WEEKLY PICTORIAL PROGRESS REPORT

Period:- From 03.02.2017 to 09.02.2017

132/33kV Sinaw GS.

33kV Surface prep for Backfilling 132kV Backfilling done up to raft level

132kV GS- MEP Box Installation 132kV GS- Concealed sleeve inst.
132/33kV Samad GS

33kV Excavation works under progress

132kV Excavation works under progress (Jack Hammer)


OHL at Sinaw

Pad 1 & Pad 2 Concreting Excavation works under Progress

Access Road work under Progress PCC works


OHL at Samd

Chimney Concreting under Progress Pit Cleaning & arrangement for PCC

Excavation works under Progress PCC Works