You are on page 1of 9

Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

PLANNING, CONTROL AND OPTIMIZATION OF EPB TBM


TUNNELING OPERATIONS IN URBAN AREAS.
A. Mignini
Amberg Engineering, Zurich, Switzerland.

ABSTRACT: This paper provides an overview on planning, control and optimization of EPB TBM
tunnelling operations in urban areas in diverse soil conditions. The extensive experience of the author
in dealing with diverse project conditions and environment around the world, are used as the basis to
provide basic guidelines to specialist contractors and consultants involved with detailed planning and
monitoring of metro projects worldwide. A dedicated TBM Integrated Program approach together
with a thorough Excavation Working Procedure, Monitoring Plan and Back-Analysis are the key
tools to successfully plan and perform TBM operations and ground deformation control.

1 INTRODUCTION The entire process usually happens as the


result of different international practices and
Much has been written on EPB tunnelling experiences, bringing together an heterogeneous
operations in urban areas, however this is an temporary association of local and international
opportunity for the author to expose and share organizations, competencies and talents with
some interesting observations and conclusions different backgrounds and objectives.
matured over his past and current experiences in Experience tells how difficult it is to find a
this growing and challenging discipline of balance and a proper path through which make
underground civil engineering. all parties involved progress in a coordinated,
The aim of this paper is to recap on some key efficient and safe manner.
aspects related with the implementation of The result is usually frequent reviews of
complex EPB tunnelling operations in urban program and budget forecast, with design
areas, with the aim to provide additional value changes and recovery or acceleration measures
to established international best practices. pushing people and organizations up to their
limits and sometimes beyond.
1.1 The International Practice
Nowadays the successful implementation of 1.2 The Network Logic
mechanized tunnelling operations are very much The process described in the previous
dependent on many factors such as contractor paragraph creates over the life of a project, from
experience and organization, tender and contract its inception to completion, a sort of network
framework, design approach and standard, made of links at many levels, that keeps
country infrastructures (transportation network, growing with the project till its saturation.
telecommunications, information technology, This is the moment when, after a significant
energy grid), local culture and market practice, period of small adjustments, a major and
working and site conditions, geology and other irreversible change of the network status takes
social and environmental factors. place (Network Theory).
1
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

In standard international practice (see Figure (activities on the CP have 0 float). A project can
1) the project is organized into areas of work, have several, parallel, near critical paths.
phases and activities according to a hierarchical When it comes to TBM tunnelling,
and incremental decomposition of its main scheduling is apparently more intuitive and easy
components that form a sort of tree structure to understand as usual practice is to have a
named Work Breakdown Structure (WBS). Linear Time-Chainage Schedule (see Figure 4).
Input Process Output
WBS Codes: ‐ Early Start ‐ Bar Chart (Gantt)
‐ Engineering ‐ Est'd Duration ‐ CPM (Pertt‐AoA)
‐ Procurement ‐ Logical Links ‐ S‐Curve
‐ Construction ‐ Constraints
Work/Phase/Task Network Diagram Baseline Program
Figure 1. Scheduling Technique by WBS Network CPM.

According to standard project management


scheduling technique it s possible to use links
and constraints to create and visualize a network
of activities in form of bar chart project
Figure 4. Example of Linear Diagram for Delhi Metro
schedule (Gantt Chart, see Figure 2). Ph.II Tender Program BC-16 (A.Mignini, 2007).

What is usually difficult to measure in this


type of diagram is the critical path of the overall
Network, which is made of other project
networks and critical paths such as TBM
procurement & commissioning, construction of
preliminary and preparatory works, interfacing
underground structures such as stations and
shafts, energy and water supply, etc.
Following are illustrated the main planning
and control activities and tools to make best use
of the Project Network resources, technology
Figure 2. Example of WBS-Gantt Chart (Wikipedia). and links available in order to minimize the
impact of tunnelling operations into the project
The shortest sequence represents the so called and affected environment.
Critical Path (CP) and the technique to identify
it is called Critical Path Method (CPM) (see
2 TBM INTEGRATED PROGRAM - TIP

A dedicated TBM Integrated Program (TIP)


for construction is proposed in this paper as a
combination of:
• CPM Scheduling
• Linear Timeline
• Contract Key Dates
• Production S-Curve
The preparation of TIP is as illustrated in the
following sections.
Figure 3).
2.1 Linear Timeline
Figure 3. Example of AoN Pert Diagram (Wikipedia).
The Timeline shall show a linear
Any delay of an activity on the CP directly representation of the line to build including the
impacts the planned project completion date following information:
X-Axis indicating:
2
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

• Chainage, length, slope and method of • TBM Assembly/Launching Shaft Detailed


tunnelling of each section Design
• Stations and Shafts (chainage, length and • Industrial Area Detailed Design and
method of construction) Technical Specifications
• Geological profile and water table • Precast Lining Detailed Design and
• Location and soil strata of relevant Technical Specifications
geological boreholes • Precast Factory Technical Specifications
• Location and code of relevant • Contract Documents for:
instrumented monitoring sections o Providers
• Construction risks/hazards o Sub-contractors
• Sensitive buildings and structures o Personnel
Y-Axis downward Timeline indicating:
Preliminary Works 2.3 Procurement
• TBM Assembly Key dates for the following activities may be
• TBM T&C shown separately:
• TBM Entry Shaft Civil Works
• Industrial Area Civil Works & • TBM Fabrication & Delivery
• TBM Transportation
Installations
• TBM Personnel (T&C, O&M)
• Operations:
o Launching
o Excavation 2.4 S-Curve
o Maintenance Stoppages
Weekly TBM S-Curve (Y-Axis = cumulative
o Crossings through Stations/Shafts
meters/rings of tunnel; X-Axis = cumulative
o Dismantling and Retrieval
week) can be also shown with indicated the
Interfering Preparatory and Underground planned stoppages for maintenance and
Works such as: intervention to the TBM and its back-up tunnel
• Utilities and Traffic installations.
• Stations Once completed, the TIP will look something
• Shafts like the example one below (see Figure 5).
• Cross Passages
• Trackwork
Project Baseline Milestones and Key Dates
such as:
• Interfacing Stations and Shafts Basic
Structure Completion
• System Wide Contractors Access and
Delivery Dates
• Trackwork Access and Delivery Dates
• Testing & Commissioning
Critical activities in red colour that lie on the
Baseline Program Critical Path. Figure 5. Example of TIP - Metro Delhi Ph.II BC-16
Tender Program (A.Mignini, Torno Int., 2007).
2.2 Engineering
3 TBM WORKING PROCEDURE - TWP
Key dates for the following activities may be
shown separately: Before start of TBM operations, it is
• TBM Manufacturer Specifications paramount to have an approved TBM Working
(Shield, Back-up cars and trains) Procedure (TWP) for each section of the tunnels
• TBM Consumption Analysis (Tools, to be excavated, covering the following topics:
Spares, Energy, Lubs) • Alignment Geometry
• TBM Delivery Route/Transport Plan • Geological Appraisal
3
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

• Ground Improvement • Existing Underground Structures


• Affected buildings, structures and services (See Figure 6).
• Wells & Boreholes
• Cross and Back-Analysis results
• TBM Advance Parameters
• TBM Work Schedule
• TBM Working Parameters
• Risk Analysis
• Monitoring
• Preventative and Contingency Measures
The document shall be completed by the
following attachments:
• Tunnel Alignment (Horizontal and Vertical)
• Train Gabarit (TBM Tolerances)
• Longitudinal Profile (Buildings, Geology, Figure 6. Example of Tunnel Profile - Sabadell Metro
Geometry, Main Parameters and other PP.KK.11+300-700 (Amberg Infraestructuras, 2011).
relevant info)
• Area of influence of affected Buildings,
Structures, Services 3.2 Face Stability and Pressure
• Inventory of Boreholes and Wells to be In order to guarantee adequate face stability
sealed off and ground deformation control due to volume
• TBM Daily Work Schedule loss during excavation, it is paramount to carry
• Exit/Entry Shaft/Station Procedure/Method out a thorough assessment of geotechnical
• Ground Treatment parameters along the alignment to be adopted in
• Cutterhead Intervention Procedure the analytical and numerical calculations
(Hyperbaric and Atmospheric) according to experience and good practice (See
• Face Stability and Recommended Working figure 7).
Pressure Calculations
• Monitoring Instrumentation Plan and
Procedure (Ground, Surface, Buildings,
Structures and Services)
• Contingency Plan
• Emergency & Evacuation Plan
• Excavated Material and Traffic Management
Plan (Handling and Disposal off Site)
Once excavation started, special attention
shall be given to the following: Figure 7. Example of Geotechnical Parameters
Assessment - Metro São Paulo Line 5 Extension Lot 3
3.1 Tunnel Profile (Amberg Engineering, 2013).
It is worth mentioning that pressure
In order to properly monitor a TBM advance calculation can depend very much on geological
it is necessary to have a complete and clear parameters as well as on water table readings in
representation of the tunnel drive and the case of ground permeability at tunnel face.
surrounding geological and affected urban It is therefore highly recommended to install
environment both on plan and longitudinal adequate number of piezometers at key
vertical profile showing the following: locations and take regular readings in order to
• Geological Strata and Water Table duly review the reference pressure before
• Boreholes Location starting TBM excavation in closed mode.
• Tunnel Chainage, Overburden and Ring Below (see Figure 8) is an example of face
Numbering stability analysis and pressure calculations
• Affected Buildings (Location, Dimension, carried out according to the silo theory Limit
Tipology and Sensitivity Colour Coding) State Equilibrium (Anagnostu and Kovari,
• Viability 1996).
4
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

3.3 TBM Pilot Instruction Sheet (PIS)


For each homogenous section of tunnel to be
excavated (in terms of geology and face
pressure), it is paramount to define reference,
warning and alert values for the TBM advance
main parameters such as:
• Recommended Earth Pressure Sensor 1 (P1)
• Expected Material Density in the Excavation
Chamber
• Collapse Pressure in Shield Sensors (If
installed)
• Recommended Grout Injection Pressure
• Theoretical Grout Volume to be injected to
fill the Annular Gap
• Soil Conditioning: FIR (incl.% of foam
agent), FER
• Penetration Rate and Revolutions of
Cutterhead per Minute
• Theoretical Weight of Material to be
Extracted
Below is an example of Pilot Instruction
Sheet (PIS) (see Figure 9).
Figure 8. Face Stability & Pressure Calculation – Sabadell
Metro (Amberg Infraestructuras, 2013).

Another key aspect is to carry out a


numerical modelling of the ground in the critical
areas where even limited ground deformation
can hinder the integrity or serviceability of
existing sensitive buildings, structures and
services.
In this regard it is highly recommended to
calibre the model especially in terms of
deformation modulus of the ground, in order to
simulate as close as possible the real ground
behaviour through a numerical iterative
calculation.
In order to do so it is paramount to install,
possibly in the very first section of tunnel and
within a non-sensitive area, as many monitoring
sections as necessary fully instrumented with
ground instrumentation and surface levelling Figure 9. Example of PIS - Sabadell Metro
points. (Amberg Infraestructuras, 2011).
These sections will allow to carry out a cross
and back-analysis between EPB mode
excavation parameters and ground behaviour 4 RISK ASSESSMENT
and as a consequence to review and optimize
the numerical model and recommended advance A duly compiled Risk Register can be an
parameters, particularly the face pressure so to effective tool to identify, analyse, assess and
achieve an optimum control of excavation (see monitor risk according to its nature, likelihood
paragraph 6). of occurrence and impact onto the project.
In EPB Tunnelling operations in urban areas,
risk is typically related with the effects of the
excavation onto the surrounding environment,
5
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

particularly where the tunnel bore is close to in place in order to mitigate potential risk and
sensitive buildings, structures and vital services hazards as part of a successful Risk
to the day to day life of the city. Management.
Where the nature and extent of information
available is not adequate to carry out a
quantitative assessment of the likelihood and 5 MONITORING
effects of the excavation it is highly
recommended to adopt a qualitative and statistic This is a key activity to succeed in the control
approach according to local and international of EPB TBM Tunnelling operations in sensitive
experience and best practice. urban areas.
In this regard a significant turning point and Though TBM excavation parameters can be
contribution to this approach was provided by available and graphed on screen in real time
the Oporto Metro experience as thoroughly with a refresh of every 10 sec, the effects of the
illustrated in recent scientific literature excavation onto the surrounding environment
(Guglielmetti et al., 2007) (see Figure 10). are subjected to the uploading and interpretation
Nowadays Risk Assessment is part of of ground and surface instrumentation readings
international tunnelling practice and at intervals of a few hours.
recommendations and guidelines in this regard This evident and excessive time gap between
can be easily sourced from both scientific a real time TBM excavation and the ground and
literature and associations such as the ITA. surface monitoring system readings requires
additional care particularly in the control of face
stability, tail gap filling and material extraction.
This is why it is so important to have a duly
compiled TIP supported by accurate face and
grout injection pressure calculations as well as
soil conditioning laboratory testing and
extracted material control through duly
calibrated scales installed onto the conveyor
belt.
The author accumulated significant
experience in this regard particularly in difficult
soft soil conditions in highly populated areas,
such as the Airport Link section of Metro
Barcelona Line 9 (A. Mignini, 2008).
In this project it was possible to install 4
control sections in the very first 500m tunnel
drive, which gave the opportunity to monitor
and relate settlements induced by a 9.4m diam.
HK EPBM tunnelling through the submersed
fine silty sands (Ql2) and clayey silts (Ql3) of
recent deltaic deposit of Llobregat River.
Geo-mechanical parameters where duly
assessed and so it was the face pressure
calculation.
However, it resulted very important to
improve upon soil conditioning and face
pressure control due to high water content in the
Figure 10. Example of Risk Register – Level 1 & 2 excavated material.
(Guglielmetti et al., 2007). Moreover settlement control required a very
However, adequate preventative and tight control of grout injection through the tail
contingency measures such as excavation real void and the extensive use of bentonite injection
time monitoring (see par. 5) and eventually through the shield to reduce volume loss related
ground improvement or special treatments and with the shield conicity (see Figure 11).
interventions to existing structures, shall be put
6
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

Figure 11. Tail Void Grout and Bentonite Injection –


Metro Line 9 Barcelona (A.Mignini et al., 2008).

Figure 14. TBM Shield Induced Settlement Profile –


All this measures resulted into ground Metro Line 9 Barcelona (A.Mignini et al., 2008).
settlement reduction below acceptable values
and an outstanding advance performance of first
and eventually second TBM, with a sequence of
world record productions of up to 1026m in
straight 30 days, including am unexcavated
station box crossing (see Figures 11 and 12).

Figure 15. TBM Shield Induced Settlement Trough –


Metro Line 9 Barcelona (A.Mignini et al., 2008).

Figure 12. Face Pressure vs TBM Advance –


Metro Line 9 Barcelona (A.Mignini et al., 2008).

Figure 13. Ring Production Cycle – Metro Line 9


Barcelona (A.Mignini et al., 2008).

With regard to settlement control the above


measures resulted in a substantial reduction of
volume loss within acceptable limit as detected Figure 16. Volume Loss Reduction – Metro Line 9
by the instrumented control sections before, Barcelona (A.Mignini et al., 2008).
during and after TBM Shield passed by (see
Figures 14, 15 and 16).
7
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

6 BACK-ANALYSIS At the time of tender design, deformation


modulus of both strata was underestimated in
Once tunnelling operations are under way the numerical model adopted, whereas
and a section of tunnel bore is complete, which permeability was overestimated, thus resulting
is representative of part or whole of the geology into TBM specifications which requested more
yet to be encountered, it is highly recommended thrust than torque, whereas the machine
to recompile and graph all major TBM eventually resulted short of the latter.
operating parameters, as well as carry out a The above resulted into a difficult first
thorough back-analysis of ground behaviour section as shown in the summary graph below,
through 2D or 3D numerical modelling. representing average TBM advance and
This activity can usually be carried out operational parameters for Sabadell Metro first
during shafts or stations crossings and allows to drive (see Figure 18).
consolidate the experience and learning curve
gained during and upon completion of a tunnel
bore, by review of pressure calculations and
tunnel excavation procedure for the section(s)
yet to be excavated.
The author gained substantial experience in
this regard through several metro projects,
where EPB tunnelling operations learning curve
highly benefited from back-analysis.
In this regard Sabadell Metro can be taken as
a very good example of learning curve, where a
6.85m HK EPB recently terminated its final
drive for the second twin tunnel after hitting an
outstanding production of aprox. 830m in a
straight month and with record low ground Figure 18. Summary TBM Av. Parameters Sec.1 –
settlement. Sabadell Metro (Amberg Infraestructuras, 2010).
Geology in this project is characterized by a
very competent and low permeable Quaternary A back-analysis was eventually carried out in
formation (Middle-Late Pleistocenium) formed a critical point of this first section (PK 13+506),
by a well cemented compound of breccia into a that allowed to calibre the 3D FLAC numerical
silty-sandy matrix, overlaying a softer stratum model by adapting the theoretical Gaussian
of Miocene Neogenic sandy compound with a distribution best-fit to the monitored settlement
lower grade of compaction. Water can be trough (Peck, 1969) by increasing the
encountered through the contact between upper deformation modulus E up to 15 times the one
Quaternary and lower Miocene strata (see assumed at design stage.
Figure 17). However, the resulting trough was still far
from approximating the monitored empirical
trough (see Figure 19).

Figure 19. 3D FLAC Best-Fit – Sabadell Metro PK


13+506 (Amberg Infraestructuras, 2010).
Figure 17. Geology Back-Analysis Section – Sabadell
Metro PK 13+506 (Amberg Infraestructuras, 2010).

8
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.

Eventually a 2D Plaxis model was adopted, face pressure with great benefit to TBM
which gave a very close best-fit with a modulus excavation performance (see Figure 22).
37 times higher than assumed at design stage
(see Figure 20).

Figure 22. TBM Excavation Performance Summary –


Figure 20. FLAC - PLAXIS Best-Fit – Sabadell Metro Sabadell Tunnel 1(Amberg Infraestructuras, 2011).
PK 13+506 (Amberg Infraestructuras, 2010).

The result of the back-analysis allowed to 7 CONCLUSION


prove feasibility of atmospheric intervention in
specific locations along the second tunnel yet to Planning, control and optimization of EPB
be excavated, through a duly calibrated 3D tunnelling operations in urban areas require
FLAC numerical model. specialist experience and competence together
Following are the results of the calculations with a holistic and coordinated technical and
carried out by Amberg (see Figure 21). managerial approach in order to successfully
carry out and complete each phase of the
process.

ACKNOWLEDGEMENTS

I would like to thank all those colleagues and


professionals I met during many years of
exciting projects around the world, who gave
me the opportunity to learn , share and improve
upon my work experience and understanding of
mechanized tunnelling operations.

REFERENCES

Anagnostou; Kovári, 1996. Face stability in slurry and


EPB shield tunnelling, Balkema, Rotterdam.
Guglielmetti, V.; Grasso, P.; Mahtab, A.; Xu, S. 2007.
Mechanized Tunnelling in Urban Areas. T. & F.
Mignini, A 2008. Surface Settlement Minimization in Soft
Soil when Excavating with an EPB Shield. Barcelona
Metro Line 9, Mas Blau – San Cosme. EPB Tunnels.
UPC, Barcelona.
Figure 21. 3D FLAC PK 11+550 – Sabadell Metro PK Mignini, A 2013. EPB Tunnelling Operations in Soft &
13+506 (Amberg Infraestructuras, 2008). Hard Soil in Urban Areas. Tunnel & Mining
International Conference Lima, Perú.
Peck, R.B. 1969. Deep excavations and tunnelling in soft
Back-analysis and a better soil conditioning ground. Proc. 7th Int. Conf. Soil Mechanics and
allowed to substantially reduce the operating Foundation Engineering, Mexico City, State of the Art
Volume, 225-290.
9

You might also like