure for estimating RUC for a rehabilitation
which is the value to be used in liquidated damages. The delay costs project.
are the most significant of the three component costs. Delays are expe-
rienced as the travel speed goes down because of capacity, geometric,
and operational constraints. The delay from the before condition is DERIVATION OF RUC VALUES
compared with that of the after or improved condition and the differ-
ence represents delay savings. The savings are then multiplied by the Selection of Model
value of time (VOT) to arrive at a dollar value of motorist time costs.
For the purpose of estimating RUC for contracting, the value of the A model was needed to calculate RUC values for the various tables.
excess delay costs will be the only component of RUC considered. The two characteristics that were important in selecting the analysis
74 Paper No. 00 - 0328 Transportation Research Record 1732

TABLE 4 Example Problem: RUC Table for Added-Capacity Projects

TABLE 5 Example Problem: RUC Table for technique were (a) that the model should be consistent with the scale
Rehabilitation Projects of analysis and the level of assumptions that would have to be made
to cover a broad range of project types, and (b) that the model should
be easy to use but based on sound traffic flow and economic theory.
The model selected for the development of RUC values is Micro-
BENCOST (MBC), a planning-level economic analysis tool devel-
oped by the Texas Transportation Institute under NCHRP Project
7-12 (6). The MBC program is designed for economic analysis of a
variety of highway improvements. It uses standard methodologies for
traffic allocation and speed/delay calculations. From an economic
standpoint, the advantage of the program is that the calculation of user
costs is included in the computations. For example, the program takes
into account the vehicle mix (including trucks) and the impact of vehi-
cle speeds as it assigns delay costs. The program calculates user costs
for a 24-h period, 365 days per year.

Use of MBC for Developing RUC Tables

Figures 2 and 3 are flow charts illustrating the basic functions of the
program and how it was used to develop RUC values for both added-
capacity projects and rehabilitation projects as part of this study.
FIGURE 2 Modification of MBC for development of RUC on added-capacity projects.
FIGURE 3 Use of MicroBENCOST for development of RUC on rehabilitation projects.
Daniels et al. Paper No. 00 - 0328 77

Added-Capacity Projects Using Speed-Volume Relationship for Suburban Arterials


Before-and-After Comparison
Traffic signals dominate the flow of traffic and dictate through traf-
As illustrated in Figure 2, the base geometric and traffic conditions fic speeds on arterial streets in urban areas. MBC uses the 1985
were provided as input, and the total motorist time costs for the Highway Capacity Manual procedures that require detailed signal
roadway were determined. As shown in the figure, the values were operation to determine delay, including signal phasing and conflict-
retrieved from the output provided for the existing, or before condi- ing cross-street traffic flows. It is impractical, however, to develop
tion, and not from the economic measures listed in the final summary. one set of assumptions for signal operation, signal spacing, and cross-
Iterative runs of the program were made for varying levels of ADT street volumes that would render meaningful and useful results for a
and truck percentages. wide range of projects. Therefore, a new speed-volume relationship
for urban arterials was devised for the program on the basis of
the Bureau of Public Roads for speed, flow, and level of service
Rehabilitation Projects Using a relationship (7):
During-Construction-Versus-After Comparison
1
Sr = S f
As illustrated in Figure 3, the full program features were used because [1 + 0.15( d c)4 ]
specific lane closure scenarios were defined. For the eight different
project types selected, two lane-closure scenarios were considered: a where
situation in which one lane is closed in the inbound direction, and
Sr = average running speed,
a second situation in which reduced capacity was seen (due to lane
Sf = free-flow speed, and
width, lateral clearance, construction activity, etc.). d/c = hourly demand-to-capacity ratio.
Table 7 presents the values used in the program for the speed-
Underlying Relationships and Assumptions volume relationship on suburban arterials with long signal spacings.

MBC is a comprehensive program utilizing best practical proce-


dures for highway economic analysis. The program combines both Development of RUC Values for
user inputs and defaults for the values used in the analysis. The full Rehabilitation Projects
research report provides the detailed input values for each project type
and a summary of the notable default parameters used by the program Additional features of MBC were used to develop two different
in the derivation of RUC (4). In all scenarios that were run, the final scenarios for a during-construction-versus-after analysis. Each is
program was given in user costs per year, which were converted to described below.
daily costs.
Described below are modifications made to the default values in Closure of One Lane MBC contains a work zone routine that can
the program. simulate lane closures. It can accept data on the number of days of
lane closure, the number of lanes closed by direction, the hours of the
lane closure, and the capacity of the remaining lanes during the clo-
VOT sure period. The default value provided by MBC is 80 percent of the
nonrestricted lane capacity. For the one lane closure scenario, the rou-
The values used for this analysis were consistent with the VOT for tine was run for a 365-day, 24-h lane closure. The final annual costs
passenger car occupants used by TxDOT, which is consistent with the were converted to daily costs.
default values used in MBC. The VOT used in MBC for trucks is also
that used by TxDOT. The values used in the program were updated All Lanes Opened with Reduced Capacity For the reduced capac-
from 1990 to 1998 values using the consumer price index (CPI). The ity scenario, which represents the condition in which the same
values used are provided in Table 6. number of lanes remains open during construction but is affected

TABLE 6 VOT Used in Derivation of RUC


TABLE 7 Speed-Volume Relationship for Principal Arterials in
Suburban Areas

TABLE 8 Model Comparisons (2,3, 8–10)


Daniels et al. Paper No. 00 - 0328 79

by reduced lane widths, lateral clearance, and other factors that influ- tion should be made of the use of MBC at the project level to analyze
ence traffic flow, a different analysis approach was taken. The exist- conditions specific to each unique project. Version 2.0 of MBC is
ing and proposed conditions were set up with identical input data, with under final revision and could be reviewed for this application. One
the exception of the 80 percent lane capacity value used in the exist- particular benefit of Version 2.0 is the incorporation of updated High-
ing condition. In other words, the program was run with the existing way Capacity Manual methodology for calculating vehicular speed
condition representing the work zone with reduced capacity, and and delay.
the proposed condition represented nonconstruction conditions.

Inclusion of Other Motorist Costs


Sensitivity of MBC and Comparison with
Other Methods Further research into the state-of-the-practice in the estimation of
vehicle operating costs and accident costs would provide a basis for
In general, MBC is most sensitive to the volume of traffic. At lower determining whether these elements can reasonably and appropri-
volumes of traffic, minor variations in the input variables have mini- ately be incorporated into calculation of RUC used for liquidated
mal impact on the final outcome. However, as traffic volumes increase, damages.
all variations in the input data should be considered important. Geo-
metric data such as lane width, median width, and shoulder width
have less of an impact on the output than percentage of trucks unless ACKNOWLEDGMENT
those measurements fall out of normal ranges. Wide variation in the
24-h distribution of traffic, average vehicle occupancy, or distribution The authors acknowledge the valuable direction of John Aldridge,
of vehicle types over that used in the development of the tables should of the Construction Division of TxDOT, who provided real-world
lead to reconsideration of the use of the tables in estimating RUC. clarity to the problem at hand and challenged the research team
MBC was compared with several different methods for calculat- throughout the project.
ing RUC. The program provides reasonable values in comparison
with other methods and given the work zone conditions analyzed. A
summary of that comparison is provided in Table 8. REFERENCES

1. Lewis, D. L. NCHRP Synthesis of Highway Practice 269: Road User


FUTURE RESEARCH and Mitigation Costs in Highway Pavement Projects. TRB, National
Research Council, Washington, D.C., Jan. 1999.
This study provides simplified manual techniques for calculating 2. Borchardt, D., and A. Voight. A Short Course on Techniques for Deter-
RUC. The findings of this research study will enable more widespread mining Construction Related Road User Costs. Texas Transportation
and consistent use of motorist costs in liquidated damages in Texas. Institute, 1998.
3. McFarland, W. F., R. J. Kabat, and R. A. Krammes. Comparison of Con-
Further support of implementation of these findings will be aided by tracting Strategies for Reducing Project Construction Time. Final Report.
additional research in the following areas. FHWA/ TX-94/1310-1F. Texas Transportation Institute, 1994.
4. Daniels, G., D. R. Ellis, and W. R. Stockton. Techniques for Manually
Estimating Road User Costs Associated with Construction Projects.
Field Testing of the RUC Tables Texas Transportation Institute, 1999.
5. Special Report 209: Highway Capacity Manual, 3rd ed. TRB, National
Research Council, Washington, D.C., 1994.
An evaluation of the validity and usefulness of the tabular format and
6. Microcomputer Evaluation of Highway User Benefits. Final Report for
the RUC values themselves should be conducted using actual field NCHRP, Project 7-12. Texas Transportation Institute, 1993.
cases. The tables were developed using typical cross sections and 7. Introduction to Urban Travel Demand Forecasting. National Highway
traffic operations data, and to ascertain the compatibility of these Institute Course Number 15254. U.S. Department of Transportation,
assumptions with actual field situations would be important. Several Washington, D.C. http://www.nhi.fhwa.dot.gov/
8. McFarland, W. F., et al. MicroBENCOST User’s Manual—Version 1.0.
case studies could be identified, and a comparison could be made of
Prepared for NCHRP, Project 7-12. Texas Transportation Institute,
table values with MBC computer runs using actual field conditions. 1993.
This process would provide an assessment of the soundness of the 9. Barton, R. Highway User Cost Tables: A Simplified Method of Estimat-
table values. ing User Cost Savings for Highway Improvements. Research and Devel-
opment Council, Transportation Association of Canada, Ottawa, Ontario,
1993.
10. Gaj, S. J. Lane Rental: An Innovative Contracting Practice. TR News,
Use of MBC for Category III and IV Projects No. 162, Sept.–Oct. 1992, pp. 7–9.
A vast array of input assumptions exists, along with an infinite com-
bination of design parameters and operational conditions. Considera- Publication of this paper sponsored by Committee on Transportation Economics.

You might also like