PRELIMINARY

2017.07.25

25100 31635 21367


STAGE 1 LAUNCHING SHAFT RECEIVING SHAFT

1. SHAFT EXCAVATION.
NORTH SOUTH MRT LINE

STAGE 2

THRUST GUIDE RAIL


2. THRUST WALL INSTALLATION.
PIPE ROOF LAUNCHING THRUST
PLATFORM MACHINE
THRUST WALL THRUST WALL 3. LAUNCHING/RECEIVING SHAFT BASE INSTALLATION.

4. PIPE ROOF (SIDE LAYER) INSTALLATION (SEE DETAIL 1).

5. BACKUP GROUTING AROUND PIPE ROOF.


LAUNCHING BASE CONCRETE
6. HORIZONTAL BORING FOR PC (PULLING CABLE) WIRE
HORIZONTAL BORING INSTALLATION.

BASE CONCRETE
STAGE 3

7. PIPE ROOF (ROOF LAYER) INSTALLATION (SEE DETAIL 1).


THRUST WALL
THRUST WALL
8. BACKUP GROUTING AROUND PIPE ROOF.
THRUST
MACHINE
9. HORIZONTAL BORING FOR PC (PULLING CABLE) WIRE
INSTALLATION.

11. PILOT TUNNEL MINING, GUIDE INSTALLATION INSIDE


PILOT TUNNEL (SEE DETAIL 1).

GUIDE TUNNEL