TBM Operations

Hard Soil + Water


Working Parameters:
Advance Rate
Mechanical Parameters
Earth Pressure
Soil Conditioning
Tail Shield Grout Injection
Hard Soil
Hard Soil
Hard Soil
Hard Soil
Hard Soil
Average Rates Progression
AVERAGE ADVANCE WORKING DAYS
RATES DURATION
WORKING DAYS
WITH STOPPAGES W/O STOPPAGES

PLANNED REAL PLANNED REAL


TUNNEL PK/LENGTH

78.0 82.0 78.0 54.0 50.0


SECTION 1 575.02

AV.AD. m/d 7.0 7.4 10.6 11.5

31.0 47.0 31.0 39.0 29.0


SECTION 2 515.90

AV.AD. m/d 11.0 16.6 13.2 17.8

61.0 79.0 61.0 58.0 48.0


SECTION 3 1,009.83

AV.AD. m/d 12.8 16.6 17.4 21.0

40.0 54.0 40.0 46.0 38.0


SECTION 4 821.81

AV.AD. m/d 15.2 20.5 17.9 21.6

2,922.56 11.15 13.92 14.84 17.71


TOTAL m TOTAL AV. AD.
210.00
TOTAL d