Professional Documents
Culture Documents
by
MARYSE MONFETTE
in
CIVIL ENGINEERING
June 2 0 04
The spillway layout affects the plunge pool scour development mainly
through the design unit discharge and total head drop for a given outflow and
reservoir level. The plunge pool scour configuration is affected by the
prevailing geological conditions. The magnitude of spillway flows appears
predominant over the frequency and duration of spills. Observations support
the concept of equilibrium conditions.
Abstract ii
List of Tables v
List of Figures vi
Acknowledgements viii
CHAPTER I INTRODUCTION 1
Figure 1.1: Free-Trajectory Jet Issued from a Typical Ski-Jump Spillway at Seven
Mile Dam (Trail, B.C.) 5
Figure 2.1: Main Parameters and Physical Processes Involved in Plunge Pool
Scour 19
Figure 2.2: Jet Behaviour in the Atmosphere 20
Figure 2.3: Jet Behaviour in the Plunge Pool 20
Figure 2.4: Erodibility Threshold for Rock and Other Complex Earth Materials . 21
Figure 3.1: Geographic Location of Dam Sites 58
Figure 3.2: Peace Canyon Dam/General Arrangement 59
Figure 3.3: Peace Canyon Spillway 59
Figure 3.4: Peace Canyon Dam/Spillway Foundation Geology 60
Figure 3.5: Peace Canyon Dam/Spillway Outflow Hydrograph - 1979 to 2001. . . . 61
Figure 3.6: Peace Canyon Dam/Plunge Pool Topography Before Spillway Operation. 62
Figure 3.7: Peace Canyon Dam/Plunge Pool Topography As Surveyed
on 15 April 1980 63
Figure 3.8: Peace Canyon Dam/Plunge Pool Topography As Surveyed
on 5 September 1981 64
Figure 3.9: Peace Canyon Dam/Plunge Pool Topography As Surveyed
on 4 August 1996 65
Figure 3.10: Seven Mile Dam/General Arrangement 66
Figure 3.11: Seven Mile Spillway 66
Figure 3.12: Seven Mile Dam/Plunge Pool Bedrock - Geological Mapping 67
Figure 3.13: Seven Mile Dam/Photographs of Plunge Pool Bedrock 68
Figure 3.14: Seven Mile Dam / Spillway Outflow Hydrograph - 1979 to 2001. . . . 69
Figure 3.15: Seven Mile Dam/Plunge Pool Topography Before Spillway Operation. . 70
Figure 3.16: Seven Mile Dam/Plunge Pool Topography As Surveyed
on 14 December 1979 71
Figure 3.17: Seven Mile Dam/Plunge Pool Topography As Surveyed
on 11-12 August 1982 72
Figure 3.18: Seven Mile Dam/Plunge Pool Topography As Surveyed
on 20 September 1984 73
Figure 3.19: Seven Mile Dam/Plunge Pool Topography As Surveyed
on 21-26 October 1997 74
Figure 3.20: Portage Mountain Project/General Arrangement 75
Figure 3.21: Portage Mountain Spillway 75
Figure 3.22: Portage Mountain Project/Right Cliff Rock Strata 76
Figure 3.23: Portage Mountain Project/Plunge Pool Geology 77
Figure 3.24: Portage Mountain Project/Spillway Outflow Hydrograph -
1972 to 2001 78
Figure 3.25: Portage Mountain Project/Plunge Pool Topography
Before Spillway Operation 79
Figure 3.26: Portage Mountain Project/Plunge Pool Topography
As Surveyed on 15-16 May 1973 80
Figure 3.27: Portage Mountain Project/Plunge Pool Topography
As Surveyed on 4 August 1996 81
Figure 3.28: Revelstoke Dam/General Arrangement 82
Figure 3.29: Revelstoke Spillway 82
Figure 3.30: Revelstoke Dam/Plunge Pool Geological Information 83
Figure 3.31: Revelstoke Dam/Spillway Outflow Hydrograph - 1983 to 2001 84
Figure 3.32: Revelstoke Dam/Plunge Pool Topography Before Spillway Operation. . 85
Figure 3.33: Revelstoke Dam/Plunge Pool Topography As Surveyed on 15 May 1984 . 86
Figure 3.34: Revelstoke Dam/Plunge Pool Topography As Surveyed
Following Spillway Tests on August 1986 87
Figure 4.1: The Latest Plunge Pool Scour Configuration at Peace Canyon Dam
and Seven Mile Dam 102
Figure 4.2: The Latest Plunge Pool Scour Configuration at Portage Mountain
Project and Revelstoke Dam 103
Figure 4.3: Spillway Flow Duration Curve of Each Site of Study 104
Figure 5.1: Peace Canyon Dam/Comparison of Prototype Scour and Model Scour . 120
Figure 5.2: Seven Mile Dam/Model Scour Patterns in Non-Cohesive Bed 121
Figure 5.3: Seven Mile Dam/Model Scour Patterns in Cohesive Bed 122
Figure 5.4: Portage Mountain Project/Plunge Pool Scour From Model Tests. . . 123
Figure 5.5: Revelstoke Dam/Scour Configuration From Model Studies 124
Figure 5.6: The Veronese Equation/Predicted Plunge Pool Floor Elevation. . . 125
Figure 5.7: The Jaeger Equation/Predicted Plunge Pool Floor Elevation. . . . 126
Figure 5.8: The Damle Equation/Predicted Plunge Pool Floor Elevation . . . . 127
Figure 5.9: The Chian Min Wu Equation/Predicted Plunge Pool Floor Elevation. 128
Figure 5.10: The Martins Equation/Predicted Plunge Pool Floor Elevation . . . 129
Figure 5.11: The Taraimovich Equation/Predicted Plunge Pool Floor Elevation ! 130
Figure 5.12: The Mason A Equation/Predicted Plunge Pool Floor Elevation . . . 131
Figure 5.13: The Mason B Equation/Predicted Plunge Pool Floor Elevation . . . 132
Figure 5.14: The Wang Shixia Equation/Predicted Plunge Pool Floor Elevation . 133
Figure 5.15: The Yildiz & Uzucek Equation/Predicted Plunge Pool Floor
Elevation 134
Figure 5.16: Comparison Between Predicted Versus Observed Plunge Pool
Scour Depth 13 5
Figure 6.1: Conceptual Approach of the Erodibility Index Method in the
Assessment of Plunge Pool Scour 159
Figure 6.2: The Erodibility Index Method Applied to the Peace Canyon
Plunge Pool 160
Figure 6.3: The Erodibility Index Method Applied to the Seven Mile
Plunge Pool 161
Figure 6.4: The Erodibility Index Method Applied to the Portage Mountain
Plunge Pool 162
Figure 6.5: The Erodibility Index Method Applied to the Revelstoke
Plunge Pool 163
Figure 6.6: The Erodibility Index Method/Predicted Plunge Pool Floor
Elevation 164
Figure 6.7: Peace Canyon/Sensitivity Analysis of Jet Velocity Profile. . . . 165
Figure 6.8: Seven Mile/Sensitivity Analysis of Jet Velocity Profile 166
Figure 6.9: Portage Mountain/Sensitivity Analysis of Jet Velocity Profile. . 167
Figure 6.10: Revelstoke/Sensitivity Analysis of Jet Velocity Profile 168
Figure 6.11: Peace Canyon/Sensitivity Analysis of Jet Impact Velocity . . . . 169
Figure 6.12: Seven Mile/Sensitivity Analysis of Jet Impact Velocity 170
Figure 6.13: Portage Mountain/Sensitivity Analysis of Jet Impact Velocity . . 171
Figure 6.14: Revelstoke/Sensitivity Analysis of Jet Impact Velocity 172
Figure 6.15: Peace Canyon/Sensitivity Analysis of Jet Air Concentration . . . 173
Figure 6.16: Seven Mile/Sensitivity Analysis of Jet Air Concentration . . . . 174
Figure 6.17: Portage Mountain/Sensitivity Analysis of Jet Air Concentration . 175
Figure 6.18: Revelstoke/Sensitivity Analysis of Jet Air Concentration . . . . 176
ACKNOWLEDGEMENTS
The break-up point marks the limit between two types of jets:
undeveloped and developed (Figure 2.2) . Undeveloped jets are characterized
by a solid, non-aerated water core as opposed to developed jets which are
fully aerated and composed of discrete water segments. As the jet free
falls, the internal turbulence intensity, drag due to air resistance, and
air entrainment processes cause the jet to transition from an undeveloped
to a developed condition (Bohrer et al. , 1998) . The deceleration caused by
air drag becomes a significant factor when the jet loses its coherence in
free-fall (Lewis et al. , 1996) . Surface tension and turbulence effects
determine the distance to the break-up point (Ervine et al. , 1997) .
The air entrained by the free jet during flight tends to cushion the
impact with the tailwater surface. Most authors agree that aerated water
will produce a lesser scour than unaerated, "solid" water (Mason and
Arumugam, 1985) . The result of air entering the jet is that the effective
time average density is considerably reduced and therefore the time
average jet dynamic pressure is also reduced in spite of the fact that
negligible jet deceleration may have occurred (Davies and Jackson, 1982).
Ervine et al. (1997) show that the combined effects of jet spreading and
air entrainment decrease the mean and fluctuating dynamic pressures on the
pool floor. If the mixing of the air is incomplete and the jet is not
fully established [developed] upon impact with the plunge pool, there will
be no cushioning effect in the core region (Spurr, 1985) .
2.1.2 Jet Diffusion and Hydraulic Action within the Plunge Pool
An approximate description of the hydraulic phenomena involved in the
diffusion of a free falling jet in the tailwater pool is possible when the
theory of the free jet turbulence is applied (Hartung and Hausler, 1973).
Upon impact with the tailwater surface, the trajectory of the free jet
follows a straight line sloping at the angle of penetration down to the
plunge pool invert. Gravitational effects on the j et would be minimal once
the jet entered the tailwater, and the jet would tend to follow a straight
line rather than a free-fall trajectory (Johnson, 1974) . As the jet
plunges into the pool, it diffuses almost linearly (Whittaker and
Schleiss, 1984). Because the turbulent plunging jet comprises an
expanding, undulating, and aerated outer zone, the initial boundaries of
the jet entering the pool are not clearly defined. On account of the
irregularity of the flow in the outer region, plunging turbulent jets will
produce surface waves in the plunge pool rather than well-defined
penetrating shear layers (Ervine and Falvey, 1987). The jet behaviour in
the plunge pool is illustrated in Figure 2.3.
The jet flow below the water surface may consist of either one or two
regions depending on the coherence of the jet (undeveloped or developed
conditions) at the moment of impact with the tailwater (Figure 2.2) . A
transition zone, known as the flow establishment region, exists when the
central core of the plunging jet is still present upon impingement (Figure
2.3). The region of flow establishment is where the shearing action at the
edge of the jet decreases the edge velocity, but does not affect the
velocity near the centre of the jet (George, 1980). The inner core takes a
wedge-like form as turbulence penetrates inwards towards the centreline of
the jet. This wedge of undiminished mean velocity is referred to as the
potential core. The length of flow establishment varies from 5 to 10 times
the thickness of rectangular jets (George, 1980). Beyond this distance,
the velocity remains a maximum along the jet centreline but the entire
flow velocity field is reduced by diffusion (Hartung and Hausler, 1973).
The zone of established flow (or fully developed flow) begins at the point
where the central core of the plunging jet is completely diffused. The
velocity profile in the established flow region has a very nearly Gaussian
distribution (George, 1980). A developed falling jet will diffuse in the
plunge pool and form a fully developed flow region (zone of established
flow) upon entrance. The diffusion process continues until all the initial
energy of the jet is dissipated, or until the influence of a boundary
causes an impinging flow region (George, 1980).
Two-phase flow develops when a plunging jet dives through the surface
of a plunge pool or tailwater (Wittier et al., Dam Foundation Erosion,
1995) . As the jet plunges into the pool, a considerable amount of air is
entrained, corresponding to an air concentration of 40 to 60% at typical
jet velocities of 30 m/s [100 ft/s] at impingement (Bollaert, 2002, as
reported by Schleiss, 2002). Bin (1984) and Ervine et al. (1980) describe
the mechanisms of air entrainment by a plunging jet at the surface of a
plunge pool. The captured air is dispersed into bubbles by shear forces
and turbulence and forms an approximately conical biphasic region (Bin,
1984) (Figure 2.3). Air concentration decreases as the jet travels into
the pool, thereby increasing jet density (Annandale et al., 1997).
Estimates of the mean air concentration with depth can be made by assuming
that the mean air flow rate decays approximately linearly from a maximum
value at the jet plunge point to zero at the maximum air bubble
penetration depth (Ervine and Falvey, 1987). At the maximum air bubble
penetration depth, the mean water velocity approximates the bubble rise
velocity ending the jet's capacity to retain entrained air. It is
reasonable to speculate that the presence of air bubbles in the diffusing
plunge pool shear layers will result in a reduction in mean dynamic
pressures (Ervine and Falvey, 1987) . However, the presence of free air
bubbles was recently shown to be important in the propagation of fully
transient water pressures in rock joints (Bollaert, 2002) .
The impinging jet induces circulation in the plunge pool (Figure 2.1).
Both horizontal and vertical velocities cause rolling actions in the
plunge pool, the mechanics of which do not appear to have been fully
investigated to date (Sutcliffe, 1985). As discussed by Spurr (1985), the
hydraulic action within the plunge pool is largely influenced by the pool
boundaries. The formation of a "backroller" (clockwise vortex) between the
jet and the upstream boundary is common knowledge (Henderson, 1966). As
the submerged jet strikes the bed, a small stream moves upstream in the
roller region, while the main stream is deflected upwards to form a
downstream surface boil. The difference in upstream/downstream water
levels induces the formation of secondary currents at the sides of the
pool. A recent study conducted at Colorado State University (Fort Collins,
CO) on plunge pool circulation and velocity prediction in a plunge pool
basin suggests the formation of a counter-clockwise vortex in the roller
region (Hamilton et al. , 1997) . The most significant factor leading to the
counter-clockwise rotating vortex is the buoyancy force resulting from the
high degree of air entrainment in the plunging jet (ibid.).
Annandale (1994, 1995) describes the removal of fragments from the rock
mass through the process of progressive dislodgment that involves three
components: jacking, dislodgement, and displacement. The jacking effect is
caused by the instantaneous differential pressures on the upper and lower
surfaces of rock blocks. Once the material is destabilized, it is
dislodged by the flowing water and displaced in the downstream direction.
When the combined effects of the plucking forces normal to the loosened
block and the tangential form drag forces induced by the local boundary
flows become sufficiently large, the block becomes dislodged and is swept
away (Spurr, 1985) . The displaced material is deposited downstream of the
scour hole as the flow transport capacity diminishes and a tailrace bar
deposit (or mounding) can form (Figure 2.1) . As the scour hole deepens,
more energy is required to remove the rock fragments and larger blocks
remain trapped inside the hole. The dislodged blocks, recirculating within
the live scour-hole, abrade through contact with the other rocks until
they are small enough to be ejected as part of the downstream wash load
(Spurr, 1985) .
The geological conditions of the plunge pool bedrock affect the scour
processes. The rate of penetration and build-up of pressure by the jet
within the bedrock is influenced by the condition and orientation of its
discontinuities (Spurr, 1985). The hydraulic breakage of the rock mass is
more efficient in rock with open joints than in sound rock with tight and
discontinuous joints. Likewise, the more closely aligned the major bedding
planes are to the angle of incidence of the plunging jet, the easier the
penetration and the more rapid will be the hydrofracture processes (Spurr,
1985) . The process of dislodgement is affected by the geometry of rock
blocks, which is determined by the discontinuity pattern of the rock
formation. Smaller size and equi-sided shape provide less resistance to
erosion. The orientation of the material relative to the direction of flow
also has an impact on its capacity to resist erosion (Annandale, 1994).
Rock dipped in the direction of flow is more easily dislodged than rock
dipped against it (Annandale et al. , 1996). The strength of rock is
determinant in the process of abrasion. The rock susceptibility to
abrasion is inversely proportional to its strength (Prochukhan et al.,
1971, as reported by Akhmedov, 1988) . The cohesive strength of the rock
formation is particularly important at the periphery of the scour hole to
resist the erosive shear forces of secondary currents. Ideally, the scour
hole is confined laterally to contain the jet and act as a dissipating
pool. The non-homogeneity of the rock in a plunge pool may significantly
affect its shape (Spurr, 1985). Asymmetrical plunge pool development
results from the bedrock heterogeneity.
The Dam Foundation Erosion Study Team (DFEST) was formed in 1993 under
the management of the U.S. Bureau of Reclamation in an effort to improve
the current technology in the assessment of scour downstream of
overtopping dams. The need for better analytical tools for analyzing
erosion in the foundation and abutment areas of dams is increasing as
costly alternatives to overtopping come under consideration (Wittier at
al., Spillway and Foundation Erosion, 1995). Wittier et al. (1995) explain
the basis for the development of new technology:
Current methods of predicting and evaluating erosion extents have
limited applicability. Existing erosion prediction formulas do not
track erosion as a function of time, and have limited application in
hard-rock or cohesive foundation materials. (Wittier at al. , Spillway
and Foundation Erosion, 1995)
d = KOZL
dz
in which K, X, y , and Z are constants derived from each author. Mason
(1984) contributed to a major improvement in the assessment of ultimate
scour depths under free jets by developing two expressions (one for model
data and one for both models and prototypes) which are dimensionally
balanced and respect the Froude scaling law. The equation for model scour
is now considered as an upper bound for prototype scour and recognized as
the most practical and state-of-the-art equation for dam design. Even so,
Mason (1984) acknowledges that accuracy is limited to 70%.
K = Ms • Kb • Kd • Js
The mass strength Ms is the dominant factor in the resistance to erosion.
The other parameters represent, respectively, reducing effects of size,
joints conditions, and shape/orientation relative to the flow on eroding
the intact rock mass. The paper by Annandale (1995) provides standard
tables quantifying these geological parameters and the principal tables
are repeated in Appendix I. The Erodibility Index Method (Annandale, 1994,
1995) is evaluated using data collected from four BC Hydro dam sites in
Chapter VI.
PLUNGE POOL SCOUR
LEGEND
Vo: initial jet velocity 111 free-trajectory jet mean dynamic pressure
Vi: jet velocity at impact with the plunge pool
bottom pressure fluctuations
Vm: maximum jet velocity in the plunge pool |U zone of flow establishment
H: head difference between reservoir level and tailwater surface shear stresses
H zone of established flow hydrodynamic fracturing
h: tailwater depth
Ds: maximum depth of scour below original bed level El impingement region hydrodynamic uplift
Ds
Figure 2.1. Main Parameters and Physical Processes Involved in Plunge Pool Scour
Figure 2.2. Jet Behaviour in the Atmosphere
ERODIBILITY
Rock and Complex Earth Materials
10,000
• Erosion
O No Erosion
1,000 • •
•
•
o
fM o
- o
E 0,-0
100 o O
•
<u •
•
o •
• •
CL
(D • +1
}.*
QJ
10 •
I/) •
C
3 • $ o
• •
o
• * / c / o
o ^O CD
cn o
• o yo
o° oo °
o
0.1
The four dam sites selected for this study are Peace Canyon, Seven
Mile, Portage Mountain, and Revelstoke, which are owned and operated by
B.C. Hydro (BCH), public corporation of British Columbia, Canada. The
Seven Mile & Revelstoke projects are part of the Columbia River Basin
(southeastern B.C.), whereas the Peace Canyon and Portage Mountain
projects are located in the Peace River Basin (central-eastern B.C.).
Refer to Figure 3.1 for geographic location.
To avoid possible damage to the powerhouse and right bank, the six
spillway gates should be opened in order 3, 4, 6, 5, 1, 2 and closed in
reverse order (BCH Report No. OMSPCN/03, 2001). Spillway Bays 3 and 4 were
selected for principal use because they are centered on the plunge pool
(BCH Report No. H1742, 1987).
The Inflow Design Flood (IDF) at Peace Canyon Dam is the Probable
Maximum Flood (PMF) based on the Williston Lake/Probable Maximum Flood
1988 study by B.C. Hydro (BCH Report No. H2003, 1988) . Because of the
limited storage in Dinosaur lake, the Williston lake PMF outflow is the
Peace Canyon PMF inflow (BCH Report No. H2767, 1994). The Peace Canyon
spillway can pass the IDF of 330,200 cfs at reservoir El. 1652.4 ft with
all gates fully open.
3.1.3 Plunge Pool Geology
Bedrock in the riverbed downstream of the spillway consists of massive
silty shale to shaly siltstone that exhibits little or no lamination (BCH
Report No. GEO 9/85, 1985). Contacts between interbedded rock types within
the foundation shale member are gradational. The lower 3-4 ft of the shale
unit is a transition rock to the underlying massive sandstone unit at
approximate El. 1430 ft. The sandstone unit is about 30 ft thick and below
is another massive shale sequence of unknown thickness. Bedding strikes
N60° and dips about 2° implying small components of dip upstream and
towards the right abutment (approximately 1.4° or 2.5V:100H). Unconfined
compressive strengths of the actual concrete dam foundation range from
about 5000 to 13,000 psi in competent shales and about 11,000 to 20,000
psi in the basal sandstone (BCH Report No. H1742, 1987).
The foundation shale member is essentially free from joints except for
a 10 0 ft wide zone oriented subparallel to the river canyon through the
left side of the spillway foundation. Jointing is generally sparse with
joints striking N30° to 40°E (i.e. at 60° to dam axis) and dipping
vertically, generally with joint spacing of 10 to 20 feet (BCH Report No.
GEO 9/85, 1985) . Joints are usually tight, discontinuous, and do not
extend upward or downward across principal bedding planes. In the Block
SI, S2 area of the spillway, there is a fractured zone termed the "hinge
zone" [Figure 3.4] where the joints have similar orientation but are more
closely spaced with tight joints at 1-3 ft spacing and with open relaxed
joints at 5-15 ft spacing (BCH Report No. GEO 9/85, 1985) . Within this
weakness zone, a sub-channel was eroded down to bedding plane B.P.4. The
fractured "hinge zone" and associated sub-channel trend downstream from
Bays 3 and 4 towards the plunge pool area but there is no subsurface
information to confirm their extent. Secondary joints are vertical, with a
strike of N110°-130°, and occur mostly in the sandstone and siltstone
beds .
The largest spill event to date at Peace Canyon Dam occurred in 1996,
from 23 June to 17 August. Spillway Gate 3 was fully open for the whole
month of July discharging approximately 47,000 cfs. Meanwhile, spilling
over Bay 4 was maintained at 31,000 cfs on two separate weeks. Outflows
through each of Bays 5 and 6 ranged between 15,000-18,000 cfs for most of
the spilling period and the peak discharge of 27,000 cfs was held for
twenty hours. The maximum spillway discharge of 116,000 cfs (35% of IDF)
recorded in 1996 remains the highest discharge recorded on site.
The scour hole downstream of the spillway flip buckets has formed for
the most part during the 1979/80 spillway operation. Prior to the 1979/80
spill a shallow circular hole with invert at El. 1477 ft was centred about
240 ft downstream of the centreline of Bay 4 and plunge pool floor
elevations were essentially above El. 1490 ft (Figure 3.6) . Overburden
conditions were however unknown. In particular, foundation construction
records indicate that an overburden infilled sub-channel (related to the
hinge zone) extended downstream from Bays 3 and 4 towards the plunge pool
area but its extent was unknown (BCH Report No. H1879, 1986). Remnants of
the downstream construction cofferdam could also have been left in place.
Following the passage of river flows through the spillway in 1979/80, the
volume of material removed below El. 1490 ft approached 1 million cu.ft
(Table 3.3) . Tailrace dredging was performed in July 1980 to remove the
accumulated debris downstream of the scour hole. The survey of 15 April
1980 showed a scour hole with invert at El. 1458 ft and the El. 1480 ft
contour extending over 310 ft in the direction of spillway flows and 220
ft across the spillway bays (Figure 3.7) . Although Bays 3 and 4 were
usually operated jointly during the 1979/80 spill, the lowest elevations
were recorded downstream of Bay 3. Maximum scour of about 45-50 ft
extended some 180-280 ft downstream of the flip buckets. Downstream of
Bays 5 and 6, the plunge pool floor was lowered to El. 1482-1484 ft for a
maximum scour depth of approximately 3 0 ft.
The plunge pool survey following the largest spill to occur at Peace
Canyon Dam in 1996 indicated a progression of scour, but longitudinally
rather than vertically. The plunge pool as surveyed on 4 August 1996 was
no deeper (invert at El. 1459 ft) but the El. 1480 ft contour extended
over 410 ft in the direction of spillway flows and 240 ft across the
spillway bays (Figure 3.9). The total volume scoured below El. 1480 ft
since the beginning of spillway operation in 1979 had reached 581,000
cu.ft. The major axis of the scour hole showed a definite inclination of
about 25° to the right of spillway flows. Despite the use of spillway Bay
3 at full capacity during the 1996 spill event, the scour hole maximum
depth remained unchanged. Interestingly, the scour hole invert had
migrated upstream to be located some 170 ft downstream of the limit
between Bays 3 and 4. Downstream of the spillway Bays 3 and 4 typically 4
m [13 ft] of rock had been eroded from the upstream slope of the plunge
pool (BCH File No. C-PCN-12 06.12, 1997). The eroded area downstream of
Bays 5 and 6 was more defined laterally but not significantly deeper
(minimum El. 1481 ft) . As part of a diving inspection, six large rock
blocks "the size of a Volkswagen buses" were identified down the base of
the slope and at the deepest part of the plunge pool.
The Seven Mile Project consists of a concrete gravity dam with a crest
length of 1138 ft and a maximum height of 262.5 ft above the foundation.
Gravity blocks are adjacent to both abutments followed by a four-unit
power intake section on the right and a five-bay spillway arrangement on
the left (Figure 3.10). The Seven Mile reservoir has a total capacity of
85,000 acre-ft at Maximum Normal Reservoir Level (El. 1730 ft) for a
surface coverage of 1000 acres. Currently, three generating units are in
service for a maximum sustained capacity of 600 MW. Site preparation for a
fourth unit is underway. The powerplant came into service in December 1979
and the third generating unit was commissioned a year later. In May 1988,
the reservoir was raised from El. 1715 ft to the current maximum normal
operating level of 1730 ft after extensions were added to the spillway
gates.
The Inflow Design Flood (IDF) for the Seven Mile Dam is the Probable
Maximum Flood (PMF) as established by a recent study (1997) by Morrison
Knudsen Corporation for Seattle City Light's Boundary Dam and B.C. Hydro's
Seven Mile Dam (BCH Report No. MEP507, 1999). The peak PMF flow (376,900
cfs) can be passed through the spillway at maximum reservoir El. 1732.0 ft
with all gates fully open.
From 1979 to 1982, the spill events were increasing in magnitude every
year:
• Initial spillway discharges, before the powerhouse was functional,
ranged between a few thousand cfs to about 3 0,000 cfs. Releases were
made through Bays 1 and 2 almost exclusively. On 5 November 1979,
the first day of spillway operation, Gates 1 and 2 were fully open
for approximately half an hour resulting in a peak outflow of 48,000
cfs .
• The first major spill occurred in the spring of 1980, from 20 April
to 23 July. Spillway flows were maintained around 70,000 cfs on
three consecutive days. Bay 3 was used along with Bays 1 and 2 for a
seven-week period at an average discharge of 12,000 cfs.
• During the 1981 spring freshet, Bays 1 to 4 were used so that flows
through the right chute (Bays 1 and 2) did not exceed the previous
year maximum. Average daily flows from Bay 3 ranged between 24,000-
26,000 cfs for twelve days and Bay 4 released a steady discharge of
8,000 cfs for nineteen days. During spillway testing on 26-28 May
1981, a peak outflow, of 98,000 cfs through Bays 1 to 4 was
maintained for over an hour.
• The 1982 spill event exceeded previous spills by magnitude and
duration. The spillway was in continuous operation from 28 April to
31 July 1982 during which discharges were maintained around 100,000
cfs for two consecutive days. Bays 1 and 2 spilled a maximum of
34,000 cfs per bay during forty hours. The operation of Bays 3 and 4
was similar in magnitude and duration as in 1981.
The spring freshet of 1997 caused the largest spill event at Seven
Mile Dam since completion of the dam. Each of Bays 1, 2, and 3 spilled a
minimum daily average discharge of 29,000 cfs (and up to 36,000 cfs for
Bays 1 and 2) for four weeks. A steady discharge of 9,000 cfs was released
through Bay 4 for nine weeks. Overall, Bays 1 to 4 spilled together
continuously for nearly ten weeks.
Due to gate restrictions, Gate 5 has never been operated for more than
three consecutive hours and the maximum discharge tested was 16,000 cfs in
July 1983.
The core of the scour hole has formed within six weeks of initial
spillway operation (5 Nov. to 14 Dec. 1979) with relatively low outflows
through Bays 1 and 2 (refer to Section 3.2.4). The plunge pool bedrock
surface before spillway operation (Figure 3.15) was gradually benched
downstream of the left chute, from El. 1565 ft at the left end of the
spillway to El. 1550 ft at the limit between the two separate chutes.
Downstream of the right chute, the bedrock sloped abruptly in a northwest
direction to El. 1495-1500 ft near the tailrace excavation limit (Station
8 + 70) . Photogrammetry of the riverbed based on 1958 and 1972 aerial
surveys indicated a shallow depression with invert at El. 1475 ft some 400
ft downstream of the powerhouse. The survey of 14 December 1979 indicated
elevation points as low as 1465-1467 ft where the pre-spill survey showed
a bedrock surface at approximate El. 1500 ft (Figure 3.16). The maximum
scour depth of 35-40 ft was located 325 ft downstream of Bay 1 flip
bucket. An estimated 74,000 cu.ft of rock was scoured below El. 1490 ft
and the resulting scour hole was relatively narrow in the direction of
spillway flows (Table 3.6). The shallow depression in the river channel
observed prior to spillway operation appeared to have been filled with
shattered rock.
The tailrace sounding survey of August 1982 followed the 1981 spillway
tests at large flows and the 1982 spring flood which exceeded previous
spills in terms of magnitude and duration. A clear progression of scour
was observed, mainly downstream of the existing minimum elevation points.
The scour hole as surveyed in August 1982 showed a rather circular
configuration with an approximate length of 175 ft and width of 200 ft
(El. 1490 ft contour) (Figure 3.17) . The amount of material removed below
El. 1490 ft had reached 368,000 cu.ft (Table 3.6). A minimum elevation of
1450 ft was recorded facing the centreline of the right chute at a
distance of 380 ft from the buckets. This represents a maximum scour depth
of 60-65 ft from the original plunge pool topography.
From 1984, the plunge pool surveys showed a rather stabilized scour
hole downstream of the spillway right chute. The scour hole surface (El.
1490 ft contour) was approximately 300 ft long and 200 ft wide and the
maximum volume of material removed below El. 1490 ft was estimated at
550.000 cu.ft. The scour hole invert (El. 1440-1450 ft) was located 350 to
400 ft downstream of the right chute and confined between the centrelines
of Bay 1 and Bay 2. An upstream progression of the scour hole towards the
left chute was observed in 1984 (Figure 3.18), which could have resulted
from the 1980 blasting and not been covered by the 1982 survey (Figure
3.17). The lowest plunge pool elevation (El. 1440 ft) was recorded in
October 1988 following the June 1988 spillway tests during which Gate 1
was fully open. No additional scour downstream of the right chute was
observed from the October 1997 survey after the passage of the largest
flood (May-June 1997) since construction of the dam (Figure 3.19).
The plunge pool bedrock downst ream of the left chute was surveyed in
1984 for the first time after the 1980 remedial works. The 1980 design
level of excavation (El. 1535 ft) was still intact in 1984 (Figure 3.18).
The following survey of the area was performed in October 1997 after Bays
3 and 4 were used extensively to pass the 1997 spring freshet. The
excavated focussing hole (El. 1535 ft) was 25-30 ft deeper over a 1200
sq.ft area downstream of Bay 3 (Figure 3.19). Scour was maximum opposite
to the limit between Bays 3 and 4 with a recorded El. 1503 ft. The minimum
elevation downstream of Bay 4 was El. 1523 ft.
The most common discontinuities are the joints and bedding plane
fractures typical of bedded sedimentary rocks (BCH Report No. H175S,
1988) . Fracturing in the shales occur at depths less than about a 100
feet. Under relief of pressure they tend to exfoliate along and across
their bedding and break down mechanically into hard buttons and cubes
(B.C. and B.B. Power Consultants Ltd. - Appendix A2.1, 1959). Also found
within shaly and coaly strata are several bedding plane seams of gouge and
breccia termed mylonites. The mylonite seams are believed to be planes of
weakness along which small shearing strains have taken place (BCH Report
No. H1756, 1988) . The seams occur as discontinuous lateral patches with
thicknesses from % inch to 4 inches. The underlying sandstones are
sparsely jointed rocks. The only joints of any significance in the thick
sandstone beds are local discontinuous bedding plane cracks (BCH Report
No. H1756, 1988). Cross fracturing is however present in the thinner
sandstone beds separating the shale units. The two predominant sets of
joints both dip steeply with one striking northwest and the other
northeast. A third, weaker set also dips steeply and strikes northerly.
The first spill event in 1972 was the most important in terms of
duration and daily peak outflow. The spillway was in continuous operation
for eighty-three days (13 June to 3 Sept. 1972) during which a total of
7.4 million acre-ft of water were spilled. The spillway discharge was
increased to 175,000 cfs (3 radial gates opened at 31.2 ft) and maintained
for eleven hours as part of spillway performance tests conducted on 10-13
July 1972. This is the highest discharge recorded at the site since the
beginning of operation and represents 57% of the radial gates capacity at
the Inflow Design Flood Level (El. 2209.5 ft).
The latest flood at the W.A.C. Bennett Dam in 1996 caused the largest
spill event to date with reference to the volume of water released. From
24 June to 17 August 1996, an approximate 9.3 million acre-ft of water was
discharged through the spillway radial gates. The daily average spillway
flows were maintained between 100,000 and 120,000 cfs for a total of
thirty days. The maximum discharge recorded during the 1996 spill was
124,000 cfs (two outside gates open at 29 ft and centre gate at 20.5 ft).
The radial gates are the primary means of spillway release. The
sluices gates were tested in June 1972, April 1983, and April 1984. The
sluices have never been operated with the radial gates open, nor have more
than three sluices ever been opened at the same time (BCH Report No.
H1756, 1988). The nine sluice gates are considered out-of-service and have
not been operated since 1984 (BCH Report No. OMSGMS/03, 2001) .
Before spillway operation, the riverbed in the zone of jet impact was
gently dipping downstream from approximate El. 1640 ft to El. 1630 ft
(Figure 3.25) . A spur dyke was built along the left side of the excavated
tailrace channel with a rockfill weir extending from its downstream end to
the right bank. The dyke was designed to contain spillway flows and
minimize the impact of the jet upon the tailrace flow. The weir was
provided as a temporary means of maintaining tailwater levels above the
cavitation limit of the generating units until the erection of the
downstream Peace Canyon Dam.
The plunge,pool was surveyed for the first time a year after the first
spill event at the site in 1972. The soundings of May 1973 showed a scour
hole more than 100 ft deep with the invert located near the centre of the
channel (Figure 3.26) . The hole, with the outer edge taken as the El. 1620
ft contour, measured about 750 ft in the direction of spillway flows and
600 ft across, in the direction of river flows. An approximate 260,000
cu.ft of material was removed from the riverbed below El. 162 0 ft
including about 12,000 cu.ft below El. 1540 ft (Table 3.9). Much of the
scoured material appears to have been deposited between the center and the
left bank of the river channel about 500 ft downstream of the center of
the scour hole (IPEC Report No. H692, 1973). The 1973 survey did not
include soundings of the weir area but photographic records indicate that
the weir sustained damage due to the 1972 spill event. The toe of the
tailrace channel dyke was, however, eroded during spilling.
The plunge pool was surveyed again in August 1996 following the
largest spring flood to occur at the site. The 1996 scour hole
configuration was essentially the same as in 1972, with the invert roughly
4 ft deeper (Figure 3.27). However, scour had progressed towards the left
bank so that the volume of material removed below El. 1540 ft was
increased to approximately 36,000 cu.ft. The 1996 soundings indicated that
the tailrace weir was for the most part eroded. To date no debris has been
removed from the river channel downstream of the scour hole.
The spillway operating gates [radial gates] are the preferred method
of release of non-power-related discharge (BCH L.O.O. 3P03-47, 2000).
Under normal operating conditions, the spillway radial gates should be
opened first and both radial and outlet gates should be opened or closed
in pairs by the same amount simultaneously.
The Inflow Design Flood (IDF) for the Revelstoke Dam is the Probable
Maximum Flood as established in 1975 as part of the preliminary design
studies (BCH Report No. 746, 1975) . The spillway (overflow bays and
outlets combined) can pass the flood peak of 251,000 cfs at reservoir El.
1885 ft.
The only extended spill goes back to initial reservoir filling. During
initial reservoir filling, from October 1983 to April 1984, the outlets
were operated at discharges varying from a few hundred cfs to about 35,000
cfs (BCH Report No. H1864, 1988). Discharge was increased up to 48,000 cfs
for a short period to test the spray condition in the river downstream of
the dam (ibid.). From April 1984, the excess water from the reservoir was
released primarily through the overflow bays.
The spill of August 1991 did not exceed the 70,000 cfs experienced in
1986 but caused considerable damages to the plunge pool and right bank
(see Section 3.4.5). The spillway discharge was increased from 16,000 cfs
to 59,000 cfs within a two-hour period, maintained at 59,000 cfs for eight
hours, and then cut back to 52,000 cfs for a further thirteen hours.
Spilling in 1991 lasted for a maximum of five consecutive days.
A first sounding survey covering the bulk of the plunge pool was
carried out on 15 May 1984. The lowest elevation recorded was El. 1392 ft
some 330-340 ft downstream of the concrete apron at the right of the
spillway centreline (Figure 3.33). This represents a maximum scour depth
of 58 ft since the beginning of spillway operation. The initial spilling
period of October 1983 to May 1984 removed an estimated 5 million cu.ft of
material from the plunge pool.
During the flood of August 10-11 [1991], the right bank protection
work failed resulting in a section of the powerhouse access road collapsed
into the plunge pool (BCH Report No. HYD.943, 1991). The following
bathymetric survey (22 Sept. 1991) reflected the accumulation of material
in the plunge pool with a minimum elevation (El. 1403 ft) more than 20 ft
higher than the previous survey lowest point (El. 1380 ft) (Appendix II,
BCH Drawing No. 212-C14-C5579). Overburden thicknesses range up to 50 ft
opposite the spillway with minimum thickness of 2 0 feet near the spillway
and rock shoreline (BCH Report No. N1315, 1992). Results of geotechnical
investigations after the August 1991 flood showed that there was no
significant change in the depth of the scour hole for most part of the
plunge pool since the 1986 spillway tests, except that the downstream
corner on the right side of the plunge pool has eroded to significant
depth due to the presence of a weak joint in the bedrock at that location
(BCH Report No. HYD.943, 1991). It is believed that the deep erosion in
the right corner of the plunge pool caused the jet to deflect towards the
right bank and undercut the underlying material thus resulting in the
collapse of the bank protection work (ibid.).
Table 3.1. Peace Canyon Dam / Spillway Characteristics
| GENERAL
Type of Spillway ! Gated Overflow Spillway
Total Spillway Width I 440 ft across Blocks SI to S7
Overall Spillway Length1 | 240 ft (Bays 1-2)
I 220 ft (Bays 3 to 6)
HEADWORKS
Overflow Bays i
!
Number of Bays 1 6
Piers Width 10 ft
Ogee Crest Elevation El. 1612 ft
Gates | 6 Radial Gates
Gates Dimension j 50 ft wide x 41.5 ft high
TERMINAL STRUCTURE
Energy Dissipation Flip Bucket
Bucket Radius 55 ft
Bucket Invert Elevation El. 1495 ft (Bays 1-2)
El. 1510 ft (Bays 3 to 6)
Bucket Lip Angle 30° (Bays 1-2)
2 0° (Bays 3 to 6)
Bucket Lip Elevation El. 1512.37 ft (Bays 1-2)
El. 1522.77 ft (Bays 3 to 6)
Bucket Width 116 ft (Bays 1-2 combined)
234 ft (Bays 3 to 6 combined)
HYDRAULICS
Normal Conditions !
Maximum Normal Reservoir Level El. 1650 ft
Tailwater Level with Four El. 1518 ft
Units Rated Discharge2 I
s
Flood Conditions
Inflow Design Flood | 330,200 cfs
Maximum Flood Level j El. 1652.4 ft
Maximum Tailwater Level2 j El. 1532 ft |
Notes. 1
1. Estimated from structural drawing of spillway sections (BCH Drawing No. 1007-C14-U4798). i
2. Estimated from current tailwater rating curve (BCH Drawing No. 1007-C14-D4954). i
Year Bays Total | Maximum Max daily Max daily Max daily
Period of days of discharge average average average
continuous operation discharge discharge discharge
spill sustained sustained
1 week 4 weeks
[cfs] i Ws] [cfs] [cfs]
1979 Total f 65 68,000 j 56,000 50,000 f 42,000
28 Oct.
to 3 - 4 | 62-64 21,000 | 15,500 12,500 11,000
31 Dec. 5 - 6 52 - 54 | 17,000 ! 14,000 12,500 | 11,000
1980 Total 107 | 60,000 I 60,000 49,500 | 36,000
1 Jan.
to |3 - 4 76 - 78 30,000 27,500 | 24,500 | 18,000
2 Apr. 5 - 6 48 - 51 26,500 j 18,000 | 13,500 9, 000
| Total 12 67,500 [ 47,000 [ 15,000 1
1981
• 24 July
to
1
I
3 12 25,000 j 22,500 15,000
|
4 7 | 25,000 22,500
5 Aug.
6 2 f 22,500 j 9,500 i
1 1 I
Total 15 | 75,000 f 45,000 | 29,000 1
1983
3 - 4 15 19,000 j 15,000 11,000 1
4-18 July
5 - 6 12 19,000 I 11,000 6,000
|
1984 [ Total 1 6 | 25,000 j 15,000 j
10-15 Oct. I 3 - 4 6 | 13,000 | 7,000
1 1 1
Total | 55 | 116,000 | 116,000 109,000 53,000
1996 i
23 June [ 55 [ 47,000 j 47,000 47,000 [ 47,000
1 3
to 4 54 31,000 j 31,000 31,000 8, 000
17 Aug.
5 - 6 40 - 41 27,000 21,000 18,000
Note.
1. The daily average discharge is the 24-hour average of spillway flows
(12:00AM to 11:59PM).
2. "Total" refers to total spillway flows without distinction for the bays in operation.
1" Survey- No. of Scour Scour : Maximum Scour Scour
| Approximate Volume Scoured Below:
Date Survey Hole Hole Scour Hole Hole
Data Invert Invert Depth2 Maximum Maximum | El. El. El. HiiT"
Points1 El. Location Length3 Width 4 I 1490 ft 1480 ft 1470 ft 1460 ft
[ft] [ft] [ft] [ft] [ft] j [cu.ft] [cu.ft] [cu.ft] [cu.ft]
i
Oct. 1700R
176 1477.4 28,000 100
1979 15 + 2 ON
15 Apr. 1 1635R
165 1458.2 50 310 220 997,000 318,000 79,000 300
1980 1 15+45N
5 Sept. 1700R
188 1461 45 300 305 1,080,000 335,000 67,000
1981 15+35N
Apr. -162 OR
N/A 1450 60 310 190 998,000 382,000 137,000 24,000
1983 -14+90
Oct. -1620R
N/A 1450 60 350 220 982,000 388,000 116,000 9, 800
1983 -14+95
9 Oct. 164 OR
230 1462 50 310 160 865,000 261,000 44,000
1985 14+80N
22 July 164 OR
130 j 1458 50 330 | 190 1,110,000 373,000 110,000 600
1 1987 14+75N
4 Aug. 1665R
434 | 1459.3 50 410 | 240 1,480,000 581,000 175,000 600
1996 14+45N 1
--
Notes.
1. Within the area of interest (600 x 600 sq.ft): Station 1300R to 1900R (Easting) by Station 14+00N to 20+00N (Northing).
2. Maximum difference in elevation with respect to the original plunge pool topography (Oct. 1979).
3. Outer edge of scour hole taken as the El. 1480ft contour; length in the direction of spillway flows.
4. Outer edge of scour hole taken as the El. 14 80ft contour; width across spillway bays.
i
GENERAL
| Type of Spillway ! Gated Overflow Spillway
Total Spillway Width j 322 ft across Blocks SW1 to
i SW4
Overall Spillway Length1 [ 330 ft (Bays 1-2)
| 2 50 ft (Bays 3 to 5)
HEADWORKS ,
Overflow Bays r
i
Number of Bays || 5
| Piers Width i 12 ft
| Ogee Crest Elevation fEl. 1679 ft
| Gates 5 Vertical Lift Gates
| Gates Dimension | 50 ft wide x 54.42 ft high
TERMINAL STRUCTURE
j Energy Dissipation Flip Bucket
Bucket Radius 60 ft
Bucket Invert Elevation El. 1545 ft (Bays 1-2)
El. 1555 ft (Bays 3 to 5)
Bucket Lip Angle 30° (all bays)
Bucket Lip Elevation El. 1555.54 ft (Bays 1-2)
El. 1565.54 ft (Bays 3 to 5)
Bucket Width 115.5 ft (Bays 1-2 combined)
17 7.5 ft (Bays 3 to 5 combined)
HYDRAULICS
Normal Conditions
Maximum Normal Reservoir Level El. 1730 ft
Tailwater Level with Three El. 1523 ft
Units Rated Discharge2
Flood Conditions
Inflow Design Flood ["376,900 cfs
Maximum Flood Level | El. 1732 ft
2
Maximum Tailwater Level j El. 1556 ft
Notes.
1. Estimated from structural drawings of spillway sections (BCH Drawing Nos. 224-C14-
D677/D678).
2. Estimated from current tailwater rating curve (BCH Drawing No. 224-C14-B1740).
Table 3.5. Seven Mile Dam / Historical Spills
Year | Bays Total { Maximum Max daily {Max daily Max daily
Period of days of | discharge average | average average
continuous | operation discharge {discharge discharge
spill ! sustained sustained
| 1 week 4 weeks
1
[cfs] [cfs] I [cfs] [cfs]
1979
5 Nov. Total1 30 48,000 29,000 26,000 15,000
to
2 8 Dec.
! Total 188 77,000 71,000 47,000 31,000
1980
20 Apr. 1 163 34,000 26,000 j 18,000 9,000
to I 2 116 33,000 33,000 | 17,000 11,000
23 July
| 3 I 4 7 15,000 12,000 j 12,000 11,000
Total [ 124 98,000 76,000 71,000 37,000
1981 j 1 | 124 30,000 24,000 16,000 7, 000
1 May
to 1 2 I 85 26,000 25,000 19,000 7, 000
14 July | 3 41 40,000 27,000 J 24,000
1982
| Total
I 1 - 2 | 141 - 93
141
| 34,000 100,000
33,000
| 64,000
j 24,000
j
|
40,000
11,000
2 8 Apr.
to | 41 | 26,000 25,000 ! 21,000 r
31 July 1 3
i !
I 4
| 39 j 8,000 8, 000 | 8,000
| Total 175 | 116,000 99,000 ! 82,000 | 60,000
1996 ! i [ 174 52,000 34,000 i '
27,000 J 21,000
12 Feb.
to 2 j 159 48,000 31,000 27,000 21,000
12 July 3 | 132 31,000 30,000 | 18,000 9,000
4
[
1 Total
[
1 128
88
|
10,000
114,000
9,000
112,000
9,000
j 107,000 F
9,000
99,000
! i
1997 I 1 | 127 40,000 36,000 | 34,000 | 30,000
15 Apr. _
to j. 103 37,000 36,000 J 34,000 j 30,000
17 July j 3
r~ "
| 31,000 31,000 i 31,000 29,000
1 86
! f
i 4
1 75 | 10,000 9,000 | 9,000 | 9,000
Notes.
1. Gate Operations Record incomplete for the year 1979. Spilling occurred over Bays 1 and 2
primarily.
2. Flows through Bay 1 and Bay 2 reached 64,000 cfs and 47,000 cfs, respectively, during
spillway testing on 30 May 1990.
3. The daily average discharge is the 24-hour average of spillway flows
(12:00AM to 11:59PM).
4. "Total" refers to total spillway flows without distinction for the bays in operation.
Table 3.6. Seven Mile Dam / Scour Hole Development
!
Survey- No. of Scour Scour Maximum Scour Scour
Approximate Volume Scoured Below:
Date Survey Hole Hole Scour Hole Hole
f
Data Invert Invert Depth2 Maximum Maximum El. El. El. El.
Points1 El. Location Length3 Width 4 1490 ft 1480 ft 1470 ft 1460 ft
[ft] [ft] [ft] [ft] [ft] [cu.ft] [cu.ft] [cu.ft] [cu.ft]
Before
-Line 1730
30 Oct. N/A 1475 . . . 29,000 2 , 100
1979 -Sta 8+50
14 Dec. Line 1600
71-45 1465 35-40 90 150 74,000 17,000 700
1979 Sta 9+30
7 Aug. Line 1615
25 1461.9 33-38 190 >175 196,000 43,000 3,200
1980 Sta 9+05
11-12
Line 1660
Aug. 42 1450 60-65 175 200 368,000 171,000 52,000 5,200
Sta 9+50
1982
20 Sept. Line 1680
N/A 1455 55-60 290 160 418,000 201,000 75,000 8,400
1984 Sta 9+60
15 Oct. Line 1660
55 1448 62-67 250 160 339,000 156,000 53,000 7,000
1986 Sta 9+55
Oct. Line 1635
61 1440 65-70 280 200 550,000 301,000 145,000 53,000
1988 Sta 9+35
21-26
Line 1670
Oct. 65-209 1450.1 55-60 280 210 520,000 269,000 116,000 31,000
Sta 9+25
1997
Notes.
1. Within the area of interest (350 ft x 200 ft): Line 1450 to 1800 by Station 8+00 to 10+00 (bathymetry)
(if second number) (600 ft x 200 ft): Line 1200 to 1900 by Station 10+00 to 12+00 (ground survey)
2. Maximum difference in elevation with respect to the original plunge pool topography (Before 30 Oct. 1979).
3. Outer edge of scour hole taken as the El. 1490 ft contour; length in the direction of spillway flows.
4. Outer edge of scour hole taken as the El. 1490 ft contour; width across spillway bays.
5. The survey performed on 30 April 1981 was not considered because taken after plunge pool blasting and biased by debris accumulation.
| GENERAL
1 Type of Spillway j Long Chute Spillway
Total Spillway Width [2 05 ft across Headworks
| Overall Spillway Length1 2400 ft
HEADWORKS
| Overflow Bays
Number of Bays 3
Piers Width 15 ft
j Ogee Crest Elevation El. 2145 ft
Gates | 3 Radial Gates
1 Gates Dimension [50 ft wide x 61 ft high
| Sluices
| Number of Sluices
Piers Width 3
8 ft
Sill Elevation El. 2105 ft !
| Gates [ 9 Vertical Lift Gates
Gates Dimension 6 ft wide x 8 ft high
TERMINAL STRUCTURE
Energy Dissipation Asymmetrical Flip Bucket
Bucket Radius Variable j
j Bucket Invert Elevation El. 1876 ft !
| Bucket Lip Angle 30° 1
Bucket Lip Elevation El. 1890 ft— — 1
i
Bucket Width 135 ft (lip length) |
!
| HYDRAULICS
| Normal Conditions
Maximum Normal Reservoir Level El. 2205 ft j
Tailwater Level with Ten El. 1655 ft j
Units Rated Discharge2
Flood Conditions l
Inflow Design Flood 307,200 cfs !
Maximum Flood Level El . 2209.5 ft I
Maximum Tailwater Level2 El. 1664 ft
Notes.
1. Estimated from structural drawings of spillway profile (BCH Drawing Nos. 1006-C14-U812,
1006-C21-U16/U32).
2. Estimated and extrapolated from Power Records data for the years 1996 to 2001.
Year Bays Total | Maximum Max daily Max daily Max daily
Period of days of discharge average average average
continuous operation discharge discharge discharge
spill sustained sustained
1 week 4 weeks
[cfs] [cfs] [cfs] [cfs]
1972
13 June
Total 85 175,000 167,000 85,000 15,000
to
3 Sept.
1974
23-31 July Total 36 27,000 25,000 18,000
3-29 Aug.
197 6
7-16 July Total 36 36,000 36,000 30,000
3-27 Aug.
r i98i
24 July
Total 13 49,000 45,000 14,000
to
5 Aug.
1983
10-30 May
2 8 June Total 68 87,000 80,000 60,000 7,000
to
11 Aug.
r 1984
7-13 Aug
Total 25 23,000 23,000
7-11 Sept.
10-15 Oct.
1996
2 4 June
Total 56 124,000 122,000 117,000 59,000
to
17 Aug. !
Notes.
1. Spillway discharges were released through the overflow bays primarily.
2. The daily average discharge is the 24-hour average of spillway flows
(12:00AM to 11:59PM).
3. "Total" refers to total spillway flows without distinction for the bays in operation.
1 Survey No. of Scour Scour Maximum 1 Scour Scour
Date Approximate Volume Scoured Below:
Survey Hole Hole Scour 1 Hole Hole
Data Invert Invert Depth2 j Maximum Maximum El. El. El. El. El.
1 Points1 El. Location Length3 Width 4 1620 ft 1600 ft 1580 ft 1560 ft 1540 ft
[ft] [ft] [ft] [ft] [ft] [cu.ft] [cu.ft] [cu.ft] [cu.ft] [cu.ft]
Dec.1967
N/A 1634
May 1969
15-16 160,150E
103 1519.6 -115 750 600 260,000 171,000 116,000 66,000 12,000
May 1973 5,22 ON
4 Aug. 160,190E
609 1516.2 -118 700 650 280,000 174,000 110,000 70,000 36,000
1996 5, H O N
Notes.
1. Within the area of interest (1000 ft x 1000 ft): 159,700E to 160,700E by 4,800N to 5,800N
2. Maximum difference in elevation with respect to the original plunge pool topography (Dec. 1967 & May 1969) .
3. Outer edge of scour hole taken as the El. 1620 ft contour; length in the direction of spillway chute (Northing).
j 4. Outer edge of scour hole taken as the El. 1620 ft contour; width perpendicular to spillway chute (Easting).
Table 3.10. Revelstoke Dam / Spillway Characteristics
| GENERAL
Type of Spillway [Long Chute Spillway
Total Spillway Width | 224 ft across Blocks SI to S3
Overall Spillway Length1 1300 ft |
I HEADWORKS
Overflow Bays
Number of Bays 2
Pier Width
Ogee Crest Elevation El. 1825 ft
Gates 2 Radial Gates
| Gates Dimension 45 ft wide x 59 ft high
Outlets |
Number of Outlets 2
| Pier Width
| Sill Elevation
1 10 ft
El. 1700 ft
Gates [ 2 Outlet Sector Gates
1 Gates Dimension 17.5 ft wide x 25 ft high
TERMINAL STRUCTURE
Horizontal Ski-Jump
J Energy Dissipation
| Bucket Radius 0°
Bucket Invert Elevation El. 1620 ft
| Bucket Lip Angle 0°
Bucket Lip Elevation El. 1620 ft
Bucket Width fiio ft
HYDRAULICS
1 Normal Conditions
Maximum Normal Reservoir Level El. 1880 ft
Tailwater Level with Four El. 1459 ft
Units Rated Discharge2
Flood Conditions
| Inflow Design Flood 251,000 cfs
[ Maximum Flood Level El. 1885 ft
| Maximum Tailwater Level2 El. 1481 ft
Note.
1. Estimated from structural drawings of spillway profile (BCH Drawing Nos. 212-C21-
U11/U4 7/U4 8) .
2. Final design values based on improved tailrace channel.
Year 1 Surface | Total Maximum 1 Max daily Max daily Max daily
Period of 1 Bays/ I days of discharge average average average
continuous | Outlets | operation discharge discharge discharge
spill sustained sustained
1 week 4 weeks
[cfs] [cfs] [cfs] [cfs]
19831 r
i
Oct. to Outlets 1 -90 48,000 N/A N/A N/A
31 Dec.
19842 Outlets 124 40,100 30,500 29,600 20,300
1 Jan. ? — ' — —
to ! Surface 1
9 May
3 2 24,200 24,200 8,000
| Bays
1985 Surface
! 6 33,600 31,100
14-19 Feb. j Bays
1986
25-28 July
Total 8 70,000
| ...
Spillway | Outlets j 5 15,000 i 10,800
Testing: f
11-14 Aug. Surface 1
l 55,000
Bays
| 3
1990 Surface !
j 5 18., 700 17,100
14-18 June Bays !
!
1991 j Surface
! 12
9-14 Aug. 59,200 35,500
18-21 Aug. 1 Bays
1997 Surface
| 4 18,400 | 18,300
2-5 Oct. Bays
j 1
Notes.
1. Gate Operations Record missing for the year 1983.
2. The spillway discharges were released through the overflow bays from 17 April to 9 May
1984 .
3. The daily average discharge is the 24-hour average of spillway flows
(12:00AM to 11:59PM).
4. "Total" refers to total spillway flows without distinction for the bays/outlets in
operation. ,
Survey No . o f Scour Scour Maximum Scour Scour
Approximate Volume Scoured Below:
Date Survey Hole Hole Scour Hole Hole
Data Invert Invert Depth2 Maximum Maximum El. El. El. El.
Points1 El. Location Length3 Width 4 1425 ft 1410 ft 1400 ft 1390 ft
[ft] [ft] [ft] [ft] [ft] [cu.ft] [cu.ft] [cu.ft] [cu. ft]
As
Excavated
114 1425
Extended
Area
110 210
| -
15 May
|"N/A 1392
44,52 0E
58 N/A 290 >1,345,000 310,000 50,000
;
1984 42,060N
Following j
44,63 0E
spill tests N/A I 1380 70 . 480 370 1,158,000 293,000 107,000 30,000
42,010N
on Aug.1986
22 Sept. 44,590E
1991
141 1403
42,170N
60 350 430 442,000 5, 000
! —
Notes.
1. Within the area of interest (700 ft x 500 ft): 44,300E to 45,000E by 41, 900N to 42,40ON.
2. Maximum difference in elevation with respect to the original plunge pool topography (As Excavated).
3. Outer edge of scour hole taken as the El. 1425 ft contour; length in the direction of spillway chute
4. Outer edge of scour hole taken as the El. 1425 ft contour; width perpendicular to spillway chute.
NORTH11
T ERR
PORTAGE
MOUNTAIN
PROJECT
( W.A.O. BENNETT
DAM)
•PEACE CANYON
DAM t
§
Uj
Uj 1500
B.R2
1400
El. 1612.00
SECTION ©
k
1600
[H
£
Sections A & B: 1007-C14-D4243
Section C: 1007-C14-U4321
SECTION © o
£
ki
I500
I400
19+00R 18+00R 17+00R 16+00R 15+00R
Station [ft]
13
m
OJ
n
cu 28 Oct. 1979ltO_2Apr. 1980
o
pj Qmax != 68,000 cfs
P Q = 50,000 60,000 cfs for 37 days
•c
o
3 25 July to 5 Aug.!. 1981
Qmax i= 67,500 cfs (Bays 3 4-6)
a Q = 40,000 - 47,000 cfsfor 4 days _(Bays 3-4-6)
si)
3
CO 4-18 July 1983
>d Qmax 75,000 cfs
H-
M A 40,.000 - 45.00C cfsfor 3 day;
M
s: 10-15 Oct. 1984
^pj Qmax 1= 25,000 cfs for 3 hr (Bays 3-4)
o
c
rt
l-h
M o
0
S
20 Jan 1987
Qmax = 25,000 cfs tor 1 hr (Bay 3)
ffi
(jd
o oo
o
113
ii ISJ
SD o
•O o
13*
vo
<1
vo
rt
O
to
o
o
24 June to 17 Aug.
U Qmax 115,000 -
C5
I Q > 110,000 cfsfor
1s
I o#
3
1
53 14Sn
^ <
^sv
-V
>
Q)
UJ 145q
1200
1100
c
o 1000
-t—>
03
CO
1 1 1 1 1 1
1200 1300 1400 1500 1600 1700 1800
Line [ft]
Notes. ROCK TYPES SYMBOLS
1. Geological Mapping Completed in August & October 1999
(Ref. BCH Drawing No. 224-C14-C1599) ARGILLITE - REWORKED, MASSIVE TO SLIGHTLY LAMINATED JOINT; INCLINED, VERTICAL
2. Topography As Surveyed in October 1997
ARGILLITE - REWORKED, HEALED SHEARS, GRAPHITIC \ V FOLIATION OR BEDDING
Figure 3.12. Seven Mile Dam / Plunge Pool Bedrock - Geological Mapping
SEVEN MILE DAM
PHOTOGRAPHS OF PLUNGE POOL BEDROCK
PLATE 2 -
ARGILLITE (MASSIVE)
•8
<u
cn
u
tn
>-
(D
J
'5.
CO
PLUNGE
POOL
ROCKFILL
GROINS
SCALE: fa - I I H—I
1890 FT
EL.2145 FT_
U
oJ
o
o
<o
6.000N
5.000N
LEGEND
Note. Peace River Coal Seam
Reference BCH Drawing Nos. Shale
Plan: 1006-C11-U6
Section A: 1006-C11-U14
Section B: 1006-C11-U19 Sandstone Water Line (~EI. 1650 ft)
SECTION B
Spillway Discharge [cfs]
•Ts-
27 Aug. 1976
cfs for 11 days
ui
CO
•g
o
I
«< -o
u>
o
o g
24 July to 5 Aug. 1981
45,000 cfs for 1 day 0 CD
§ m
-J
oo
PORTAGE MOUNTAIN PROJECT I PLUNGE POOL
~W BEFORE SPILLWAY OPERATION
G
1
o0
^ 65 0
•S 160Q
1
U 55(K
UJ
°Oo
CHUTE
iL
TERMINAL
STRUCTURE
HEADWORKS-
SURFFACE BAYS PLAN A N D PROFILE
„ 0U.I 80
SCALE: 160
I I=J FT
El. 1425
SECTIONS
El.1700 FT „„„ ,, 0h- I 80
SCALE: I | 160
t FT
HEADWORKS-OUTLETS CHUTE
Z
42,400- z ia:
d- i
3 ^
o i I- > -
t- UJ UJ UJ cc
a: a: t a. uj
or 9
3 ^ UJ o§
_i a. UJ
o >- o
42,300- 1 Grovel, cobbled
and boulders
with some sond
Sond, grovel, Gr
Coo
bvbe^lgro
Bveslond
cobbles 8 boulders
M If") send WL
i withsom^
42,200-
p i bou>lbdbeiress,agrsaavnedl
SuortzTte V
(GW) Sandy grovel gneiss
cn with some cobbles
Ouarl12 feldspar sw
a M&
H l ! Quartzite
^ I
I
'Hl'lU'I'I'll
Ouorlzite gneiss
iiif OH 74-2
42,100
DH 7 3 - 9
42,000-
>
oz o o „ IE
<<r> a: UJ
>
o o
CO o
UJ O
o u. 0
41,900-
Overburden IOO 1
Broken, loose,
weathered
v C v - 3 Quartzite gneiss
50 1538
Thick bedded
Quartzite gneiss
•Altered
'Quortzite gneiss
IOO t h i n bedded
Quartzite gneiss
\Morble
Thick bedded
Quartzite gneiss
Thin bedded
150 1437
Quartzite gneiss
D.H. 7 5 - 18
2QO
Note.
Reference BCH Drawing Nos.
Plan: 212-C14-U5499
Drill Logs: 212-C14-D499/D500
D502/D508
(
<1)
fD
M Oct. - pec. 1983: Outlets
01 Qmax = 48,000 cfs
rt
O 1 Jan. to 16 Apr. 1984: OuJets
W 17 Ap . to 9 lay 1904: Overflow Says
fD June & July 1984: Outlets, Overflo w Bay:
D
0) 14-19 Feb. 1^85: Overflow Bays
3 Qmax 33,000 - 34,000 cfs for 30 hrs
to
p- 25-28 July 1986: Outlets 11-14 Aug. 1986: Spillway ;reeboard Te:ts
Q = 10,800 :fs for '3 da^fe Qmax = 70,,000 cfs for < 15 min [Overfl 3w Bays & Outlets)
£
flj
O
e cn
rr T3
l-h 1
I-
O CD
£
W
><
&
O 14-18 June 1 390: Overflow Bays o
IQ -< Q = 17,000 f )r 2 days
H fD c
(1) Q)
-1 3 to
tr
9-14, 18-21, & 25 Aug. 1991: Overflow Bays
Qmax = 59,000 cfs "or 8 hrs
o m
LT) Q-52,000 cfs for 13 hrs * £
vo
•g. f 5
CO
u> W 5
QJ _
§
rt -ai
<
O O -a P
T3 ui IT >
to fD o
o O
o =3 UD
00
U)
NJ NJ
O
o O
o
o
S 8
8. sm
1
I S
REVELSTOKE DAM I PLUNGE POOL
BEFORE SPILLWAY OPERATION End Ski-Jump
Figure 3.34. Revelstoke Dam / Plunge Pool Topography As Surveyed Following Spillway Tests on August 1986
CHAPTER IV
COMPARATIVE ANALYSIS OF FACTORS AFFECTING PLUNGE POOL SCOUR
At Peace Canyon Dam, the flat bedding planes appear to be limiting the
depth of erosion in favor of lateral expansion of the bottom of the plunge
pool (BCH Report No. HY296, 1985). Following increased spillway discharges
of the 1996 spill, the surveyed plunge pool had extended over about 80 ft
in the flow direction but was not found to be deeper. The steeped profile
and flat base of the scour hole are indicative of the influence of bedding
planes and steep joints (Figure 4.1) . As well, the scour hole orientation
clearly defined from the 1996 soundings is closely associated with the
plunge pool geological features (Figure 3.4) . Orientation of the plunge
pool axis is similar to jointing in the foundations of Blocks SI to S4 and
of the closer jointed and previously eroded "hinge zone" under parts of
Block SI [refer to Figure 3.4] (BCH Report No. H1742, 1987). The Peace
Canyon plunge pool started to form in the bedrock weakness zone downstream
of spillway Bays 3 and 4 and developed in accordance with joints and
bedding planes features.
The main scour hole at Seven Mile Dam (downstream of spillway Bays 1
and 2) is confined and rather symmetrical in the upstream/downstream
direction, but its left side slope is much steeper than the right one
(Figure 4.1) . Were the plunge pool development to occur independently of
bedrock conditions, one would expect some lateral symmetry because
spillway Bays 1 and 2 have typically been operated together. In fact, it
appears that the protruding bedrock downstream of Bays 3 to 5 is more
resistant to scour than the riverbed downstream of Bays 1 and 2. In the
first two weeks of spillway operation, flows of 25,000-29,000 cfs through
Bays 1 and 2 combined (q=220-250 cfs/ft) scoured a hole roughly 35-40 ft
deep. Contrastingly, flows through Bays 3 to 5 were deflected by the
massive rock slab and the plunge pool had to be blasted and excavated
across Bays 3 to 5 to contain future spills (1980 remedial works). In
1997, the excavated level was scoured down by 25-30 ft after Bay 3 was
operated at approximately 30,000 cfs (q=500 cfs/ft) for a month. Scour
downstream of the spillway left chute is localized, whereas the main scour
hole from the right chute spills extends over an approximate 150 ft
radius.
The scoured plunge pool at Portage Mountain Project is deep and fully
confined (Figure 4.2), as expected by the lateral homogeneity of the
sedimentary rock and the similarity in strength of the shale/sandstone
strata. The scour hole is essentially circular in shape but with somewhat
straight segments oriented northeast and northwest, equivalent to the
predominant joint patterns. The side slopes of the hole are irregular but
the effect of the downstream dip of the stratification is observed towards
the left bank. Along the dipping direction of bedding planes (Figure
3.23), the plunge pool wall is steeper on the downstream face than on the
upstream face.
Each of the four dam sites has experienced at least one extended
spill:
• At Peace Canyon Dam, river flows were routed through the spillway
for about five months before commissioning of the generating units.
The major spill event of 1996 lasted for eight consecutive weeks.
• At Seven Mile Dam, continuous spill exceeding a month in duration
has been common during spring freshets of the 1979-2001 period. In
1996, the spillway was in operation for nearly half the year. In
1997, total spillway discharges were maintained above 100,000 cfs
for about four weeks.
• Three spill events at Portage Mountain Project have lasted more than
a month and occurred in 1972, 1983, and 1996. The 1996 spill event
was the most important in terms of continuous operation and volume
spilled.
• The only extended spill at Revelstoke Dam goes back to initial
reservoir filling, from October 1983 to April 1984. Subsequent
spills lasted at most six consecutive days.
The effect of spilling duration on the progression of scour is closely
related to the issue of scour rate. As discussed in the next section,
plunge pool performance data of the four studied sites seem to indicate
that scour progresses rather quickly and that extended spills are not a
condition to plunge pool development.
For each dam site, the spillway discharge is recorded every hour and a
daily spill value, averaged over a twenty-four-hour period, is derived.
The recorded magnitudes of peak flow and maximum daily average spill with
the associated plunge pool response are reviewed:
• The highest magnitude of spillway flows was observed at Portage
Mountain Project in 1972 with 175,000 cfs following which a scour
hole more than 100 ft deep had formed. The peak discharge was held
for eleven hours before which flow was maintained at 160,000 cfs
from which the daily average discharge of 167,000 cfs.
• The maximum flood discharge to be passed over the spillway at Peace
Canyon Dam and Seven Mile Dam is the same with 116,000 cfs (4 bays)
during the 1996 spring freshet. The discharge was maintained for
twenty-four hours at Peace Canyon as opposed to Seven Mile for which
the daily average spill was smaller. Plunge pool scour depths are
similar at both sites (50-60 ft) but were attained before 1996
following smaller spillway flows. In fact, the plunge pool bottom
elevation at Peace Canyon Dam was reached following the 1979/80
spill with a maximum recorded discharge of 68,000 cfs (4 bays). At
Seven Mile Dam, average spillway flows of 25,000-29,000 cfs through
Bays 1 and 2 combined scoured the bedrock down to 35-40 ft depth in
1979.
• The maximum discharge to be released from the Revelstoke spillway
was 70,000 cfs (held for about fifteen minutes) during the 1986
spillway tests. This is less than half the peak flow experienced at
Peace Canyon and Seven Mile dams and yet, the scour depth increased
and reached 70 ft following the tests. The maximum daily average
spill at Revelstoke Dam was 35,500 cfs in 1991, suggesting that
spillway flows greater than 40,000 cfs have been rather unusual and
of short duration.
Along with the magnitude of spillway flows, the width of flow should be
considered. Large spillway flows at Peace Canyon Dam and Seven Mile Dam
were released through four bays of about 60 ft width whereas spills at
Portage Mountain Project and Revelstoke Dam were routed through a single
chute with a terminal width of 135 ft and 150 ft, respectively. In
addition, variable spillway discharges from one bay to another are common
at Peace Canyon Dam and Seven Mile Dam due to the preferential use of
certain spillway bays. In any cases, the maximum spillway discharge per
width of flow (or unit discharge) was witnessed at Portage Mountain
Project. In Chapter V, the unit discharge is used to calculate scour
depth.
At Portage Mountain Project, a scour hole more than 100 ft deep has
formed following a single spill event in the early years of spillway
operation. The spill event lasted from 13 June to 3 September 1972 but
daily average spillway discharges greater than 100,000 cfs occurred on
five days only (non-consecutive). High flows spillway tests were performed
on one day during the 1972 spill and a peak discharge of 175,000 cfs was
held for eleven hours. During the 1996 spring flood, the historical peak
discharge (175,000 cfs) was not exceeded but spillway flows were more
constant and daily average discharges were maintained above 100,000 cfs
for thirty days. The 1996 scour hole configuration was essentially the
same as in 1972, with the exception that the scour hole invert had
progressed towards the left bank and scour depth was roughly 4 ft deeper.
This suggests that even a massive scour hole can form within a single
spill event and that scour can approach equilibrium after a few daily peak
flows.
From the available information, it appears that plunge pool scour can
progress rather quickly and that equilibrium conditions can be reached.
The concept of ultimate or equilibrium scour depth is well represented by
the Seven Mile plunge pool. Experience at Seven Mile Dam and Portage
Mountain Project also suggests that this scour limit can be attained
within a few days. Plunge pool scour can progress even more quickly
(within hours) as observed following the 1986 spillway tests at Revelstoke
dam.
Loose material removed from the scour hole may accumulate at the
downstream margin of the scour hole and form a bar deposit. Accumulation
of debris in the tailrace area following important spills was observed at
all four sites of study, especially in the early stages of plunge pool
development. The tailrace bar can raise the tailwater level and hence
limit the depth of scour for a given spillway discharge. Once the debris
are removed and the riverbed restored to its original elevation, scour may
progress further without increase in spillway flows. A summary of
observations on plunge pool development relating to tailrace improvements
at each dam site is presented:
| SEVEN MILE 1
I CANYON | PORTAGE
j Bays Bays 1 Bays | Bays j MOUNTAIN |REVELSTOKE
I 1-2 3-6 | 1-2 | 3-5 ! 1
| Spillway Characteristics
| Total spillway length i
| 240 I 220 j 330 | 250 | 2400 | 1300
L [ft]
i
Clear span at crest ! i
i 100 | 200 | 100 | 150 I 150 | 90
! w 0 [ft] i 1 s
s i
1 Clear span at bucket lip
1 116 j 234 j 116 1 178 | 135 | 150
1 W £ [ft]
] Differential head between i
| MNRL1 and bucket lip 138 127 j 174 164 315 | 260
I h Q [ft]
1 Total head between MNRL1 i
j and tailwater level [ 132' I 2 07 550 j 421
I H 0 [ft] i
r 1
I Bucket lip angle
| 20 | 30 [ 30
1 e [°] 1 30
I
| 0
I Jet impingement angle^ ! 3 I 23 1 3 7 | 39 | 49 ! 38
| 9' [°] i i \ f
I Notes.
| 1. MNRL: Maximum Normal Reservoir Level
i 2. Theoretical value; no allowance for energy losses on spillway face, flow aeration, and
j air retardation.
j 3. The bucket structure is submerged at maximum normal tailwater level (four units rated
1 discharge).
PEACE CANYON SPILLWAY SEVEN MILE SPILLWAY BAY 3 BAY 4 BAY 5
BAY 6i BAY 5! BAY 4! BAY 3 i
BAY 2iBAY 1 i
BAY 1!BAY 2
POWERHOUSE
n
PORTAGE MOUNTAIN
SPILLWAY
Figure 4.2. The Latest Plunge Pool Scour Configuration at Portage Mountain Project and Revelstoke Dam
200,000 200,000
PEACE CANYON DAM SEVEN MI LE DAM
150,000 150,000
Note. Note.
Data from 28 Oct. 1979 Data frcim 5 Nov. 1979
to 4 Aug. 1996 to 21 O ± 1997
—i—i—i—r -1—i—i—r —i—i—r
100 200 300 400 500 100 200 300 400 500
Number of days discharge is equalled or exceeded Number of days discharge is equalled or exceeded
200,000 200,000
MOUNTAIN PROJECT REVELSTOKE DAM
150,000 150,000
•6 1972 spill 85 days •8
1974 spill 36 days CD 1983/84 spill: ~200 days
<u O)
1976 spill 36 days 1985 spill: 6 days
O) 1981 spill 13 days —
o 100,000 O 100,000 1986 spill: 8 days
<2 1983 spill 68 days <2 1990 spill: 5 days
b b
1984 spill 25 days 1991 spill: 12 days
1996 spill 56 days Maximum = 70,000 cfs
'S
Q •TO
50,000 50,000 -
• Average : 35,500 cfs
Note. Note.
Data from 13 June 1972 Data frfam 1 Jan. 1984
to 4 Aug. 1996 to 22 S;pt. 1991
—I—I—I—r
100 200 300 400 500 100 200 300 400 500
Number of days discharge is equalled or exceeded Number of days discharge is equalled or exceeded
Figure 4.3. Spillway Flow Duration Curve of Each Site of Study
CHAPTER V
CONVENTIONAL ASSESSMENT OF PLUNGE POOL SCOUR
Hydraulic model studies were conducted for each site of study and
plunge pool scour tests were part of the investigation. The results of
model studies for Peace Canyon Dam, Seven Mile Dam, Portage Mountain
Project, and Revelstoke Dam are summarized and modelled scour patterns are
compared with observed plunge pool scour on site. The aim of this section
is not to identify the flaws of each model study, but to highlight that
great care must be taken in order to achieve reasonable results in the
prediction of plunge pool scour.
Case studies show wide variances in the accuracy of the predicted and
actual depths of scour (Wittier et al., Dam Foundation Erosion, 1995). The
reasons for the lack of accuracy are model specific formulas, site
specific application, fragmented results from multiple studies, and the
factors of geology and cohesive material properties (ibid.). The objective
of this section is to present some of the most common empirical formulas
for the assessment of maximum scour depth and evaluate their accuracy in
predicting past scour development at Peace Canyon Dam, Seven Mile Dam,
Portage Mountain Project, and Revelstoke Dam.
First, the empirical formulas selected for this study are listed with
brief comments of their derivation. Then, the accuracy of each equation is
evaluated through a back analysis of plunge pool development at the four
sites of study.
7. Mason (1984) and Mason and Arumugam (1985) presented two equations
for the prediction of ultimate scour depth by a plunging jet based
on the analysis of 26 sets of scour data from prototypes and 47 from
models. The two equations, which are dimensionally balanced and
respect the Froude scaling law, are generally considered state of
the art. The Mason A formula (7A) was developed as a best fit for
all of the model data and the Mason B formula was derived using both
model and prototype observations (7B) . The model data best fit is
now considered to be an acceptable upper bound for prototype scour.
The results of the back analysis using empirical formulas are combined
in Figure 5.16 in terms of scour depth below tailwater level. Differences
of 60-80 ft between computed depths for a unique set of hydraulic
conditions are common. The accuracy of each formula was assessed by the
ratio of calculated scour depth over observed depth, or relative error x e,
^calculated I ^observed
V = Sjx e
Note.
Units are imperial.
Nomenclature
| Maximum
error1
Minimum
error1
Mean
error1
Coefficient of
| variation2 [%]
Mean
error1
Coefficient of
variation2 [%]
!
I Veronese - 1937 | 4 .32 1.48 2 .19 | 40.8 1.4171 41. 63
j 1
j. 2 | Jaeger - 1939 j~ 1. 94 1. 05 1.52 17 . 7 j~ 1.3973 39.00
[ 3 1
i
Damle - 1966 j 2.32 0 . 78 1.14 39 . 7 | 0.7064 33 .16
i i
i
1 8
jWangShixia - 1987 1.78 0 . 72 1.14 37.4
|
1 9 1 Yildiz & Uziicek - 1994 | 2 . 62 | 0.67 1.23 46 . 9
f
1 Notes.
i 1. Relative error (jt ) = calculated scour depth (D calculaled) / measured scour depth (D observetl)
j 2. Coefficient of variation (K) = standard deviation (5 ) / mean error (jf ) [%]
! 3. Mean error and coefficient of variation obtained using the model data only (47 scour data sets).
i
•Source: P.J. Mason and K. Arumugam, "Free Jet Scour Below Dams and Flip Buckets", Journal of Hydraulic Engineering, ASCE, Vol. Ill
(Feb. 1985): 220-235, Table 3.
PEACE CANYON DAM
COMPARISON OF PROTOTYPE SCOUR AND MODEL SCOUR
c
o 1500
J->
ru
>
V
UJ
Prototype - October 1979
1450 -
Prototype - August 1996
Hydraulic Model
(Ref. BCH Report No. H715,
1970, Figure 20)
1400 T
~r r
t—|—i—i—r 1 1 1 1 1 1 1
'l n—I—I—I—|—I—i—I—i 'I ~i i i i i r
1300 1400 1500 1600 1700 1800 1900
Station N [ft]
Figure 5.1. Peace Canyon Dam / Comparison of Prototype Scour and Model Scour
SPILLWAY DISCHARGE = 120,000 C F S
(24,000 CFS PER BAY)
7 MILE PROJECT
PEND D'OREILLE RIVER
IUOO SCALE MODEL
Figure 5.3. Seven Mile Dam / Model Scour Patterns in Cohesive Bed
PORTAGE MOUNTAIN PROJECT
PLUNGE POOL SCOUR FROM MODEL TESTS
Figure 5.4. Portage Mountain Project / Plunge Pool Scour From Model Tests
fwi
4,500 y
1520 Notes.
1. Refer to Table 5.1 for the
mathematical expression.
2. Refer to Table 5.2 for details
1500 H
on the scour data sets.
3. Constant value of dm: 0.82 ft
4. Equation not applicable to the
1480 data sets SEV97-3 & SEV97-4 'On• <T>
d o
00 Q
IE
o z a.
4-> u
f
>U 1460 Q. *
a) *
* *
"O 1440
a» vO
LiD rvl
U r
CL <~o
cn Qv
E 1420 z Z
o o
u CL
CL
1400
1380 rv
en
21
CO
1360
1340 !"T"I J' I I I " ' I ' | I I I I | I I I I | I 1 I I j I I I I j ! 1 I I " J I I I ! |T T T T j I I I i | H " l"l |"T
I l l l | l l l 111111111111111
l | l l l
1340 1360 1380 1400 1420 1440 1460 1480 1500 1520 1540 1560
1520 - d Notes.
1. Refer to Table 5.1 for the
mathematical expression.
2. Refer to Table 5.2 for details
1500
on the scour data sets.
1480 - d
c
o
U-> 1460 - d
0
>3
CD
T3
1440
<u
Q.
E
o 1420
1400
1380 - d
1360 - d
1340 r M I I | I II I | ! I! I | I I I I | I I I I i
| i
IiII
I i 11 i i i i i i i i I
i I
i II | I I II | I I M | I I I
1340 1360 1380 1400 1420 1440 1460 1480 1500 1520 1540 1560
1520 - d Notes.
1. Refer to Table 5.1 for the
mathematical expression.
2. Refer to Table 5.2 for details
1500
on the scour data sets.
1480 - d
c
o
4-J
> 1460 - d
<u
T3 1440
CU
4->
Q. 1420
E
o
u
1400
1380 - d
1360 - d
1340 r M i i i i II i i i i i i i i i I I i i i i i i i i i i i i i i i i i i i i i i i II i i i i i i i i M i i i i i | i i i i | i i i i | i i i i | i i i i | II i i | I I i i | i i i i | i i M | i II i | i i i i
1340 1360 1380 1400 1420 1440 1460 1480 1500 1520 1540 1560
1520 - d Notes.
1. Refer to Table 5.1 for the
mathematical expression.
2. Refer to Table 5.2 for details
1500 - d
on the scour data sets.
1480 - d
c
o
'•*->
> 1460
_QJ
LU
T3
C1J 1440
CL
E
o 1420 - d
u
1400 - d
1380
1360
1340 [ i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i M i[ i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i | i i i i | i i i i | i i M | I i i i j i i i i
1340 1360 1380 1400 1420 1440 1460 1480 1500 1520 1540 1560
1520 -3 Notes.
1. Refer to Table 5.1 for the
mathematical expression.
2. Refer to Table 5.2 for details
1500
on the scour data sets.
1480
c
o
4-> 1460
ro
>
cu
TJ
O) 1440
O 1420
U
1400
1380
1360
1340 [ I I I ! | I I I I | I I I I | i I I I | I I I I | : I :< j I !
1520 -E Notes.
1. Refer to Table 5.1 for the
mathematical expression.
2. Refer to Table 5.2 for details
1500
on the scour data sets.
3. Wang Shixia coefficient:
Kr = 1.25 for PCN
1480 Kr = 0.90 for SEV
Kr = 1.25 for PMD
c Kr = 1.10 for REV
o<->
'•
ro
> 1460
cu
T3
CU 1440
4—>
CL
E 1420
o
u
1400
1380
1360
1340 i i i i i i M i i i i i i i i i i i i i i i i i i i i i i i ii i i i i i i i i i i i i i M i i i i M i i i i ii M i i i i i M i i ii i | i M i | i i i i | i M i | i i M | M M | i i i i | i i i i
1340 1360 1380 1400 1420 1440 1460 1480 1500 1520 1540 1560
1520 Notes.
1. Refer to Table 5.1 for the
mathematical expression.
m
2. Refer to Table 5.2 for details o
1500 - d oo rsi
on the scour data sets.'
z
u i—1
CL 1
1480 ~d
# cn
>
a to
o
j-J #
ro
> 1460
_gj ro#
LU VO
cntN
T3 1440 - d lJ-r*
<3J CL i
J-J CO
>
O
LU
CL m
E
o 1420
1400 - d
1380 - d
1360 - d
LEGEND
1 - Veronese
*
+
200 — 2 - Jaeger
3 - Damle
O 4 - Chian Min Wu
180 — X
•
5 - Martins
•
6 - Taraimovich
A
7A - Mason A
7B - Mason B
160 —
8 - Wang Shixia
140 —
CL
oj 120
T3
i_
Z!
O
u
in
TJ 100
<u
4—»
=3
CL
E
o
u
80
60
Notes.
1. Scour depth below tailwater level.
2. Refer to Table 5.1 for the list of
empirical equations and Table 5.2
40 — for the scour data sets.
3. Constant value of dm: 0.82 ft
4. Wang Shixia coefficient:
Kr = 1.25 for PCN
Kr = 0.90 for SEV
Kr = 1.25 for PMD
20 — Kr = 1.10 for REV
5. Outside values:
Veronese: (131, 256)
Mason B: (131, 597)
Mason B: (144, 564)
When formed in 1993, the main objective of the Dam Foundation Erosion
Study Team (U.S. Bureau of Reclamation, Golder Associates Inc., Colorado
State University, and other partners) was to develop a state-of-the-art
procedure for predicting the extent of plunge pool scour caused by
overtopping dams. The Erodibility Index Method (or hydraulic erodibility)
by Annandale (1994, 1995) was chosen as the working basis for the study.
Extensive research was conducted at the Hydraulic Laboratories of Colorado
State University (Fort Collins, CO) to supplement the existing knowledge
of plunging jet hydraulics and validate the method on different erodible
media. This chapter presents an evaluation of the Erodibility Index Method
in the assessment of observed plunge pool scour at Peace Canyon Dam, Seven
Mile Dam, Portage Mountain Project, and Revelstoke Dam. First, the
conceptual approach of the new technology is described. Then, the
methodology is applied to the four sites of study using past scour
conditions. A sensitivity analysis of key parameters is also performed to
complete the evaluation of the Erodibility Index Method.
K = Ms • Kb • Kd • Js (6.1)
Kd = JrjJa
where RQD is the Rock Quality Designation, Jn the joint sets number, Jr
the joint roughness number, and Ja the joint alteration number. The
constituent parameters of the Erodibility Index are rated with the use of
standard tables (Appendix I) . The generic expression for the stream power
P or rate of energy dissipation per unit area was presented in Chapter II
(Section 2.2.3) in terms of velocity V and energy loss A E such as:
The essence of the method that was developed to calculate the scour
depth by using the Erodibility Index Method entails a comparison between
Generally, the bedrock quality increases with depth. For instance, the
rebound fractures formed along bedding planes and relaxation joints
present in the Peace River Canyon (Peace Canyon Dam and Portage Mountain
Project) vanish with depth. Also, weathering of the argillite composing
the Seven Mile plunge pool is more important near the surface than at
depth. In this analysis, the rock mass quality is assumed constant with
depth in reason of a lack of information on the subsurface distribution of
geological parameters. The "typical" Erodibility Index is considered to be
representative of the bulk of the plunge pool bedrock.
in the plunge pool (power available for scour [PA~\) can be expressed as a
discretized function of the total head at various elevations (j , j +1,
etc...) along the centerline of the submerged jet (ibid.) :
dP A j yvjMj
(6.6)
dz 1000(zy -z j+ l)
The change in energy AEj between points j and j +1 represents the sum of
changes in velocity head, pressure head, and elevation head such as:
f..2 .2 A
Pj ~Pj +1 (6.7)
AEj = +
2g r
where V is the jet centreline velocity [m/s], p the static pressure [Pa],
unit weight of water [Pa/m]. The second and third terms of equation 6.7
cancel out and the change in energy AEj is equal to the change in velocity
head (first term). The dynamic pressure of the jet above hydrostatic
converges towards hydrostatic pressure as the jet travels deeper under the
plunge pool surface (Golder Associates, 2001). The vertical distribution
of power available for scour (P A) in the plunge pool is essentially
related to the submerged jet velocity profile. The level of accuracy in
the prediction of the latter is determinant in the evaluation of the
Erodibility Index Method.
Most past research work on the diffusion of jets has been confined to
submerged entry cases (Ervine and Falvey, 1987). Little attention has been
paid to the more complex problems arising from the influence of impinging
free turbulent jets and air entrainment on the diffusion process (ibid.) .
Theoretical expressions on computation of jet velocity decay in a plunge
pool presented here are derived from two distinct studies: the work by
Ervine and Falvey (1987, 1997) and the research conducted at Colorado
State University as part of the Dam Foundation Erosion Study (Lewis et
al., 1996; Bohrer et al., 1998). Ervine and Falvey (1987) investigated the
characteristics of a turbulent circular jet issuing horizontally and
plunging through the atmosphere and diffusing into a pool. The free-fall
jet was treated as a continuous mass with a solid core (undeveloped jet)
dissipating most of its energy in the plunge pool. Research conducted at
Colorado State University focused on simulating dam overtopping conditions
(rectangular jet) to characterize the behavior of a free-falling jet in
both undeveloped and developed conditions. Ervine and Falvey (1987)
suggested a relatively simple expression for the calculation of velocity
along the centreline of a plunging jet in a pool, based on an estimated 8°
of inner core decay and the assumption of linear velocity decay with depth
in the zone of established flow. Bohrer et al. (1998) considered an
empirical approach using dimensional analysis. From Bohrer et al. (1998),
the velocity decay of the jet as it progresses towards the bottom of the
plunge pool is a function of the jet velocity at impact with the pool
surface, the angle of impingement, the air concentration of the jet at
impact, and the gravitational acceleration.
Table 6.5 summarizes the computational steps in the prediction of the
jet centreline velocity profile in a plunge pool, and subsequently the
rate of energy dissipation. First, the flow depth and velocity at the exit
of the flip bucket are estimated using the Bernoulli equation. The
required basic hydraulic data are the spillway unit discharge, the energy
head at the exit of the flip bucket, and the flip angle. Once the initial
jet velocity is known, the free jet velocity upon entrance in the plunge
pool can be calculated from the ballistic equations knowing the head drop
from the bucket lip to the pool surface. However, this overlooks the fact
that the jet loses its coherence with the fall and is affected by air
resistance. A Dimensional Equation Technique (DET) was developed by Lewis
to estimate the velocity of a turbulent, developed jet by incorporating an
aerodynamic drag deceleration term into the Ervine and Falvey (1987)
expression for undeveloped jets (Lewis et al., 1998). The coherence of the
jet (undeveloped or developed) at impact with the pool surface was
identified by Bohrer et al. (1998) to affect the submerged jet velocity
decay. The determination of the jet breakup length is thus an important
step in the computation of the jet velocity profile. Once the jet velocity
profile is known, equations 6.6 and 6.7 are used to derive the
distribution of the power available to scour.
The Erodibility Index Method was applied to the four sites of study
based on the best information available at the time. Considering the
extended range of Erodibility Index that characterizes each plunge pool
bedrock and the uncertainties involved in the jet hydraulics computations,
a sensitivity analysis of key parameters involved in the scour depth
analysis is performed. The parameters which are further investigated based
on their respective influence on scour depth predictions are the
Erodibility Index, the jet velocity profile, the jet impact velocity, and
the jet air concentration at impact with the plunge pool surface.
The predicted elevations of maximum scour depth for the expected range
of Erodibility Index (low, typical, and high rock mass quality) are
presented in Table 6.7. For each site, given the extended range of
Erodibility Index that characterizes the plunge pool bedrock, the power
The sensitivity analysis confirms that the jet velocity at impact with
the plunge pool surface is an important parameter in the assessment of
maximum scour depth using the Erodibility Index Method. However, in the
cases of Peace Canyon and Seven Mile, the effects of a diminution in jet
impingement velocity are rather minor on the scour depth predictions. In
this study, the uncertainties regarding the estimation of jet impact
velocity were primarily directed toward the sites of Portage Mountain and
Revelstoke because of the lengthy plunge of the spillway jet.
Surprisingly, the Erodibility Index Method underestimates the maximum
scour depth elevation of both plunge pools although using the maximum
theoretical value of jet impact velocity.
6.4. EVALUATION
BEDROCK - SHALE
Low ] Typical High
Unconfined Compressive
Strength (UCS)1 5,000 psi 10,500 psi 17,000 psi
Ms 34 72 117
2
Rock Quality Designation 70% 90% 95%
RQD 70 90 95
Number of Joint Sets 3 + random 3 3
Jn 3 .34 2 . 73 | 2 . 73
Roughness of Joint Open Discontinuous i Discontinuous
Jr 1. 0 4.0 [4.0
Alteration of Joint Crushed rock filling Unaltered j Unaltered
Ja 4.0 1. 0 i 1. 0
-Main Discontinuity N30-40 °/90 ° N60°/2° N60°/2°
-Dip Direction With flow With flow
-Apparent Dip in
Direction of Flow 90° 1° i 1°
-Ratio of Joint Spacing 1:1 1:2 1:1
Js 1 . 14 1 . 33 1 . 50
K=Ms»(RQD/Jn)•(Jr/Ja).Js | 203 12,600 24,400
r
P R = K0'75 [KW/m2] 53 . 8 1190 1950
Notes.
1. Based on Laboratory Rock Testing Program of 1959 5 tests-dry), 1967 (4 tests-dry), and
1975 (2 tests-dry) (BCH Report No. 354, 1959; BCH Drawing Nos. 1007-C14-C3854 &
1007-14-D424 9).
2. Based on 502 ft of core logging from 1977-78 post- grout drilling of the dam foundation
(hole series STH); the statistical distribution is presented below.
RQD Distribution
400
350
300
250
200
150
100
50
0
£ £ £
§ £ §
RQD [%]
BEDROCK - ARGILLITE
Low Typical High
Unconfined Compressive
Strength (UCS)1 5,000 psi 20,000 psi 33,000 psi
Ms 34 138 228
2
Rock Quality Designation 60% 90% 95%
RQD 60 90 95
Number of Joint Sets 3
4 3 + random 3
Jn 4 . 09 3 . 34 2 . 73
3
Roughness of Joint j Smooth planar Smooth undulating Discontinuous
Jr | 1.0 2.0 4.0
Alteration of Joint3 Graphitic Slightly altered Unaltered
Ja 4.0 2. 0 1.0
-Main Discontinuity N110-120°/4 0-4 5° N110-120°/40-45° N110-120°/40-45°
-Dip Direction With flow With flow With flow
-Apparent Dip in
Direction of Flow 40° 40° 40°
-Ratio of Joint Spacing 1:4 1:2 1:1
Js 0.46 0.49 0 . 53
K=Ms»(RQD/Jn)•(Jr/Ja)»Js 57 . 4 1, 820 16,800
P R = K0'75 [KW/m 2 ] 20 . 8 279 1480
Notes.
1. Based on Laboratory Rock Testing Program of 1973 (8 tests) (BCH Report No. 750, 1975).
2. Based on 414 ft of core logging from 1973 exploration drilling in the riverbed argillite
(DH73-1A/3/8/10); the statistical distribution is presented below.
3. Reference BCH Report No. PSE362 - Appendix G, 2001.
RQD Distribution
200
£ 150
o>
g 100
o 50
o
0 =F
5s $§
9
£
£ §
.
S
££
RQD [%]
BEDROCK
Low 1 Typical High
Unconfined Compressive 1
Strength (UCS)1 10,000 psi 22,000 psi
f 18,000 psi
Ms 69 j 124 152
Rock Quality Designation 50% | 80% 95%
RQD 50 ; 80 95
Number of Joint Sets 4 3 + random 3
Jn 4 . 09 3 . 34 2 . 73
Roughness of Joint Open Open Discontinuous
Jr 1. 0 1. 0 4.0
Alteration of Joint Crushed rock filling Surface staining Surface staining
Ja 4.0 1. 0 1. 0
-Main Discontinuity N132°/10° N132°/10° i N132°/10°
-Dip Direction With flow With flow With flow
-Apparent Dip in
Direction of Flow 10° 10° 10°
-Ratio of Joint Spacing 1:4 1:1 1:1
Js 0 . 98 1.25 1 .25
K=Ms»(RQD/Jn)•(Jr/Ja)«Js 207 3 , 710 26,400
P R = K0'75 [KW/m2] 54 . 5 476 2070
Note.
1. Based on Laboratory Rock Testing Program of 1958 (4 tests-dry), 1959 (6 tests-dry), and
1965 (33 tests-dry); the statistical distribution is presented below (BCH Report No. 150,
1958; BCH Report No. 31, 1959; BCH File No. 003805546, 1965).
10
8
6
4
2
0
to O <V V- Co % iv >
V <b
UCS [x1,000 psi]
10
8
6
4
2
0
<b <v V- Co 'b is iV > A) ib is
^ <6
( BEDROCK SOIL
| Low Typical | High j Typical
Unconfined Compressive
Strength (UCS)1 3,000 psi 9,000 psi 20,000 psi SPT=30-50
Ms 21 62 138 0 . 19
Rock Quality Designation 2
5% 10% 80% 5%
RQD 5 10 80 5
Number of Joint Sets r " 3 + random 3 5
Jn 5 . 00 3 .34 2 . 73 5 . 00
Roughness of Joint Smooth planar Rough planar Rough undulating
Jr 1.0 1.5 3. 0 Jr/Ja=0.6
Alteration of Joint Graphitic,>5 mm Slightly clayey Surface staining (<f> = 30°)
Ja 13 . 0 3. 0 1. 0
j -Main Discontinuity N56°/26° N56°/26° N56°/26°
-Dip Direction With flow With flow With flow
-Apparent Dip in Flow
Direction 5° 5° 5°
-Ratio of Joint Spacing 1:4 1:2 1:1
Js 1 . 09 1 .23 1 .39 1 . 00
K=Ms*(RQD/Jn)•(Jr/Ja)*Js 1 . 76 114 16,900 "oTTi
PR = K - 0 75 2
[KW/m ] 1 1.53 34 . 9 1480 0 . 183
Notes.
1. Based on Laboratory Rock Testing Program of 1972 (16 tests), 1976 (42 tests), and 1978 (28
tests); the statistical distribution is presented below (BCH Report No.664, 1973; BCH File
No.15-2-57, 1976; BCH Report NO.H1204, 1980).
2. Based on 905.5 ft of core logging from exploration drilling in the plunge pool
surroundings (DH73-8/9, DH74-1A/2, DH75-17/18/19/20/21, and DH76-29/32/36); the
statistical distribution is presented below.
3. For cohesionless granular material, P„ = 0.480K0'44 [KW/m2] (Wittier et al. , 1998).
UCS Distribution
(0 20
in
« 15
10
o 5
o 0
z
$
to
o
<V
$ <V
UCS [x1,000 psi]
RQD Distribution
300
200
100 -
0
o Q .O ,S> ,§>
O ^
"> Is y
£ CO
£lb Q>
Kd tCV5 ^e> fr <c0i £
C5 ,
RQD [%]
Table 6.5. Jet Hydraulics - Computational Steps
Fo=Vol4gd~o
4. Compute the jet velocity at Undeveloped jet J Ervine et
impact with the plunge pool surface, ! al., 1997
Vi. V,=^+2gHd
Developed jet Lewis et
al., 1996
V ;=^+2gH d -RF
RF = ^ Cd(palpjH dl<S>)vZ
5. Estimate the jet thickness at Ervine et
impact with the plunge pool surface, d, = d„ al., 1997
di.
V = V: for
Developed jet
In = 0.638 In
V = V, for In
0.638
Notes.
* Assumed energy loss on spillway surface of 5% for Peace Canyon and Seven Mile and 10%
for Portage Mountain and Revelstoke.
** Estimated turbulence intensity (Tu) of 5% for flip bucket jets.
*** Calculated from gravitational considerations only.
Nomenclature
Bi [--] = Ratio of air to water flow rate entering the plunge pool
C [--] = Jet turbulence parameter
Cd [--] = Drag coefficient
Ci [--] = Air concentration of the jet at impact with the plunge pool
surface
do [ft] = Initial jet thickness (at the exit of the flip bucket)
di [ft] = Jet thickness at impact with the plunge pool surface
E [ft] = Specific energy available at the exit of the flip bucket
Fo [--] = Initial Froude Number of jet
g [ft/s2] = Gravitational acceleration
Hd [ft] = Head drop from the bucket lip to the plunge pool surface
2
q [ft /s] = Spillway unit discharge (discharge per unit width)
L [ft] = Distance along the jet centreline trajectory beneath the
water surface
Lb [ft] = Jet breakup length
RF [ft/s] = Retardation factor (aerodynamic drag deceleration term)
Tu [--] = Turbulence intensity of jet
Vo [ft/s] = Initial jet velocity (at the exit of the flip bucket)
Vi [ft/s] = Jet velocity at impact with the plunge pool surface
V [ft/s] = Underwater velocity along the jet centreline trajectory
y [ft] = Elevation head at the exit of the flip bucket
0 [°] = Angle of flip bucket exit
® [ft] = Diameter of a sphere having the same volume as a water drop
pa [lbm/ft3] = Air density
pw [lbm/ft3] = Water density
Table 6.6. Jet Hydraulics - Basic Parameters
Scour q E 9 Vo do Hd ( Lb Hd/Lb Vi RF di 1Ci 1 6'
Data S e t 1 | [%]
[cfs/ft] [ft] [ft/s] [ft] [ft] [ft] (jet coherence) [ft/s] [ft/s] [ft]
| [°]
[°]
PCN96-5/6
| 810
| 360
120
| 120
20
20
84 . 3
| 86 . 3
9.0
3.9
8.6
5 . 9
| 133
| 62
0.06
0.09
(undeveloped)
(undeveloped)
| 87.5
| 88.5
| 9.4
4 .1
16
20
25
23
|i
SEV97-1/2
| 570
| 620
150
164
30
30
J 96.2
| 101
I 5.1
5
30.5
23 . 6
!81
i 8 5
0.3 8
0.2 8
(undeveloped)
(undeveloped)
106
108
|
j
5 . 7
6.0 , 30
33 38
36
'4
1
I
SEV97-3 520 154 30 f~98 . 0 4.6 33.2 1 73 0.4 6 (undeveloped) | 108 j | 5.0 35 38
s
§
SEV97-4 100 154 30 I 99.4 0 . 9 31.0 | 15 2.08 (developed) 1 109 | 125 1.0 54 38
?
PMD72 [ 124 0 284 30 j 133 8 .0 244 | 129 1.89 (developed) j 183 j 519 | 7.9 52 51
1
!55
PMD96 900 270 30 130 6.0 | 233 98 2.3 9 (developed) | 179 533 5 . 9 51
REV84
s
I 190 195 0 | 112 1. 7 5 173 29 I 5.8 9 (developed) 154 431 1.5 | 67 43
REV86 J 330 j 233 122 2 .7 J" 1 6 1 " | 46 j 3.51 (developed) 159 | 430 2.4 40
0 6 1
1 1
| Notes.
| 1. Refer to Table 5.2 for a complete description of hydraulic conditions in each of the scour data sets.
| 2. Refer to Tables 6.5 and 5.1 for a description of parameters.
Table 6.7. Sensitivity Analysis of Erodibility Index
SEV8 0-1/2 El. 1474 ft | El. 1504 ft El. 1513 ft El. 1462 ft
-2.
Figure 6.1. Conceptual Approach of the Erodibility Index Method in the Assessment of Plunge Pool Scour
PEACE CANYON
1540 -
S u b m e r g e d J e t Velocity Profile
1530 -
1520 -
1510 -
1500 -
1490 -
1480
.9 1470
(O
jj 1460 Scour Data Tailwater Impact
1450 Set Elevation Velocity
1410
1400 I I I II I I I I I I I I I I I II I I l I II II I I I I I I II I I I I I I I I I I II I II I I
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Jet Centreline Velocity [ft/s]
1540
S u b m e r g e d J e t S t r e a m P o w e r Profile
1530
1520
1510
1500
1490
1480 —
.1 1470
(O
jy 1460 Scour Data Maximum Scour Depth El.
1450 Set Predicted . Observed
1410
1400 | i i i i | i i i i | i i i i | i i i i | i i i i i| |II
i iiiii||iiiiiii i| |i IIi ii ii | i
0 100 200 300 400 500 600 700 800 900 1000 1100 1200
Stream Power [KW/m2]
Figure 6.2. The Erodibility Index Method Applied to the Peace Canyon
Plunge Pool
SEVEN MILE
1540
S u b m e r g e d Jet Velocity Profile
1530
1520
1510
1500
1490
1480
c
_o 1470 Scour Data Tailwater :—
Impact
a> 1460 Set Elevation Velocity E—
LLI
SEV79-1/2 El. 1516 ft Vi 109 ft/s E_
1450 SEV80-1/2 El. 1527 ft Vi 107 ft/s E
1440
SEV82-1/2 El. 1528 ft Vi 106 ft/s E—
SEV97-1/2 El. 1535 ft Vi 108 ft/s E
1430 SEV97-3 El. 1535 ft Vi 108 ft/s
SEV97-4 El. 1535 ft Vi 109 ft/s i
1420
1410
1400 111111111111111111111111111111111111111
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
1510
1500
1490
a 1480
c
_o 1470
Scour Data Maximum Scour Depth El.
J3 1460 Set Predicted Observed
1410
1400
i | > i i i | i i i i | i i i i | i i i i | ii i| II
i |i II
i ii i
| |i ii Mi i
i |
| i
i i i i
100 200 300 400 500 600 700 800
900 1000 1100 1200
Stream Power [KW/m2]
Figure 6.3. The Erodibility Index Method Applied to the Seven Mile Plunge
Pool
PORTAGE MOUNTAIN
Figure 6.4. The Erodibility Index Method Applied to the Portage Mountain
Plunge Pool
REVELSTOKE
1460 —
_—
1450 —
Submerged Jet Velocity Profile
1440
1430 E—
1420 E—
1410 - -
E-
1400 —5 :—
ET - i
1390 —z E—
a 1380
o
'4-t
>
(U 1370
dJ
UJ 1360 -
1320 —
i—
1310 E—
1300 i
M i i | M i i | M 11 | 1 1 1 1 | 11111111111111111
111 |11 1 | 1 1 ! 1 | 1 1 1 1 | 1 1 1 1 | 11111111111111111111111
111| 1111| 1111|1 1
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Jet Centreline Velocity [ft/s]
1450 —-,
:
Submerged Jet Stream Power Profile i
1440 -
E
1430 i
1420 E—
:—
1410
i
1400
g 1390 E
-o
r
c 1380
o 73
<
>o 1370 - II E
Ul z—
33
LU 1360 —i lo -
ii
1340 —i * Set Predicted Observed
E—
1330 REV84 El. 1397 ft El. 1392 ft ~. .
1310 —
E—
I
1300
i i i i | I Ii i j i i i i i i i i | II i i | i i i i | M i i | i M i | i i i i | i II i | i i M | M i i
c 100 200 300 400 500 600 700 800 900 1000 1100 1200
Stream Power [KW/m2]
Figure 6.5. The Erodibility Index Method Applied to the Revelstoke Plunge
Pool
1620 -q
1600 -=
1580 -
Notes.
1560 - 1. Refer to Figures 6.2 to 6.5
for estimates of maximum scour
depth elevation.
1540 2. Refer to Table 5.2 for details
on the scour data sets.
1520
c
.2
ro 1500
>
QJ
m
T3 1480
oi
Q.
E
o
U
1340 I I I I | I I II | I I I I | I II I | II II | I I I I | I I I I | I I I I | I I I I | I I I I | I II I | I I I I | I I I I | I II I | I
1340 1360 1380 1400 1420 1440 1460 1480 1500 1520 1540 1560 1580 1600 1620
I I I I | I II I | M I I | I I I I| I I I I | I I I I| I
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Jet Centreline Velocity [ft/s]
1660 -q
1640 —
1620 -
1600 -
1520 -
Observed El. 1516 ft
1500 —
1480 —
1460 I I | I I I I | I I I I | II I I | I I I! | I I I I | I I I I | I I II | I
0 100 200 300 400 500 600 700 800 900 1000 1100 1200
Stream Power [KW/m2]
1460
1450
1440
1430
1420
1410
1400
1390
c
o 1380
DATA SET: REV86
(D
1370 DEVELOPED JET
5
1360
1300
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Jet Centreline Velocity [ft/s]
1460
1450
1440
1430
1420
1410
1400
1390
c 1380
o Observed El. 1380 ft
fD 1370
£
1360
1350
Predicted Maximum Scour Depth El.
1340
Ervine and Falvey 1987: El. 1432 ft
1330
Bohrer et al. 1998 (Undeveloped): El. 1389 ft
1320 Bohrer et al. 1998 (Developed): El. 1399 ft
1310
1300
i i i i i i i i i i i i i i i i i i i i i i
100 200 300 400 500 600 700 800 900 1000 1100 1200
Stream Power [KW/m2]
Jet Centreline Velocity [ft/s]
1530
1520
1510
1500
1490
1480
c
_o 1470
JS 1460
LU
1450
1440
1430
1420
1410
1400
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200
Jet Centreline Velocity [ft/s]
1540
1530
1520
1510
1500
1440
1430
1420
1410
1640 —
1620
1600 —
£7 1580 -
.1 1560 -
(D
>
CL>
1540 — |
1520 -
1500 —
1480 —
0 100 200 300 400 500 600 700 800 900 1000 1100 1200
Stream Power [KW/m2]
Jet Centreline Velocity [ft/s]
7.1 LIMITATIONS
For each plunge pool, the scour hole development was analyzed by means
of sounding surveys which involve some uncertainties. Although the depth
measurement from an echo sounder can be quite precise (within a foot), the
plan positioning accuracy can be more challenging depending on the method
used. The Global Positioning System technology was not available when the
first surveys were carried out and is not always functional in deep canyon
area. When a tag line with shore based control points is used, measuring
errors of approximately ± 3-6 ft can be encountered. The existing plunge
pool surveys for each site were often performed by different crews with
different instrumentation and means of positioning. The signal recorded by
the sonar beam is a reflection of the river bottom, without distinction
between sound bedrock and overlying loose rock or soil. The amount of
loose material trapped within the scour hole, if any, is unknown. Finally,
the sounding survey coverage can be limited by turbulent waters because
the excess of air bubbles interferes with the technology. Some limitations
with regard to plunge pool surveys are characteristic to each site in this
study:
This study on plunge pool scour was based on the best information
available at the time. The limitations discussed above are common when it
comes to investigate plunge pool scour on prototypes. Complete reviews of
plunge pool performance with time and with respect to bedrock geology and
spilling history are seldom done because accurate details of spillway
discharge, head drop, tailwater depth, plunge pool geology, and scour
depth are difficult to come by. This study is very valuable in that
regard.
7.2 CONCLUSIONS
The main objective of this study was to evaluate the Erodibility Index
Method for estimating plunge pool scour and see if there is an improvement
in accuracy when compared to conventional methods such as empirical
formulas and hydraulic model studies. The results of downstream scour
tests from small-scale model studies were comparable to prototype
observations in one of the four study cases (Section 5.1). The main
difficulty in modelling plunge pool scour in laboratory is the appropriate
scaling of bed material. The problem when using empirical equations to
estimate the maximum scour depth is the variability in results for a
single data set and the inconsistency of a given formula from one site to
another. Ten well-known formulas were tested and the standard error of
estimate varied from 16 ft for the Damle equation to 70 ft for the
Veronese expression (Figures 5.6 to 5.15). Despite a tendency for
underestimation, the Damle empirical formula was seen to give the best
combination of precision and accuracy in the prediction of plunge pool
scour depth at the four sites of study; accuracy of more than 60% should
however not be expected. The performance of the Erodibility Index Method
in the assessment of maximum scour depth was disappointing and did not
outclass the conventional methods. Even supposing an accurate bedrock
characterization and improved equations for the computation of jet
velocity profile, the use of the Erodibility Index Method is questionable.
The main weakness of the approach is that the vertical distribution of
power available for scour in the plunge pool is essentially related to the
submerged jet velocity profile which do not reflect the changing magnitude
of spillway discharges. The erodibility threshold relationship, which
forms the basis of the approach, was also derived from a majority of
observations on auxiliary earth channel spillways. The overall performance
of the Erodibility Index Method in the assessment of maximum scour depth
for four distinct plunge pools was characterized by a generalized tendency
for underestimation and a standard error of estimate of 53 ft.
At this time, no new technology has been proven reliable for the
assessment of plunge pool scour. The Erodibility Index Method, even with a
refinement of equations to describe the jet hydraulics, is questionable.
Current effort is directed towards the numerical analysis of hydraulic
transients propagating through the discontinuities in the rock mass.
Simoes and Vargas (2001) proposed a hydromechanic, coupled analysis, using
the finite element method for the hydraulic problem, involving flow and
wave propagation in the fractures, and discrete element method for the
mechanical problem of block equilibrium. Bollaert (2002) (reported by
Schleiss, 2002) based his work on fully transient water pressures in rock
joints and developed a new model for the evaluation of the ultimate scour
depth which includes the hydrodynamic fracturing of closed-end rock joints
and dynamic uplift of rock blocks. Until these new approaches are tested
independently on an extensive database of known prototype scour
conditions, one must rely on the conventional methods of prediction. In
the feasibility design stage of a project, the scour tests results from
the hydraulic model studies should be used in conjunction with empirical
equations. Considering the great variability offered by the existing
equations, a careful selection should be based on the applicability of the
formula (ski-jump spillway vs free overfall) and its performance in
predicting scour depth in similar geological conditions. The engineering
decision could be based on a statistical analysis of results obtained from
the chosen empirical formulas, reinforced by the intuitive knowledge of
hydraulic action in the plunge pool gained from the small-scale model
studies. For an existing project with unforeseen plunge pool development,
complementary hydraulic model studies in which the bed material is
calibrated to the observed scour configuration are suggested to evaluate
future scour progression in response to higher spillway flows.
• Since 1984, the major scour hole at Seven Mile Dam did not progress
either in depth or extent despite the reach of new historical limits
from the 1997 spill. The maximum spillway discharge recorded on site
reached 116,000 cfs which represents 31% of the Inflow Design Flood.
The 1997 survey of the Seven Mile plunge pool indicated minimum
elevations of 1450 ft and 1503 ft downstream of the right and left
chutes, respectively. The major scour hole is confined and effective
in containing spillway flows from the spillway right chute, whereas
the plunge pool configuration downstream of the spillway left chute
is not fully developed to contain a full discharge from the three
bays. The expected plunge pool bottom elevation to result from the
Inflow Design Flood using the Damle equation (El. 1461 ft) is above
the current low. The small-scale model studies suggest a minimum
bedrock elevation around El. 1450 ft downstream of the spillway left
chute.
The Portage Mountain plunge pool was submitted to large spillway
flows of 175,000 cfs (57% of the IDF) in the early years of
operation (1972). The plunge pool has remained relatively stable
since and the lowest elevation recorded from the 1996 soundings is
El. 1516 ft. The plunge pool is deep (more than 100 ft) and confined
and is therefore efficient in containing spillway flows and
dissipating the excess of energy. The Damle empirical formula
predicts a maximum scour depth at El. 1441 ft for the Inflow Design
Flood conditions.
The plunge pool at Revelstoke Dam is still immature since the
spillway has been used with restraint over the years. The spillway
discharge reached a peak of 70,000 cfs (28% of the IDF) for a few
minutes as part of the 1986 spillway tests, after which the plunge
pool was scoured down to El. 1380 ft. The Revelstoke plunge pool is
known to respond rapidly to increases in spillway discharges and its
performance is jeopardized by unconfined conditions. The maximum
scour depth associated with the Inflow Design Flood is estimated at
El. 1317 ft according to the Damle empirical formula. The hydraulic
model studies included scour tests up to a spillway discharge of
about half the Inflow Design Flood and the maximum equilibrium depth
of scour was observed near El. 1310-1320 ft.
SELECTED BIBLIOGRAPHY
PAPERS
Annandale, G.W. 1994. Taking the Scour Out of Water Power. International
Water Power and Dam Construction 46 (November): 46-49.
Annandale, G.W., S.P. Smith, R. Nairns, and J.S. Jones. 1996. Scour Power.
Civil Engineering, July, 58-60.
Annandale, G.W., T.M. Lewis, R.J. Wittier, S.R. Abt, and J.F. Ruff. 1997.
Dam Foundation Erosion: Numerical Modeling. In Energy and Water:
Sustainable Development: Proceedings of the XXVII IAHR Congress Held in
San Francisco, California, 10-15 August 1997, Theme D, edited by F.M
Holly and A. Alsaffar, theme editor J.S. Gulliver, 429-434. New York
(NY): ASCE.
Annandale, G.W., R.J. Wittier, J.F. Ruff and T.M. Lewis. 1998. Prototype
Validation of Erodibility Index for Scour in Fractured Rock Media.
Proceedings of the 1998 ASCE International Water Resources Engineering
Conference Held in Memphis, Tennessee, 3-7 August 1998, 1096-1101.
Bin, A.K. 1984. Air Entrainment by Plunging Liquid Jet. In IAHR Symposium
on Scale Effects in Modeling Hydraulic Structures Held in Esslingen,
West Germany, September 3-6, edited by H. Kobus, 5.5-1-5.5-6.
Bohrer, J.G., S.R. Abt, and R.J. Wittier. 1998. Predicting Plunge Pool
Velocity Decay of Free Falling, Rectangular Jet. Journal of Hydraulic
Engineering 124 (October): 1043-1048.
Davies, T.W., and M.K. Jackson. 1982. Optimum Conditions for the Hydraulic
Mining of China Clay. Proceedings of the First U.S. Water Jet
Conference Held in Golden, Colorado, 7-9 April 1981, 129-146. Golden
(CO): Colorado School of Mines Press.
Davies, T.W., and M.K. Jackson, n.d. Nozzle Design for Coherent Water Jet
Production. Exeter (U.K.): Exeter University, Department of Chemical
Engineering.
Ervine, D.A., and H.T. Falvey. 1987. Behaviour of Turbulent Water Jets in
the Atmosphere and in Plunge Pools. Proceedings of the Institution of
Civil Engineers, Part 2, 83 (March): 295-314.
Galvagno, G. 1998. A Study of Scour Below Ruskin Dam Spillway Using a Non-
Cohesive Bed Hydraulic Model. M.A.Sc. Thesis, University of British
Columbia.
George, R.L. 1980. Impinging Jets. Denver (CO): Engineering and Research
Center, Water and Power Resources Service. REC-ERC-80-8.
Hager, W. H. 1998. Forum Article - Plunge Pool Scour: Early History and
Hydraulicians. Journal of Hydraulic Engineering 124 (December): 1185-
1187 .
Hamilton, K.J., S.R. Abt, R.J. Wittier, and G.W. Annandale. 1997. Erosion
at Dam Foundations: Plunge Pool Circulation. Proceedings of the
Association of State Dam Safety Officials Annual Conference Held in
Pittsburgh, Pennsylvania, 7-10 September 1997, 693-702.
Hartung, F. 1959. Die kolkbildung hinter iiberstromten wehren im hinblick
auf eine bewegliche sturzbettgestaltung. Die Wasserwirtshaft 49(1):
309-313. In German.
Hartung, F., and E. Hausler. 1973. Scours, Stilling Basins and Downstream
Protection Under Free Overfall Jets at Dams. Transactions of the 11th
International Congress on Large Dams Held in Madrid, Spain, 11-15 June
1973, 39-56.
Johnson, P.L. 1974. Hydraulic Model Studies of Plunge Basins for Jet Flow.
Denver (CO) : Engineering and Research Center, Bureau of Reclamation.
REC-ERC-74-9.
Lewis, T.L., S.R. Abt, J.F. Ruff, R.J. Wittier, and G.W. Annandale. 1996.
Erosion at Dam Foundations: Predicting Jet Velocities. Proceedings of
the Association of State Dam Safety Officials Annual Conference Held in
Seattle, Washington, 8-11 September 1996, 437-446.
Lowe III, J., P.C. Chao, and A.R. Luecker. 1979. Tarbela Service Spillway
Plunge Pool Development. Water Power and Dam Construction 31
(November): 85-90.
Martins, R.B.F. 1975. Scouring of Rocky River Beds by Free Jet Spillways.
Water Power and Dam Construction 27 (April): 152-153.
Mason, P.J. 1984. Erosion of Plunge Pools Downstream of Dams Due to the
Action of Free-Trajectory Jets. Proceedings of the Institution of Civil
Engineers, Part I, 76 (May): 523-537.
Mason, P.J., and K. Arumugam. 1985. Free Jet Scour Below Dams and Flip
Buckets. Journal of Hydraulic Engineering 111 (February): 220-235.
Mason, P.J. 198 9. Effects of Air Entrainment on Plunge Pool Scour. Journal
of Hydraulic Engineering 115 (March): 385-399.
Mason, P.J. 1993. Practical Guidelines for the Design of Flip Buckets and
Plunge Pools. Water Power and Daw Construction 45 (September/October):
40-45.
Otto, B. 1986. Study of Scour Potential at Burdekin Falls Dam Due to Rock
Stresses. Queensland Water Resources Commission.
Prochukhan, D.P., S.A Fried, and L.K. Domansky. 1971. The Rock Foundation
of Hydraulic Structures. Stroiizdat, Moscow.
Quintela, A.C., J.S. Fernandes, and A.A. Da Cruz. 1979. Barrage de Cahora-
Bassa. Problemes poses par le passage des crues pendant et apres la
construction. Transactions du Treizieme Congres des Grands Barrages
tenu a New Delhi, India, 713-730.
Schleiss, A.J. 2 002. Scour Evaluation in Space and Time - The Challenge of
Dam Designers. In Rock Scour Due to Falling High-Velocity Jets:
Proceedings of the International Workshop on Rock Scour in Lausanne,
Switzerland, September 25-28, edited by A.J. Schleiss and E. Bollaert,
3-22. Lisse (Switzerland): Swets and Zeitlinger.
Simoes, G.F., and E.do A. Vargas JR. 2001. Analysis of Erosion Processes
Downstream of Spillways in Large Dams. Proceedings of the 38th U.S. Rock
Mechanics Symposium Held in Washington, D.C., 7-10 July 2001, 959-966.
Wittier, R.J., J.F. Ruff, S.R. Abt, G.W. Annandale, B.W. Mefford, K.
Adhya, and D. Morris. 1995. Dam Foundation Erosion: 1994 Year End
Summary Report. Denver (CO) : US Bureau of Reclamation Water Resources
Research Laboratory.
Wittier, R.J., B.W. Mefford, S.R. Abt, J.F. Ruff, and G.W. Annandale.
1995. Spillway and Foundation Erosion: Estimating Progressive Erosion
Extents. Proceedings of Waterpower'95 Held in San Francisco,
California, 25-28 July 1995, 1706-1714.
Wittier R.J., G.W. Annandale, S.R. Abt, and J.F. Ruff. 1998. New
Technology for Estimating Plunge Pool or Spillway Scour. Proceedings of
Association of St-citZG D3.ni S3.fs ty Off i. ci 3 2. st D3.n\ Ss.f s t y' 98, Hq 2. c?
Vegas, Nevada, 11-15 October 1998, 755-766.
Wittier R.J., G.W. Annandale, J.F. Ruff, and S.R. Abt. 1998. Prototype
Validation of Erodibility Index for Scour in Granular Media.
Proceedings of the 1998 International Water Resources Engineering
Conference Held in Memphis, Tennessee, 3-7 August 1998, 1090-1095.
Yang, C.T. and A. Molinas. 1982. Sediment Transport and Unit Stream Power
Function. Journal of the Hydraulics Division, ASCE, 108, HY.6: 774-793.
Yildiz D., and E. Uziicek. 1994. Prediction of Scour Depth from Free
Falling Flip Bucket Jets. International Water Power and Dam
Construction 46 (November): 50-56.
BC HYDRO REPORTS
BCH Report No. 354: Report of Laboratory Testing on Rock Core Samples /
Peace River Project (by Ripley and Associates). June 1959.
BCH Report No. H715: Peace River Site 1 Development / Detail Spillway
Hydraulic Model Studies (by Lasalle Hydraulic Laboratory Ltd.).
December 1970.
BCH Report No. 966: Peace River / Site 1 Project / Gravity Dam and
Spillway Foundation Report. December 1978.
BCH Report No. HY296: Peace Canyon Project / Review of Spillway Scour
Potential. February 1985.
BCH Report No. GEO 9/85: Peace Canyon Project / Memorandum on Plunge Pool
Development. July 1985.
BCH Report No. H1742: Peace Canyon Dam / Design Report. December 1987.
BCH Report No. H2 003: Williston Lake / Probable Maximum Flood. June 1988.
BCH Report No. H2767: Peace Canyon Dam / Comprehensive Inspection and
Review 1993. November 1994.
BCH File No. C-PCN-1206.12: Peace Canyon Plunge Pool, Spillway and
Tailrace Channel Inspection. June 1997.
BCH Report No. OMSPCN/03: Peace Canyon Dam / Operation, Maintenance and
Surveillance Manual for Dam Safety. February 2001.
BCH Report No. 750: Pend d'Oreille River / Seven Mile Project / Summary of
Information for Advisory Board Meeting No.1. June 1975.
BCH Report No. H1743: Seven Mile Dam / Design Report. August 1988.
BCH Report No. H2062: Seven Mile Dam / Deficiency Investigations. March
1990 .
BCH System Operating Order No.4P-36: Seven Mile Project. May 1997.
BCH Report No. PSE362: Seven Mile Dam / Dam Safety Improvements /
Auxiliary Spillway / 1999-2000 Investigations Report. May 2001.
BCH Report No. PSE401: Seven Mile Dam / Dam Safety Improvements / Working
Dam Foundation Summary (Draft). October 2001.
BCH Report No. N1926: Seven Mile Dam / Plunge Pool Scour Report. March
2002 .
BCH Report No. 150: First Report of Laboratory Testing on Soil and Rock
Samples / Peace River Project (by Ripley and Associates). June 1958.
BCH Report No. 31: Report of Laboratory Testing on Rock Core Samples /
Peace River Project (by Ripley and Associates). July 1959.
B.C. and B.B. Power Consultants Limited. Report on the Peace River Hydro-
Electric Project Vol. II - Appendix A2.1: Geological Report #3 /
Portage Mountain Site (by D. Campbell). June 1959.
B.C. and B.B. Power Consultants Limited. Report on the Peace River Hydro-
Electric Project Vol. II - Appendix A2.3: Geology of Portage Mountain
Dam Site (by V. Dolmage). June 1959.
IPEC Report No. H692: Portage Mountain Development / W.A.C. Bennett Dam /
1972 Spillway Tests. July 1973.
BCH Report No. H2417A: W.A.C. Bennett Dam / Comprehensive Inspection and
Review 1990 / Hydrotechnical. October 1992.
BCH Report No. OMSGMS/03: W.A.C. Bennett Dam / Operation, Maintenance and
Surveillance Manuel for Dam Safety. January 2001.
Revelstoke
BCH Report No. 664: High Revelstoke Versus Downie - Low Revelstoke /
Feasibility Study. January 1973.
BCH Report No. 746: Revelstoke Project / Spillway Design Flood. March
1975 .
BCH Report No. H1624: Summary of Information for Advisory Board Meeting
No. 11. June 1983.
BCH Report No. 2278: Report on Revelstoke Project / Spillway Plunge Pool
Model Study (by Western Canada Hydraulic Laboratories Ltd.). August
1983 .
BCH Report No. H1864: Revelstoke Project / Design Report. February 1988.
BCH Report No. HYD.943: A Fact Finding Report on the Failure of Revelstoke
Powerhouse Access Road During the August 1991 Flood - Draft. November
1991.
BCH Report No. N1315: Report on Overwater Acoustic Profiling and Seismic
Refraction Survey / Revelstoke Dam - Access Road Replacement Project.
January 1992.
BCH Local Operating Order No. 3P03-47: REV - Outlet Works and Spillway
Operation (Non Power Water Discharges). March 2000.
Appendix I
Erodibility Index Charts
ERODIBILITY INDEX CHARTS
Erodibility Index. K
T h e R o c k Q u a l i t y D e s i g n a t i o n ( R Q D ) is a s t a n d a r d p a r a m e t e r in drill c o r e l o g g i n g a n d is c a l c u l a t e d a s
the ratio (in p e r c e n t ) of the c u m u l a t i v e length of all p i e c e s of c o r e g r e a t e r than 10 c m to the total
length of the c o r e run. T h e other p a r a m e t e r s a r e d e f i n e d in the following t a b l e s from A n n a n d a l e
(1995).
T a b l e 1. M a s s S t r e n g t h N u m b e r for R o c k s ( M s )
Unconfined Mass
Hardness Identification in Profile Compressive Strength
Strength Number
(MPa) (Ms)
Very soft Material crumbles under firm (moderate) blows with sharp < 1.7 0.87
rock end of geological pick and can be peeled off with a knife; is
too hard to cut triaxial sample by hand. 1.7-3.3 1.86
Soft rock C a n just be scraped and peeled with a knife; indentations 1 3.3-6.6 3.95
mm to 3 mm show in the specimen with firm (moderate)
blows of the pick point. I 6.6-13.2 8.39
r
Hard rock Cannot be scraped or peeled with a knife; hand-held j 13.2-26.4 17.70
specimen can be broken with hammer end of geological I
pick with a single firm (moderate) blow. I
Very hard Hand-held specimen breaks with hammer end of pick under j 26.4-53.0 35.0
rock more than one blow. 53.0-106.0 70.0
Extremely Specimen requires many blows with geological pick to >212.0 280.0
hard rock break through intact material.
Note.
The value of Ms for rock can be determined by equating it to the unconfined compressive strength in MPa if the strength is
greater than 10 MPa, and equal to 0.78*UCS 1 0 5 when the strength is less than 10 MPa.
T a b l e 2. M a s s S t r e n g t h N u m b e r for G r a n u l a r S o i l s ( M s )
Mass
Consistency Identification in profile SPT B l o w Strength
Count Number
(Ms)
^ e r y loose Crumbles very easily when scraped with geological pick. 0-4 0.02
Loose Small resistance to penetration by sharp end of geological 4-10 0.04
pick.
Medium Considerable resistance to penetration by sharp end of 10-30 0.09
dense geological pick.
Dense Very high resistance to penetration by sharp end of 30-50 0.19
geological pick - requires many blows of pick for excavation.
Very dense High resistance to repeated blows of geological pick - 50-80 0.41
requires power tools for excavation.
Note.
Granular materials in which the SPT blow count exceeds 80 to be taken as rock - see Table 1.
Table 3. Joint Set Number (Jn)
Number of J o i n t Sets J o i n t Set Number
(Jn)
Intact, no or few joints/fissures 1.00
One joint/fissure set 1,22
One joint/fissure set plus random 1.50
Two joint/fissure sets 1.83
Two joint/fissure sets plus random 2.24
Three joint/fissure sets 2.73
Three joint/fissure sets plus random i 3.34
Four joint/fissure sets j 4.09
Multiple joint/fissure sets ! 5.00
Note.
For intact granular materials take Jn = 5.00.
filling
Unaltered joint walls, surface staining only 1.0 — —
-1000
-900
V)
CD
800 o'
-700
-600
-500
1200 2100
Line [ft]
SEVEN MILE DAM
SURVEY OF TAILRACE CHANNEL
ON 7 AUG. 1980
Reference Drawing No. 224-C17-X7016
1000
900
cn
Q)
i—t-
800 o"
13
700
600
500
1200 1700 2200
Line [ft] SEVEN MILE DAM
TAILRACE SOUNDINGS - OCT. 1988
PLAN
Reference Drawing Nos. 224-C22-D6 to D9
t TOO Reference line
1630
% 1600
a
I* 13 SO
ISOO
SECTION LA
NOTES
/. Sounding undertaken on Hay IS and Uay 16, 1973
by Burnett Resource Surveys Ltd.
( Owg No. IOOS - C26- D! )
2. Dotted contours taken from IPEC
Dwg No. U-3040-II35 (June 1969 )
KL0HN-CR1PPEN 1NTEQ
BRITISH COLUMBIA HYDRO AND POWER AUTHORITY
mi
FEB 1993
D. Y. /HCP OWO Ma I 0 0 6 - C I 4 - B I 2 6 2
REPORT No. KCt 139 (H2709! _
215
E 48600.000 E 48700.000 E 48900.000 E 49000. 000 E 49100.000
+ + + +
Stc 33+43. 42 N 1800. 000
E 48800.000
0*00 r 8
-)-N 1700.000
A
IP t 6 M
B E R M
N 1500.000
+
I *«JNCTI0NAI CvCE
1 2. 07
C«*»N PPOJECT NO
C. 0. B.
S2 BChydro
CMCCICO INSPECTED SLRvEr anO PhOTOCRaumCTRi CEPaATwCnT
G. M. SHR'JM GENERATING S T A T I O N
l*SPeCT£0 :.NSP£CTE0
Spillway - Piange Pool
inspected NTS fi£?. Ba+hyme+ric Survey - 1996
93016
OAIE 5C't£ i:2ooo " 1 0 0 6 - C t l - D i l O T i"
DCS nico BRITISH COLUMBIA HYDRO AND POWER AUTHORITY
MW COLUMBIA R I V E R - R E V E L S T O K E PROJECT
CCA (TtCK)
CMKD WfO
SPILLWAY PLUNGE POOL
IMP AWO
SOUNDING SURVEY TAKEN 15 MAY 1984
I I 1 I I 1 1 1 1 1 OATI
'FOLLOWING INITIAL SPILLWAY OPERATION
MO 18 MAY 1984
•McnoriLMce
m v i t i O N t jmno. °°'SS*CT acALi I'-20' MOW 212- C2I - 07125 R 0
aid
1443-6
-| /SOO £
-] /480 k
1460
^
$
I4Z0 ^
1 S
1400 ki
-I /3SO ^
BRITISH COLUMBIA HYDRO aad POWER AUTHORITY APPROVALS B. C. H Y D R O - CIVIL INSPECTION SECTION
DATE DATE REVELSTOKE G. S.
OKS.
DM SURVEY OF RIVER CHANNEL IMMEDIATELY
DOWNSTREAM OF PLUNGE POOL
Contours redrawnDA I /8 Oft. DAJ FCB'tn FOLLOWING SPILL TESTS
DR.
A
Section A notes chongec/
\DAJ\ CM.
A! i=t»'<7
II TO 14 AUGUST 1986
I. iff. SCALC: MICROFILM ID
REFERENCE PRAWlNO» M M C I PRAWINOR REMARKS 9Y [ cw. \rrml pate . M . » T _ . , _ | •"•« • » 212 - C 2 I — D 1 3 4 |"2