Data

Blinding Concrete 50 mm
Working Space(around Footing) 1.2 m
Batter 45°
Reinforced Concrete 140 kg/m3
Allowable bulking of excavated material 25%
Time for formwork to remain in place 7 days
Backfill 300 mm

Concrete Footing
Width 10 m
Length 15 m
Depth 1.75 m
Top of Blinding 1.5 m(below ground level)

Available Equipment
20T excavator with 0.9m3 bucket 40 m3
Vibrating plate compactor 40 m3
Concrete Pump 25 m3/hour

Crew Trades
Foreman 1 per crew
Carpenter (formwork) 0.75 mhrs/m2
Steel fixer (reinforcement) 200 kg/hr
Labourer One each per Carpenter