Professional Documents
Culture Documents
ABSTRACT: This paper provides an overview on planning, control and optimization of EPB TBM
tunnelling operations in urban areas in diverse soil conditions. The extensive experience of the author
in dealing with diverse project conditions and environment around the world, are used as the basis to
provide basic guidelines to specialist contractors and consultants involved with detailed planning and
monitoring of metro projects worldwide. A dedicated TBM Integrated Program approach together
with a thorough Excavation Working Procedure, Monitoring Plan and Back-Analysis are the key
tools to successfully plan and perform TBM operations and ground deformation control.
In standard international practice (see Figure (activities on the CP have 0 float). A project can
1) the project is organized into areas of work, have several, parallel, near critical paths.
phases and activities according to a hierarchical When it comes to TBM tunnelling,
and incremental decomposition of its main scheduling is apparently more intuitive and easy
components that form a sort of tree structure to understand as usual practice is to have a
named Work Breakdown Structure (WBS). Linear Time-Chainage Schedule (see Figure 4).
Input Process Output
WBS Codes: ‐ Early Start ‐ Bar Chart (Gantt)
‐ Engineering ‐ Est'd Duration ‐ CPM (Pertt‐AoA)
‐ Procurement ‐ Logical Links ‐ S‐Curve
‐ Construction ‐ Constraints
Work/Phase/Task Network Diagram Baseline Program
Figure 1. Scheduling Technique by WBS Network CPM.
particularly where the tunnel bore is close to in place in order to mitigate potential risk and
sensitive buildings, structures and vital services hazards as part of a successful Risk
to the day to day life of the city. Management.
Where the nature and extent of information
available is not adequate to carry out a
quantitative assessment of the likelihood and 5 MONITORING
effects of the excavation it is highly
recommended to adopt a qualitative and statistic This is a key activity to succeed in the control
approach according to local and international of EPB TBM Tunnelling operations in sensitive
experience and best practice. urban areas.
In this regard a significant turning point and Though TBM excavation parameters can be
contribution to this approach was provided by available and graphed on screen in real time
the Oporto Metro experience as thoroughly with a refresh of every 10 sec, the effects of the
illustrated in recent scientific literature excavation onto the surrounding environment
(Guglielmetti et al., 2007) (see Figure 10). are subjected to the uploading and interpretation
Nowadays Risk Assessment is part of of ground and surface instrumentation readings
international tunnelling practice and at intervals of a few hours.
recommendations and guidelines in this regard This evident and excessive time gap between
can be easily sourced from both scientific a real time TBM excavation and the ground and
literature and associations such as the ITA. surface monitoring system readings requires
additional care particularly in the control of face
stability, tail gap filling and material extraction.
This is why it is so important to have a duly
compiled TIP supported by accurate face and
grout injection pressure calculations as well as
soil conditioning laboratory testing and
extracted material control through duly
calibrated scales installed onto the conveyor
belt.
The author accumulated significant
experience in this regard particularly in difficult
soft soil conditions in highly populated areas,
such as the Airport Link section of Metro
Barcelona Line 9 (A. Mignini, 2008).
In this project it was possible to install 4
control sections in the very first 500m tunnel
drive, which gave the opportunity to monitor
and relate settlements induced by a 9.4m diam.
HK EPBM tunnelling through the submersed
fine silty sands (Ql2) and clayey silts (Ql3) of
recent deltaic deposit of Llobregat River.
Geo-mechanical parameters where duly
assessed and so it was the face pressure
calculation.
However, it resulted very important to
improve upon soil conditioning and face
pressure control due to high water content in the
Figure 10. Example of Risk Register – Level 1 & 2 excavated material.
(Guglielmetti et al., 2007). Moreover settlement control required a very
However, adequate preventative and tight control of grout injection through the tail
contingency measures such as excavation real void and the extensive use of bentonite injection
time monitoring (see par. 5) and eventually through the shield to reduce volume loss related
ground improvement or special treatments and with the shield conicity (see Figure 11).
interventions to existing structures, shall be put
6
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
8
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Eventually a 2D Plaxis model was adopted, face pressure with great benefit to TBM
which gave a very close best-fit with a modulus excavation performance (see Figure 22).
37 times higher than assumed at design stage
(see Figure 20).
ACKNOWLEDGEMENTS
REFERENCES