1) Connect together the GND terminals of the two controllers.

2) Create a new terminals ‘10A’ on both controllers to supply with a new 3 Amp. diode
the floor registration lamps: they have not to be supplied by the original terminal ‘10’.
The original terminal ‘10’ will continue to supply only all the other cabin and position
lamps and signalling (see the annexed electric diagram example).
3) Connect together the new ‘10A’ terminals of the two controllers.
4) Connect together the RS232 male DB9 connectors (9 pins) on the EURO boards
using a three wires unshielded cable (maximum 15m length) equipped with two female
DB9 plugs.
The pin connections at DB9 plugs shall be: pin 5 to pin 5, pin 3 to pin 2, pin 2 to pin 3.
5) Connect all the floor registrations lamps and buttons to both EURO boards inputs
in parallel.
If you have two push button plates on each floor (one per cabin), they can be connected
each one to the corresponding EURO board input, but in any case you have to connect in
parallel the floor registration EURO inputs on the controllers site in machine room (see
the annexed electric diagram example).
6) Modify the values programmed at parameter 34 of both Euro boards: one of them
with value 38 (master) and the other one with value 34 (slave).