01 Hanger Sizing in CAESAR II PDF
01 Hanger Sizing in CAESAR II PDF
David Diehl
CAESAR II
© Intergraph 2013
Variable Supports
© Intergraph 2013
CAU Express 2013 1
Hanger Sizing
David Diehl
Selection Procedure –
1: Collect Data
© Intergraph 2013
Selection Procedure –
1: How the Data is Collected
© Intergraph 2013
CAU Express 2013 2
Hanger Sizing
David Diehl
Selection Procedure –
2: Find the Right Hanger
Selection Procedure –
3: Check Load Variation
© Intergraph 2013
CAU Express 2013 3
Hanger Sizing
David Diehl
Selection Procedure –
4: Identify the Hanger
© Intergraph 2013
Post Selection –
5: Include Selection in the Model
CAU Express 2013 4
Hanger Sizing
David Diehl
© Intergraph 2013
CAU Express 2013 5
Hanger Sizing
David Diehl
© Intergraph 2013
Data Folder –
Configuration Settings (1/3)
© Intergraph 2013
CAU Express 2013 6
Hanger Sizing
David Diehl
Data Folder –
Configuration Settings (2/3)
© Intergraph 2013
Data Folder –
Configuration Settings (3/3)
© Intergraph 2013
CAU Express 2013 7
Hanger Sizing
David Diehl
Data Folder –
Configuration Settings (3/3)
© Intergraph 2013
Data Folder –
Configuration Settings (3/3)
© Intergraph 2013
CAU Express 2013 8
Hanger Sizing
David Diehl
© Intergraph 2013
Number of Hanger
Design Operating
Load Cases
Multiple Load Case
Design Options
Calculate Actual
Cold Loads
© Intergraph 2013
CAU Express 2013 9
Hanger Sizing
David Diehl
© Intergraph 2013
CAU Express 2013 10
Hanger Sizing
David Diehl
© Intergraph 2013
For example:
Operating Case 1 (LC1) Operating Case 2 (LC2)
Design
for LC1
Design
for LC2
© Intergraph 2013
CAU Express 2013 11
Hanger Sizing
David Diehl
CAU Express 2013 12
Hanger Sizing
David Diehl
© Intergraph 2013
© Intergraph 2013
CAU Express 2013 13
Hanger Sizing
David Diehl
© Intergraph 2013
Hanger Table
Select one of the 33 manufacturer’s data sets
Check boxes (more later)
Extended Range – go beyond the “recommended”
range
Cold Load – size spring to balance the cold load;
useful in aligning equipment
Hot Load Centered – try to select a ”better” spring
© Intergraph 2013
CAU Express 2013 14
Hanger Sizing
David Diehl
© Intergraph 2013
Piping Input –
Hanger Data
Locating a hanger
Selecting a hanger
Specifying a hanger
© Intergraph 2013
CAU Express 2013 15
Hanger Sizing
David Diehl
Piping Input –
Node Data (1/3)
Node / CNode
Node: You define where the support should be
located.
CNode: Think of the CNode as the other end of the
hanger (which may have vertical growth to be
included in the selection).
© Intergraph 2013
Piping Input –
Design Data (2/3)
© Intergraph 2013
CAU Express 2013 16
Hanger Sizing
David Diehl
Piping Input –
Design Data (2/3)
Hanger Table
CAESAR II provides 33 hanger manufacturer catalogues
All have 3 spring sizes (e.g. short, mid & long range)
Some have a fourth (extra long) size
© Intergraph 2013
Piping Input –
Design Data (2/3)
CAU Express 2013 17
Hanger Sizing
David Diehl
Piping Input –
Design Data (2/3)
Available Space
Specifies the amount of room above or below the pipe where
you can install the hanger or can. If the value is negative,
then CAESAR II assumes that a can is to be installed.
CAESAR II will select the spring only if its basic hanger/can
length is below the entered value.
No space provided for hardware.
CAESAR II
CAESAR II CAESAR II true
value for value for
hangers cans
© Intergraph 2013
Piping Input –
Design Data (2/3)
© Intergraph 2013
CAU Express 2013 18
Hanger Sizing
David Diehl
Piping Input –
Design Data (2/3)
© Intergraph 2013
Piping Input –
Design Data (2/3)
© Intergraph 2013
CAU Express 2013 19
Hanger Sizing
David Diehl
Piping Input –
Design Data (2/3)
Piping Input –
Predefined Hanger Data (3/3)
© Intergraph 2013
CAU Express 2013 20
Hanger Sizing
David Diehl
Piping Input –
Predefined Hanger Data (3/3)
Hanger Display
© Intergraph 2013
CAU Express 2013 21
Hanger Sizing
David Diehl
Required Analyses
for Hanger Sizing
© Intergraph 2013
CAU Express 2013 22
Hanger Sizing
David Diehl
Note
“StressType”
Output Status
General results for Load Cases with Stress Type of
HGR are suppressed
As these results do not include the selected hangers,
it is unwise to activate their display (i.e. “Keep”)
© Intergraph 2013
CAU Express 2013 23
Hanger Sizing
David Diehl
Error Check:
© Intergraph 2013
CAU Express 2013 24
Hanger Sizing
David Diehl
© Intergraph 2013
© Intergraph 2013
CAU Express 2013 25
Hanger Sizing
David Diehl
Hanger Table:
Hanger Table
with Text:
© Intergraph 2013
Output (1/3)
© Intergraph 2013
CAU Express 2013 26
Hanger Sizing
David Diehl
Output (1/3)
8. Check horizontal
displacement for rod
swing
© Intergraph 2013
Output (3/3)
9. Spring size
© Intergraph 2013
CAU Express 2013 27
Hanger Sizing
David Diehl
© Intergraph 2013
© Intergraph 2013
CAU Express 2013 28
Hanger Sizing
David Diehl
Spring:
Anvil Fig. 82
Size 6
Hot Load=390
k=168 Hanger
load
Pump load
© Intergraph 2013
© Intergraph 2013
CAU Express 2013 29
Hanger Sizing
David Diehl
Spring:
Anvil Fig. 82
Size 7
Hot Load=558
k=224 Hanger
load
Pump load
© Intergraph 2013
CAU Express 2013 30
Hanger Sizing
David Diehl
Specified
HGR Load
© Intergraph 2013
© Intergraph 2013
CAU Express 2013 31
Hanger Sizing
David Diehl
Zero Load
Review hanger
locations when
CAESAR II notes
that hangers are
not carrying
weight.
During Solution
© Intergraph 2013
Zero Load
Review hanger
locations when
CAESAR II notes
that hangers are
not carrying
weight.
In the Solver
In the Hanger
Table
© Intergraph 2013
CAU Express 2013 32
Hanger Sizing
David Diehl
Zero Load
10/11 20 30
© Intergraph 2013
CAU Express 2013 33
Hanger Sizing
David Diehl
Hot Load
within 10%
© Intergraph 2013
548
653
574
10% 653
© Intergraph 2013
CAU Express 2013 34
Hanger Sizing
David Diehl
© Intergraph 2013
Two springs
CAU Express 2013 35
Hanger Sizing
David Diehl
© Intergraph 2013
CAU Express 2013 36
Hanger Sizing
David Diehl
© Intergraph 2013
Default
selection
Include spring
stiffness in
initial
operating
analysis
© Intergraph 2013
CAU Express 2013 37
Hanger Sizing
David Diehl
© Intergraph 2013
Different Springs!
Different Travels
© Intergraph 2013
CAU Express 2013 38
Hanger Sizing
David Diehl
© Intergraph 2013
Questions? Comments?
© Intergraph 2013
CAU Express 2013 39
Hanger Sizing
David Diehl
Thank You
© Intergraph 2013
CAU Express 2013 40