As-Planned Schedule
1 Mar 502 days 15 Jul
Actual Delay
16 Jul 175 days 6 Jan
Windows Analysis Method Windows Analysis
502 days 16 Jul 74 days 27 Sep
Actual Delay
16 Jul 175 days 6 Jan
doduykhuong.com
SUMMARY OF WINDOW ANALYSIS METHOD
2001 2002 2003
Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan
As-Planned Schedule
1 Mar 502 days 15 Jul
Windows
Windows Analysis
No.1 Method Excusable Delay
1 day
1 Mar - 30 Oct 16 Jul
Windows No.4
15 Sep - 6 Jan
As-Built Schedule As-Planned Schedule
Excusable Delay
7 days
23 Dec - 29 Dec
As-Planned Schedule
1 Mar 502 days 15 Jul
Forecast Finish Date
Windows No.1 As-Planned Noncompensable
Compensable
05 Sep DelayDelay
49 days 3 days
1 Mar - 30 Oct Forecast Finish Date
As-Built Windows No.2 Forecast Schedule Noncompensable
Compensable
06 NovDelay
Delay
42 days 20 days
31 Oct - 28 Feb Forecast Finish Date
As-Built Windows No.3 Forecast Schedule
Noncompensable
Compensable
22 Dec Delay
Delay
42 days 4 days
1 Mar - 14 Sep
Windows No.4
114 days
15 Sep - 6 Jan Forecast Finish Date
As-Built Forecast ScheduleNoncompensable
06 Jan Delay
15 days