ABENGOA

CONTRACT NO: N-18138B


CONTRACT TITLE :
Lot.2, Lot.3, Lot.4: OHL modification and Remote End works for establishing Mahawe-Wathba 220 kV OHL circuit 2 & Dismantling of 220 kV
OHLS UNPS-MHWG-WATH-RAMG/KHZG/SHME and 400 kV SASN-MOSG

REPLY TO COMMENTS ON DTS : 002 ATTACHMENT TO DTS : 040

TITLE: Lot 2,3 and 4

Master Time schedule CSD No: N18138B CF 7600 X 991 A

S/N Comments vide CS-002 Reply to comments

1 Program should highlight the pre-requisites as explained at the The Pre-requisites like submission of performance bank guarantee
Contract Kick-Off Meeting and Insurance policies is included.

2 Remove the term “MOS”. It is either “Method Statement (MS)” OR Corrected as "Method statement".
“Statement of Method (S-o-M)” and, the former is recommended.

3 Appropriate Primavera Original File should also be submitted. The Master time schedule is prepared in MS project and original file
(soft) along with the document is included in the folder uploaded in
TAQA collaboration portal.
4 Please follow the guidelines of Transco for Reporting Methodology of Noted. We have incorporated the baseline & actual planning of the
Time and Cost development program / schedule including reporting Mastet Time schedule.
procedures.
5 Brief description of the Scope of work, Legend for abbreviations, Legends for abbreviation is included in the bottom of the each sheet.
details of project calendar for review, Engineering, procurement, and The schedule includes the different stages like engineering and
construction etc., shall be included in the Master Time schedule. construction as applicable under the subject contract.

6 Please show the total float, free float, and critical path for the proposed Incorporated.
master time schedule.

7 Work Breakdown Structure (WBS), dependencies are not logically / Noted and corrected in the new baseline plan.
sequentially linked. For example, WBS ID: 1.3.4 – prep & submission
of MS for dismantling of 400KV OHL is between 15th July – 20th July,
whereas WBS ID: 1.5.1.4 dismantling of section commences between
04th July. Scaffolding Method statement submission is on 10th July
and the works are shown as commencement on 04th July. Please
check and correct all WBSs. Please check and correct in Lot 2, Lot3 &
Lot 4.
8 Master project schedule shall be corrected as Project Baseline Master project schedule is corrected as Project Baseline Schedule.
Programme/Schedule and WBS structure shall be limited to level 3. WBS is limited to level 3 which spans the entire project and includes
The detailed Level – 4 shall be submitted to project supervision team, major milestones in document submissions, construction and
prior to execution. importat stages applicable in the project.

9 WBS ID: 1.5.1.4.7 – Transportation of material to Transco stores, all he WBS for transportation of materials is linked to the completion of
dismantled conductors and accessories shall be shifted on daily basis destringing works & other OHL materials and may not happen daily in
and link shall be updated accordingly. This applicable for all lots. practical situation and the dates indicated in the schedule are
planned dates only. Actual dates will be monitored and entered as
actual start and actual finish during the progress of work.

10 Contract BOQ is only a Lot item. No breakdown of activities or items


WBS shall be prepared inline to contract BOQ and operative is provided in the BOQ from client/consultant and covers only
systems/sub-systems. dismantling of OHL and material handover as just lot items.

11 Master baseline schedule completion is earlier than the contract the observation is correct. The acual start and actual finish date may
completion period Pease check and re-confirm. change according to the delays beyond Inabensa control (for
example , receiving traffic detour permits, delay in providing
shutdowns, delays in receiving NOCs etc)
12 WBS ID: 1.5.2 - LOT 3: - DISMANTLING MHWG-WATH- 220kV OHL The scope related to Lot 3 and its related activities are included in
Ckt. 1 & 2 and MAHAWE 220kV S/S – Telecom modification works for the Baseline schedule.
MHWG and WATH missed out. Please revise and include
13 WBS ID: 1.5.2.3 - REMOVAL OF SINGLE OPGW ASSOCIATED Noted and corrected.
WITH MHWG-WATH D/C OHL & WBS ID: 1.5.2.7.3 & 1.5.2.8.3 -
OPGW DISMANTLING to be justified. Both are same activities.
ABENGOA

CONTRACT NO: N-18138B


CONTRACT TITLE :
Lot.2, Lot.3, Lot.4: OHL modification and Remote End works for establishing Mahawe-Wathba 220 kV OHL circuit 2 & Dismantling of 220 kV
OHLS UNPS-MHWG-WATH-RAMG/KHZG/SHME and 400 kV SASN-MOSG

REPLY TO COMMENTS ON DTS : 002 ATTACHMENT TO DTS : 040

TITLE: Lot 2,3 and 4

Master Time schedule CSD No: N18138B CF 7600 X 991 A

S/N Comments vide CS-002 Reply to comments


14 In Master Time Schedule (Project Baseline Programme/Schedule), Noted and incorporated.
Contract Title ”N-18138/B”, Project title, revision status etc., shall be
updated.

15 Please be suggested to use the below Lot references (extract from Noted and incorporated.
SOW/LOA) in the milestone and all appropriate places as required.

16 Please refer “DTS-003” for Additional comments. noted and complied as applicable.

17 Please update Rev status on DTS top sheets & CSD sheet. Updated rev status in the DTS top sheets and CSD sheet.

Project Manager: