ID Task Task Name Duration Start Finish 2019 2020 2021

Mode Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
1 1 JASA KOSULTASI TEKNIS SISTEM PIPELINE 540 days Fri 16/11/18 Thu 10/12/20
2 1.1 PEMUTAKHIRAN SYSTEM TATA KERJA 108 days Fri 16/11/18 Tue 16/04/19
3 1.1.1 Collecting As Built Data 14 days
4 1.1.2 Renew Document 94 days
5 1.2 EVALUASI TEKNIS PERLINTASAN JALAN 108 days Wed 17/04/19 Fri 13/09/19
6 1.2.1 Collecting As Built Data 14 days
7 1.2.2 Site Investigation 14 days
8 1.2.3 Analyse Phase 40 days
9 1.2.4 Report & Reccomendation 40 days
10 1.3 EVALUASI TEKNIS PERLINTASAN UTILITAS 108 days Sat 14/09/19 Tue 11/02/20
11 1.3.1 Collecting As Built Data 14 days
12 1.3.2 Site Investigation 14 days
13 1.3.3 Analyse Phase 40 days
14 1.3.4 Report & Reccomendation 40 days
15 1.4 EVALUASI DESAIN PROTEKSI PIPA 108 days Wed 12/02/20 Fri 10/07/20
16 1.4.1 Collecting As Built Data 14 days
17 1.4.2 Site Investigation 14 days
18 1.4.3 Analyse Phase 40 days
19 1.4.4 Report & Reccomendation 40 days
20 1.5 EVALUASI DESAIN TIE IN 108 days Sat 11/07/20 Tue 08/12/20
21 1.5.1 Collecting As Built Data 14 days

Task Manual Task Deadline

Split Duration-only Baseline

Milestone Manual Summary Rollup Baseline Milestone

Project: Schedule Summary Manual Summary Baseline Summary


Date: Fri 16/11/18 Project Summary Start-only Progress

Inactive Task Finish-only Manual Progress

Inactive Milestone External Tasks

Inactive Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish 2019 2020 2021
Mode Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
22 1.5.2 Site Investigation 14 days
23 1.5.3 Analyse Phase 40 days
24 1.5.4 Report & Reccomendation 40 days

Task Manual Task Deadline

Split Duration-only Baseline

Milestone Manual Summary Rollup Baseline Milestone

Project: Schedule Summary Manual Summary Baseline Summary


Date: Fri 16/11/18 Project Summary Start-only Progress

Inactive Task Finish-only Manual Progress

Inactive Milestone External Tasks

Inactive Summary External Milestone

Page 2