Professional Documents
Culture Documents
Basic CTs For HORS 2013-3 PDF
Basic CTs For HORS 2013-3 PDF
March 6, 2013 1
Objective of the presentation:
For participants to increase their
knowledge level of Current Transformers in
the following areas:
◦ CT Theory
Basic Operation
CT Polarity
CT Connections
◦ Safety Hazards
◦ Basic Safe Work Practices
March 6, 2013 2
Examples of CT’s March 6, 2013 3
Examples of CT’s March 6, 2013 4
Examples of CT’s March 6, 2013 5
Examples of CT’s March 6, 2013 6
Basic Theory:
March 6, 2013 13
Death
March 6, 2013 14
A CT can easily supply currents above lethal levels!
The open circuit situation resolves to high voltages and lethal
currents… WATCH THIS!!
Click Video to
Run
March 6, 2013 15
Shows instantaneous current flow
Polarity Mark generally indicates H1/X1 terminals.
‘Make before
Break’ switch with
contact to
shorting bar. Schematic and Current path
for ABB Flexi-test switches –
Switches ‘Open’
March 6, 2013 30
‘Make before
Break’ switch with
contact to
shorting bar.
Westinghouse-ABB Case/Switches
March 6, 2013 31
‘Jack’ point for in-
service readings.
Westinghouse-ABB Case/Switches
March 6, 2013 32
Blade pulled slightly
out makes contact
with bar before
separating from relay
circuit.
Westinghouse-ABB Case/Switches
March 6, 2013 33
Shorting
Bar
Shorting
Bar
Westinghouse-ABB Case/Switches
March 6, 2013 34
Shorting
Bar
Test Plug
Spring
Loaded
Contacts
March 6, 2013 39
Working around CT Circuits:
◦ Circuit Identification
• Wiring Diagram / AC Schematic Information.
◦ Testing for Energized Circuits
Secondary Current measurement.
Audible/Visual arcing check.
◦ Safe work practices
◦ Job Briefings
◦ Methods of shorting at CT Shorting Blocks
Example of critical
information pertinent to
physical location of CT
Circuits.
March 6, 2013 43
CT Secondary Wires should be lifted
slowly while listening for arcing as a final
verification check.
The visual/audible Arcing Check is also not
100% reliable as a test for an open-circuit
CT condition.
◦ In brightly lit and/or noisy areas, it may be
difficult to detect the arcing condition.
◦ With low values of CT secondary current, there
may be little-to-no arcing when wiring is lifted.
Fluke Current
Measuring
Devices March 6, 2013 45
Care should be taken to keep yourself
from becoming a possible current path for
the CT should it become open-circuited.
ARC EXITED
HERE
Quote from
the Accident
Report:
“The
Electrician
ARC ENTERED said he
HERE
could smell
his flesh
burning”
CABLE
62E-04
March 6, 2013 47
When shorting CT secondaries at CT
Shorting Blocks, care must be taken to
properly short the CT Circuit.
CT ratio tap
wiring from one
individual CT
Single-Phase
wiring from
Note that a individual CT
minimum of two to relays,
screws are instruments,
needed to short etc.
this 1 CT – if the
full winding is Ground screw
shorted (Y1-Y5 connection
in this case). normally left in-
place.
Shorting Block
Ground
March 6, 2013 49
Single-Phase Shorting Block Example March 6, 2013 50
‘Three-Phase’ Type CT Shorting Block
Three-Phase
CT wiring from wiring to relays,
three single- instruments, etc.
phase individual
CT’s (three pairs)
Note that it takes
a minimum of
four screws to
short this set of 3
Shorting Block CT’s – (2Y1, 4Y1,
Ground 6Y1, and one of
2Y5, 4Y5, and
6Y5 in this case) –
as long as the
Wye connection is
Ground screw intact – white
connection wiring here.
normally left in-
place.
March 6, 2013 51
Three-Phase Block Analysis March 6, 2013 52
Make sure necessary wiring is in place to
effectively short ‘Three-Phase’ type blocks.
March 6, 2013 54