Professional Documents
Culture Documents
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 1 of 8 200-345-65925
INSTALLATION MANUAL
C:\Dokumente und Einstellungen\Harald Hof\Eigene Dateien\Aufträge Job\O&M\Montage+Bedienungsanleitung\WBHD\200-345-65925 WBHD-DT-XXX-ALL INSTALLATION MANUAL.doc
WHEEL BRAKES
WBHD-DT-060-ALL
HILLMAR WORKS HAVE A FULLY REGISTERED ISO 9001: 2008 QUALITY ASSURANCE PROGRAMME (QCB #01-1525)
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels
Sheet Number:
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 2 of 8 200-345-65925
INDEX
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels
Sheet Number:
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 3 of 8 200-345-65925
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels
Sheet Number:
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 4 of 8 200-345-65925
WHEEL
BRAKE DT
.
WHEEL
3.4 CENTERING THE BRAKE
6-8mm
1. Once the bracket is mounted make sure
the brake is centered.
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels
Sheet Number:
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 5 of 8 200-345-65925
CAUTION: Wheel Brake comes in released position from factory. Do not pressurize the cylinder prior
to brake adjustment.
1. Piston rod
Nominal released position Piston Rod Extension = 23mm
Total stroke = 16mm of Rod Movement
2. Shoe clearance
Nominal brake clearance = 0.5 mm per side (installation clearance)
Maximum brake clearance = 1.5 mm per side (after shoe wear)
Note: Wheel brake must be readjusted at this clearance
3. Maximum adjustment
Pads must be replaced when lining thickness t< 5.5mm.
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels
Sheet Number:
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 6 of 8 200-345-65925
installation.
NOTE: Once the Brake is mounted to 0.5 mm gap on
GUIDE ROLLER MUST each side of brake pad, adjust guide rollers by
PROTRUDE BEYOND PAD threading in the adjuster bolt so that there is
minimal equal force acting on both the guide
rollers to keep float on the shoes.
WHEEL
FLANGE
CAUTION: Do not tighten the bolt all the way
in, it may damage the guide roller assembly
ROLLER
PAD
0.5mm
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels
Sheet Number:
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 7 of 8 200-345-65925
CAUTION
Ensure that the wheel brake pad gap adjustment
procedure has been completed prior to proximity
switch installation to avoid any physical damage
to the switch.
SWEEPER
ASSEMBLY
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels
Sheet Number:
WHEEL BRAKES
Hillmar
Hillmar Industries Ltd.
WBHD-DT-030-060-090-120-ALL
INSTALLATION MANUAL
Job Number:
275-213-01649
7371 Vantage W ay PARTS & SVC Form Number: Rev:
Delta, BC V4G 1C9 ENGLISH
P:604 946-7115 F:604 946-0329
info@hillmar.com www.hillmar.com Company / Project Reference: Date: Page: Document Package No.: Rev:
Konecranes / PacNat RMG 16JAN11 8 of 8 200-345-65925
F
E
*MIN. 75mm
A *D
*NOTES:
1) IF WHEEL LATERAL MOVEMENT IS > ±12mm, PLEASE CONTACT HILLMAR.
2) WHEEL SURFACES MUST BE FREE FROM CONTAMINANTS TO PROLONG PAD LIFE.
3) ALL DIMENSIONS IN mm
4) WHEEL WIDTH TOLERANCE MUST BE WITHIN ± 1 mm OF NOMINAL WHEEL WIDTH
- PARALLELISM
- FLATNESS
Storm Brakes • Thruster Disc Brakes • Thrusters • Industrial Disc Brakes • Hydraulic Power Units • Cable Reels