RATE ANALYSIS FOR REINFORCED CEMENT CONCRETE


DOWNLOADED FROM THECONSTRUCTOR.ORG

RCC 1 :1 :2 Analysis for 2


Wet Volume 1.00 m 3

Dry Volume 1.54

MATERIAL Qty. Units Rs. / Unit


CEMENT BAGS 11.10 bags 300
SAND 0.39 m3 900
Aggregate 0.77 m 3
700
Reinforcement 157.00 Kg 60

LABOUR With
Mechanical Mixer & Vibrartor Days
MASON 0.37 300
LABOUR 3.50 200
WATER CARRIER 1.39 200
BAR BENDER 1.57 200
MIXER OPERTOR 0.071 200
MIXER VIBRATOR 0.071 200
0.00
PRIME COST (Rs.):

Water Charges 1.5%


Sundries (including mixer machine, transportation etc) 7.5 %
Contractor's Profit 14 %

Total Cost per m3 of RCC =

Cost of RCC for Given Data = Rs.


CONCRETE
Steel % by volume
of Concrete
SLAB 1.00%
BEAM 2.00%
COULMN 2.50%
Road 0.60%
AMOUN SUBTOT
T (Rs.) AL (Rs.)
3329
347
539
9420
13634.03

111.00
700.00
278.00
314.00
14.28
14.28 1431.56

15066

226
1130
2109

18531

18531