Professional Documents
Culture Documents
Perencanaan Drainase
Analisa Hidrologi
Pembahasan
Tahun
Bulan
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Januari
Februari
Maret
117
53
76
115
60
52
58
78
55
27
25
94
R
R
R
84
103
76
70
51
54
110
85
140
80
84
25
45
85
35
43
13
54
46
60
70
Sta. Hujan Socah
April 37 53 70 15 64 58 73 25 67 32 31 58
Mei 40 60 55 20 32 60 19 45 60 41 34 33
Juni 10 40 35 0 55 0 70 51 52 24 4 8
Juli 0 0 0 20 0 0 16 0 5 67 5 32
Agustus 0 0 0 R 30 0 0 5 5 61 5 0
September 0 0 0 R 2 0 27 0 5 82 9 25
Oktober 54 0 1 R 0 0 0 65 20 180 60 43
Nopember 34 54 24 25 51 0 20 43 45 71 53 22
Desember 60 41 63 0 80 121 104 78 58 125 23 23
MAKS 117 115 78 94 80 121 104 140 84 180 60 70
Sta. Hujan
Tahun
Bulan
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Januari R 169 49 37 75 0 0 84 27 28 0 6
Labang
Februari R 40 49 60 102 0 0 54 80 72 0 72
Maret 31 80 77 0 41 99 0 69 35 63 34 62
April 46 18 17 0 0 67 R 37 43 48 67 30
Mei 47 30 30 R 0 42 10 13 31 44 44 54
Juni 15 0 0 0 75 0 25 0 51 47 47 34
Juli 0 0 0 0 0 0 0 0 0 29 29 25
Agustus 0 0 0 0 0 0 0 0 0 25 32 53
September 0 0 0 0 0 0 0 0 0 24 22 24
Oktober 69 0 10 0 95 0 66 86 3 67 12 67
Nopember 20 17 25 0 21 5 56 27 11 58 31 58
Desember 68 64 35 0 21 0 42 69 17 39 39 39
MAKS 69 169 77 60 102 99 66 86 80 72 67 72
Tahun
Bulan
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Januari 96 130 52 0 15 55 5 5 7 7 5 8
AN SAL. KIRI
DAERAH ALIR DAERAH
ALIR ALIRAN DAERAH ALIR
AN SAL. KAN
SAL. TEN AN DAERAH AN
GAH
GAH SAL. TEN
5% 5% 5%
2% 5% 5%
5% 5%
2m 7m 2m 5m 2m 7m 2m
Gambar. Pembagian Daerah Pengaliran pada perhitungan t0
Perencanaan Drainase
0 Analisa Hidrolika
0.70
Pembahasan
Tipikal Saluran
0.90 Tepi
Perencanaan Drainase
Analisa Hidrolika
Pembahasan
Volume Galian
PERMUK
AAN TANA
H EKSISTING
48247746,44 m3
LUAS PENAMPANG GALIAN
Volume Timbunan
LAPISAN PERKERASAN 160462,395 m3
PERMUKAAN TANAH RENCANA
Sal. Precast
12124 buah
Saluran Tengah
0.50
LASTON MS744 10cm
BATU PECAH KELAS B 20cm
2.50
SIRTU PITRUN KELAS A 20cm
5m 8m 5m Marka Jalan
0.12 m 1396,70 m2
Analisa Anggaran Biaya
Biaya Konstruksi
Pembahasan
UPAH PEKERJA
No.
No. Uraian
Uraian Kode
Kode Satuan
Satuan Harga
Harga (Rp)
(Rp) Keterangan
Keterangan
11 Pasir
Pasir Beton
Beton (Kasar)
(Kasar) M01a
M01a m3
m3 151525
151525
22 Pasir
Pasir Pasang
Pasang m3
m3 151525
151525
33 Pasir
Pasir Urug
Urug M01d
M01d m3
m3 120175
120175
Upah/Hari 44 Agregat
Agregat Kasar
Kasar M03
M03 m3
m3 167200
167200
No. Uraian Satuan Upah/Jam 55 Agregat
(Rp) Agregat Halus
Halus M04
M04 m3
m3 161975
161975
66 Filler
Filler M05
M05 Kg
Kg 1568
1568
1 Mandor O.H 85000 10625 77 Kayu
Kayu meranti
meranti bekisting
bekisting m3
m3 1966500
1966500
88 Kayu
Kayu Kamper
Kamper balok
balok 3/5
3/5 m3
m3 5700000
5700000
2 Operator 125000 15625
99 Plywood
Plywood tebal
tebal 99 mm
mm lembar
lembar 84170
84170
3 Pembantu Operator O.H 75000 9375 10
10 Paku
Paku Usuk
Usuk Kg
Kg 15675
15675
11
11 Minyak
Minyak Bekisting
Bekisting ltr
ltr 6270
6270
4 Supir 75000 9375 12 Thermoplastic Kg 21898
12 Thermoplastic Kg 21898
5 Pembantu Supir O.H 67500 8437.5 13 Glass
Glass Beed
Beed Kg
Kg 40945
13 40945
14
14 Batu
Batu Kali
Kali m3
m3 125400
125400
6 Pekerja/Pembantu Tukang O.H 70000 8750 15 Batu
15 Batu Pecah
Pecah Mesin
Mesin 1/2cm
1/2cm m3
m3 271700
271700
7 Tukang Besi O.H 75000 9375 16
16 Batu
Batu Pecah
Pecah Mesin
Mesin 2/3cm
2/3cm m3
m3 175085
175085
17
17 Batu
Batu Pecah
Pecah Mesin
Mesin 0,5/1cm
0,5/1cm m3
m3 155705
155705
8 Kepala Tukang Besi O.H 80000 10000 18 Batu
18 Batu Krikil
Krikil Beton
Beton m3
m3 130625
130625
9 Kepala Tukang Batu O.H 80000 10000 19
19 Tanah
Tanah Urug
Urug m3
m3 120175
120175
20
20 Sirtu
Sirtu M16
M16 m3
m3 130625
130625
10 Tukang Batu O.H 75000 9375 21 Aspal Curah Kg 7315
21 Aspal Curah Kg 7315
22 Tack Coat Liter 12540
HARGA
22 Tack Coat Liter 12540
23
23 Geotextile
Geotextile M30
M30 m2
m2 15200
15200
SEWA ALAT
24
24 Minyak
Minyak Tanah
Tanah liter
liter 8360
8360
BAHAN
25
25 Semen Portland (40kg)
Semen Portland (40kg) Zak
Zak 49685
49685
26
26 Air
Air (Biaya
(Biaya Air
Air Tawar)
Tawar) Liter
Liter 25
25
27
27 Besi
Besi Beton
Beton Kg
Kg 8645
8645
28
28 Kawat Beton
Kawat Beton Kg
Kg 15675
15675
29
29 U
U Gutter
Gutter U/1000/1000-2400
U/1000/1000-2400 Bh
Bh 2448435
2448435
30
30 U
U Gutter
Gutter U/1200/1200-2400
U/1200/1200-2400 Bh
Bh 2938122
2938122
31 U Gutter U/1500/1500-2400 Bh 3672652
No. Uraian Kode Satuan Harga (Rp) 31 U Gutter U/1500/1500-2400 Bh 3672652
32
32 Kayu
Kayu Meranti Bekisting
Meranti Bekisting m3
m3 1966500
1966500
1 Motor Grader 125-140 pk Jam 261250 33 Katu
33 Katu Kamper
Kamper Balok
Balok 3/5
3/5 m3
m3 5700000
5700000
2 Truck Tangki Air Hari 470250 34
34 Plywood 9mm
Plywood 9mm Lembar
Lembar 84170
84170
35 Paku Usuk Kg 15675
3 Walles Jam 100320 35 Paku Usuk Kg 15675
36
36 Minyak
Minyak Bekisting
Bekisting Liter
Liter 6270
6270
4 Asphalt Mixing Plant Jam 3762000 37
37 Box
Box Culvert
Culvert 1500X1500X1200
1500X1500X1200 Bh
Bh 6880000
6880000
5 Generator Set Unit 522500 38 Box
Box Culvert 2400x2400x1200
Culvert Bh 11257000
:http://esourcing.surabaya.go.id/profil/bor
Pipeline
38 2400x2400x1200 Bh 11257000
:http://esourcing.surabaya.go.id/profil/bor
BoralPipeline
39 Box Culvert 4500x2500x1200 Bh 17635000
Sumber
6 Wheel Loader 10-15 HP Jam 543400 39 Box Culvert 4500x2500x1200 Bh 17635000
Indonesia| |Sumber
40
40 Box
Box Culvert 4300x2500x1200
Culvert 4300x2500x1200 (t(t == 200mm)
200mm) Bh
Bh 15330000
15330000
PT.Boral
7 Dump Truck 8-10 m3 (5T) Jam 61750 41
41 U-Ditch
U-Ditch 600x600x1200
600x600x1200 Bh
Bh 1317000
1317000
al?page=5
al?page=5
42 U-Ditch 600x800x1200 Bh 1530000
PrecastIndonesia
8 Asphalt Finisher Jam 992750
dariPT.
42 U-Ditch 600x800x1200 Bh 1530000
43 U-Ditch
U-Ditch 800x800x1200 Bh 1591000
hargadari
9 Tandem Roller Jam 250800 43 800x800x1200 Bh 1591000
44 U-Ditch
U-Ditch 1000x1000x1000 Bh 1910000
Berdasarkanharga
44 1000x1000x1000 Bh 1910000
andPrecast
10 Pneumatic Tire Roller Jam 209000 45
45 U-Ditch
U-Ditch 1000x1000x1200 (t=150mm)
1000x1000x1200 (t=150mm) Bh
Bh 1602000
1602000
Berdasarkan
46 U-Ditch 1000x1500x1200 Bh 2646000
11 Alat Bantu Pembuatan Aspal Emulsi Unit 19000 46 U-Ditch 1000x1500x1200 Bh 2646000
and
47 U-Ditch 1000x1200x1200 Bh 2579500
47 U-Ditch 1000x1200x1200 Bh 2579500
12 Asphalt Spayer Jam 26125 48 U-Ditch 1200x1200x1200 Bh 2175000
48 U-Ditch 1200x1200x1200 Bh 2175000
13 Compessor 400 - 600 L/M Jam 88825
14 Excavator (6m3) Jam 123500
15 Vibrator Roller Jam 128250
16 BullDozer Jam 385695
17 Tandem Roller (min 5 jam) Jam 250800
Analisa Anggaran Biaya
Biaya Konstruksi
Pembahasan
Harga Satuan
No. Uraian Pekerjaan Volume Satuan Jumlah Harga
Pekrjaan
1 Pekerjaan Tanah
1.1 Pembersihan Lahan 407375.08 m2 Rp 32,655.28 Rp 13,302,948,117.17
1.2 Galian Tanah 48247746.44 m3 Rp 20,942.05 Rp 1,010,406,597,714.44
1.3 Timbunan Tanah 160462.395 m3 Rp 169,477.83 Rp 27,194,817,698.89
2 Perkerjaan Perkerasan
2.1 Lapis Permukaan (AC-WC) 71698.01 Ton Rp 880,342.93 Rp 63,118,836,431.59
2.2 Lapis Pondasi Atas (Agregat B) 40651.268 m3 Rp 310,309.67 Rp 12,614,481,491.62
2.3 Lapis Pondasi Bawah (Sirtu Pitrun Kelas B) 70433.8 m3 Rp 202,863.89 Rp 14,288,474,471.72
2.4 Perbaikan Tanah (Soil Improvement) 78656.34 m3 Rp 169,477.83 Rp 13,330,505,425.66
2.5 Lapis Resap Perekat (Prime Coat) 285162.55 liter Rp 13,113.47 Rp 3,739,471,528.36
2.6 Lapis Perekat (Tack Coat) 81475.016 liter Rp 12,925.99 Rp 1,053,145,242.07
3 Pekerjaan Drainase
3.1 Saluran Tepi (Batu Kali Belah) 13843.54 m3 Rp 621,358.21 Rp 8,601,797,234.46
3.2 Plesteran (1 pc : 4 ps) 69218 m2 Rp 48,904.86 Rp 3,385,096,779.45
3.3 Saluran Tengah (U-Ditch Precast) 12124 m' Rp 1,259,413.01 Rp 15,269,123,310.39
3.3 Gorong-Gorong Precast (1500 x 1500 x 1200) 176 m' Rp 6,358,625.70 Rp 1,119,118,122.87
Total Biaya Konstruksi
Rp. 1.312.858.711.150,-
4 Pekerjaan Pengaman Longsor
4.1 Dinding Penahan Beton (Tipe I) 198.2 m3 Rp 5,087,333.35 Rp 1,008,309,469.97
4.2 Dinding Penahan Batu Kali (Tipe II) 184.65 m3 Rp 621,358.21 Rp 114,733,793.48
4.3 Dinding Penahan Batu Kali (Tipe III) 4705.42 m3 Rp 621,358.21 Rp 2,923,751,348.50
5 Pekerjaan Minor
5.1 Marka Menerus (Solid) 1745.89 m2 Rp 648,099.51 Rp 1,131,510,457.88
Terbilang :
5.2 Marka Putus-putus 1396.7 m2 Rp 648,099.51 Rp 905,200,589.11 “Satu Triliun Tiga Ratus Dua Belas Miliar
Jumlah Rp 1,193,507,919,227.61 Delapan Ratus Lima Puluh Delapan Juta
PPN (10%)
TOTAL
Rp
Rp
119,350,791,922.76
1,312,858,711,150.38
Tujuh Ratus Sebelas Ribu Seratus Lima
Terbilang Puluh Ribu Rupiah”
Satu Triliun Tiga Ratus Dua Belas Miliar Delapan Ratus Lima Puluh Delapan Juta Tujuh Ratus Sebelas Ribu Seratus Lima Puluh Ribu Rupiah
projectCONCLUSION
KESIMPULAN
Kesimpulan dan Saran
Pembahasan
6. Biaya Konstruksi