You are on page 1of 6

- 619 -

Assessment of Harmonics at a Medical Facility


David Ramirez-Castro Efiain O'Neill-Camllo Julio Santiago-P&ez
Electrical and Computer Engineering Department
University of Puerto Rico-Mayagiiez
Ma- PR

Abstract A high quality of power is required in healthcare Mli- Events such as voltage transients may cause a micro-
ties due to increased use of microprocessor-based equipment. processar to read voltage levels incorrectly, resulting in in-
However, the ability to diminish power quality concems depends correct data processing (ones being read like zeros) or al-
on the limitations imposed by the system under study, especially tered stored data/settings. Table l presents malfunctions in
infi.sstructute c " * ts. This paper describes a power quality medical equipment caused by power quality events 121.
audit amducted at a medical facility. Voltage and current meas-
These examples illustrate the importance of taking care of
ured at various points were used to assess the quality of the service
power quality issues at a medical facility. The effkcts range
h m the utility as well as the condition of the hospital's electrical
system. The main power quality problem bund was hannonic fiom being as simple wasted supplies or repeated procedures
distortion. Measurements of the total harmonic distortion (TIID) to serious situations at intensive care or operating areas.
were used to locate harmonic sources. Potential problem areas Source of power quality problems at hospitals include:
were identified within the facility. A correlation was made be- 0 Utility side events (e.g., capacitor switching)
tween portable, medical equipment and power quality concerns. 0 Accidents and nature phenomena (e.g., lighting)
Recommendations are presented based on the results of the audit. 0 Inadequate Wiring and grounding
This study will serve as a guide for installations of new equipment
and futm expiinsions in the hospital. 0 High-wattage equipment
Testing of emergency generators
Keywords: Power quality, harmonic distortion, voltage distur- Physical plant renovations
bances, transient phenomena The first two are related to events outside the hospital elec-
trical system, and a m the quality of the power delivered to
L INTRODUCTION the facility [3]. The last four depend on the characteristics of
the medical facility's system. An increase in the number of
The advent of the microprocessor has dramatically sensitive, nonlinear loads at hospitals should go in-hand
changed the healthcare industry. Magnetic resonance im- with improvements in the facilities' electrical systems.
aging (MRI), monitoring devices and portable x-ray ma- However, many buildings were exempt of complying with
chines are common equipment in any hospital. figher new or revised regulations. Compounding the problem is the
quality of power is required at all healthcare facilities due to fkct that many codes or regulations deal with safety issues,
the sensitive nature of microprocessor-based equipment. but they do not address power quality concerns [2]. Fre-
Nowadays, medical devices are smaller and faster, but they quently, largedemand equipment such as x-ray machines is
are also more susceptible to electrical disturbancesthan they installed at fkcilities without a complete power quality sur-
were twenty years ago. Electrical transients that were once vey. Power quality problems are also cumulative; therefore,
normal, are now intolerable due to these machines. Many of small power quality events can lead to loss-of-life and even-
these devices are not only sensitive to, but also generate tually equipment failure.
power quality problems as part of their normal operation, Changes in the quality of power have been observed at
e.g., radiology equipment. ofiice equipment also has a sig- the Bella Vista Hospital in Mayagiiez, PR An increase of
nificant impact on the quality of the electric service at a sensitive medical equipment, recent problems with an expen-
medical facility. Therefore, it is not only important to sive catheterization equipment and the installation of mil-
monitor the quality of the power supplied by the utility, but liondollar equipment, motivated the Hospital's Engineering
also monitor the power quality impact among loads within
the medical facility [ 11.

Problem Possible Cause


*
Distortion of displays Distorted voltage, altered
data
Incorrect diagnostic results EM, grounding
Equipment lockup Voltage surges or sags
r
Control/alarm malfimction Microprocessor malfunction

C- 7303-6439-5/00/$1C. 00 2050 I EEE


- 620 -
Department to conduct a power quality audit. The main The physical facilities at Bella Vista Hospital range
objectives of this work were to assess the quality of service fiom 25 to 45 years old. Although the electrical system of
received &om the utility and to identify areas within the hos- the five-story building has undergone many renovations, it
pital where power quality problems currently exist or may may not be suited to support power qualily conditions related
develop in the near future. This information will be used for to the operation of a large number of sensitivq microproces-
better planning when instailing sensitive equipment and in sor-based devices. The neutral wires were not designed to
future expansions. Other objectives were the study of the support nonlinear loads and harmonic flow. There is a pos-
impact of portable medical equipment upon other sensitive sibility of grounding problems caused by corroded wiring.
devices and to evaluate the condition of the hospital's elec- Rooms that had one or two medical devices in the past, now
trical system. house complex medical systems and/or numerous portable
devices.
IL DESCRlPTION OF THE SYSTEM The interaction between loads is also a concern at BVH.
OiEce equipment and medical devices with high distortion
The peak load at Bella Vista Hospital (BVH)is 1 MVA, can affect the operation of miaoprocxssor-based equipment
as measured by the local utility. The load is distributed even if the latter has built-in power cunditimm. Imaging
among thirty-seven circuits, using two 1 MVA dry-type systems cause sags that may generate some of the problems
transformers. Fig. 1 shows the main circuits of the system. shown in Table 1.
Service fim the Puerto Rico Electric Power Authority Recently, there have been problems with a catheterism
(F'REPA) comes fim a 4.16 kV feeder. The hospital is lo- equipment. This is an image processing equipment known
cated in a residential area over the top of a hill. as C-Arm, used for fluoroscopy studies. This study is similar
BVH has an alternate power supply consisting of two in concept to an x-ray image, but it continuously projects the
generators. The first one has a capacity of 625 kVA, and image in a monitor instead of a film. The device's power
can supply emergency power in only 5 seconds, as required drivers and its emission tube had to be replaced. A surge
by regulations [4]. The second is a backup in case of mal- was blamed for the failures, even though the f i e ' s surge
function of the main gene". It has a capacity of 487 protection was in g d condition and showed no evidence of
kVA. The emergency energy is supplied trough fifteen operation. Other power quality issues may be a better expla-
transfer switches. Individual l d can be selectively turned nation to these even?.
omon with this configuration. However, the topology in- The conditions described above and the installation of
creases significantly the number of components in the sys- another milliondollar machine (a new MRI) made it clear
tems that can have troubles. that a power quality audit was needed at BVH.

IIL METEODOLOGY

The first step of the power quality audit was an inspec-


tion of the hospital's electrical system. Even though numer-
ous renovations had been made in the last fifteen years, a
one-line diagram of the electrical system was not available at
BMI. There were only original drawings of the facilities
and separate drawings for major improvements without
documentation of the changes made in the system. During
the inspection of the system, information was gathered to
develop a complete, current schematic of the system. The
hospital has 37 major circuits available in the two switchgear
at the substation, and more than 50 panelboards distributed
4.16 KV through the building. The single line diagram was indispen-
YA sable for the power quality audit.
A portable, stand-alone, single-phase power quality
analyzer was used to record the measurements [5]. One 500
A clamp-on CT and a 2000 A flexible clamp-on CT were
also used. The final analysis was perfinmed using sofhvare
provided with the equipment by the manubturer as well as
commercially available mathematical sofhvare. The tools
Fig 1. Pictorial for the hospital's electrical system used were relatively inexpensive equipment when one thinks
about the capabilities they ofFer and the many tasks that can
be paformedwith them.
,621 -

Common practices recommend that three-phase meas-


urements be taken for seven days to register the fluctuations
and the most critical scenarios possible [l]. There were a
total of 75 points to be measured in the system, firom the sub-
station transformers, to the output of each circuit breaker,
then at the input of each distribution panel, and finally
through the individual loads. Spending a week in each point
was not a feasible alternativeto log the required data. A fav
tests w e performed to determine if less time could be spent
making the measurements at each point, using a single-
phase instead of a three-phase instrument.
The first circuit measured was the office area, it is a 130
A load. The reason for this selection was that in a medical
facility the office area is the most unpredictable load. Each
phase was measured during 05ce hours (8 hours a day) at
normal load. The first day, measures for voltage and current
were logged. The next day, power and power factor were
logged. After taking the first voltage and current measure-
ments, it was evident that harmonics were the main problem
in the facility. Therefore, the THD was also measured on the
third day. The procedure was repeated for the remaining
two phases. The voltage and current measurements were
repeated on a different day of week fix each phase. There
were no major differences between the first set of measure-
ments and the second. The peak load occurred between
10:30 am and 11:30 am for both sets of measurements.
To reduce the time required for data acquisition, a total
of sixteen measurements were taken, two minutes apart fiom
each other in the office area. There were 254 samples per
measurement in an interval of 4 cycles or 67 ms. The sam-
pling time was 2.6(10") ms. The three phases were evalu-
ated in only 1 % hour. The values for power and THD were
calculated f?om the digitized wavefoxms stored in the com-
puter. The results were compared with the previous meas-
urements. The error was less than five percent, which was
small compared to the savings in time. Furthermore, in most
cases the connected load was known, and any variation could
be predicted. The exception was measuring at the trans-
formers. At that point the measurements were taken at 15-
minute intervals for 24 hours in each phase. This was done
because the whole hospital can be monitored at those points,
and load behavior can not be predicted with a reasonable
precision.
Temperature readings were also taken to study the ef-
fects of the harmonics and other power quality problems in
the system. A formal infiared study was recommended and
performed in the main circuits and critical services in the Site vrms Inns TI-Q
facility. This study revealed some hot points in circuits (one Main Transformer # 1 123.56 995.64 3.91%
as high as 349" F), which gave evidence of the deterioration Main Transformer # 2 119.28 1230.42 5.26%
L
of the contacts. Harmonics were present at some of these office Loads 120.34 84.65 14.29%
hotpoints. Portable X-Ray 119.63 13.88 23.61%
M e r the tests to validate the method, voltage and cur-
Surgery Suits 121.81 18.78 29.17%
rent measurements were taken at various points in the sys-
tem. A method based on the current-source model was used surgery suits (EM) 122.65 74.35 21.76%
to locate harmonics [6]. One can trace a harmonic source CathLab Idle 277.40 20.80 47.1oyo
kom multiple measurements of THD in the system. The 1CathLabON 1272.44 140.40 134.00% I
- 622 -
For the surgery suits there are two main circuits. One In Fig. 4, the catheterism machine is operating. The current
has general equipment amneded to it, including the surgery distortion looks like a step square wave. The steps follow a
luminaries. These luminaries were experiencing fiequent sinusoidal wave. This behavior agree with the way this ma-
bum out. M e r they were moved to a circuit with less har- chine operates, as explained in section 11, were amtinuos
monic distortion, the luminaries' life was increased. The "shoots" of x-ray draw high current in steps. As with idle
other circuit has the isolation monitors for the suits and the operation, there is minimal voltage distortion. The total
anesthesia machine. It is interesting that the ground refer- current is almost double in this case, but the distortion is
ence at this point is precisely the interface between the oldest very different. Fig. 5 is the corresponding frequency spee
and newest part of the Hospital. Grounding problems seem trum for the device's current. In thii case the fifth harmonic
to be the cause of harmonic levels at this point. Further is the largest, typical for switching devices. The current
analysis is required at this point. magnitude of the third harmonic is slightly reduced as com-
In Fig. 2 a high degree of distortion is observed for the pared to idle operation, and its percentage in the spectnrm is
current, but the voltage presents only minimum distortion. significantly reduced since the total current magnitude is
The same distortion is observed in both sides of the wave- double.
form (positive and negative). It is a typical magnetic distor- Besides the harmonic distortion, the audit identified the
tion with some switching component. At this point the cur- monthly emergency test on generators as a recurrent power
rent draw was around 20 A. The load was the in-line volt- quality monitor as in [l] and [2]. The emergency generator
age regulator and the C-Arm equipment (described in sec- must be tested monthly. The purpose of the test is to ensure
tion II) in idle mode. that in case of real power fiilure the generators will start
Fig. 3 showsthe harmonics present in the current for the normally within the required parameters and that it can
catheterism machine. There is a high degree of third har- manage the emergency load. This requirement is known as
monic present in this case, typical of magnetic devices. The 30/50[4]. This means that the generator should run with
system is not affected by this distortion because as it can be 30% of the nameplate or 50% of its actual connected emer-
seen in Fig. 1, there is a transformer in a wyedelta configu- gency load. The larger of these two quantities should be
ration. This configuration effectively isolates the triplens used. The standards also require that the generator should
harmonic fiom the rest of the system. The only problem is be supplying energy to the load in 8 seconds or less. This
in the transformer itselt where this harmonic heats up the
windings. This transformer presents some damage in its
windings and is under schedule to be replaced. The equip- t : . : . _ , . .

ment harmonic distortion seems to be the cause.

___---__-___-___________________________-------------------------.
.iwm
Cat L a b fwe A - Yo Load
a.?

Fig 2. Catheterism equipment idle (phase A)

rm onar ,a, ~
(ina

30 90
- . _ _ _ ~ ---___
80 ....

m .................................. -....................................... ., m
8 ) - ____
60
5.I.z
U)

30
..
~

-. .................................................................. . .-. . . .
zo I
10

1 3
I5 m7 9 1 1 1 3 1 5 1 7 1 9 2 l 2 3 2 5
0
1 3 5 7 9 1 1 1 3 1 5 1 7 1 9 Z l D 2 5
HaaatNunbs
_____________________.____________._____-----------------------
C- W Tu. b 6- Load -
.................................................................
Cat L a b Lase A - Bo Load
HdNunba

Fig. 3. Harmonic strength for equipment idle (phase A) Fig. 5. Harmonic strength for equipment operating (phase A)
- 623 -
test represents a power quality problem since it is responsible V. CONCLUSIONSAND FUTUREWORK
for contactors in transfer switches to operate for the single
purpose of testing, this reduce its useful life and increase the This paper presented a description of a power quality
contact resistance which produce a cumulative effect that audit carried out at the Bella Vista Hospital. The method is
increase power quality problems. In this case sags and simple; the measuring equipment is relatively inexpensive.
swells may be the most common problems associated with However, the information obtained from such a study is in-
the recurrent operation of the generator. valuable to conduct preventive maintenance or to trace
Another important outcome of the power quality audit is sources of power quality problems. Harmonic distortion was
in regard to the condition of the electrical system. Installa- the main problem found in this audit. Measurements of
tion of new equipment did not go in-hand with infrastructure THD were used to identify the harmonic sou~ces. The prin-
improvements (at least they were not made hst enough). As cipal power quality offenders were high-wattage medical
in most facilities changes occur at a fast pace, new equip- equipment in surgery units and office areas. Areas that are
ment is added almost daily, from office equipment, diagnosis sensitive to power disturbances were also identified. Poten-
equipment, and patient treatment equipment. When in the tial problem areas were identified within the facility.
past a single receptacle per bed in patient rooms was more The study revealed conflicting point of views between
than enough, today two or three are insufficient. Unfortu- standard compliandinterpretation and actual power quality
nately, services are added most of the time without improv- problems found inside installations. A detailed study of
ing feeders, panelboard capacity, circuit protection and infia- harmonic propagation is required. Evaluation of grounding
structure in general. Therefore, a system that was once stiff connections throughout the facility is underway. Finally, a
is now operating near its limits. This change in operating periodic power audit should be performed at the facility to
point has already cawed malhctions in equipment such as prevent hture power quality problems.
patient’s IV pumps (used to administer serum and other
medicines to patients). VIL ACKNOWIXDGMENTS
Maybe one of the major fkdings in this audit is related
to standards compliance. For example IEEE 519 refers to a The authors wish to acknowledge the support f?om the
5% TH4, at the point of common coupling. The intend of Bella Vista Hospital. Mr. Luis J. Rodriguez, biomedical and
this standard is to avoid that the distortion caused by one communications technician, his help was invaluable in the
user to be a problem to other users. Quality of the service data collection process. Mr. Wilfiedo Perez biomedical
from the local utility was acceptable. Therefore, the hospital technologist, who supplied detailed information on the op-
has minimal power quality impact on neighboriig loads. eration of the biomedical and medical image processing
Nevertheless, some people interpret this compliance with equipment. Also Mr. Fred Medina electrician who supplied
IEEE 519 as if there are no power quality problems inside information neceSSary for the single line diagram. Finally
their facility. This is not necessarily true. Individuai circuits Mrs. Olga Babilonia, Vicepresident and responsible for the
may present problems at various points in the facility, ,as acquisition of the measurement equipment.
shown in the preceding discussion. At the hospital under
study, there were also continuous motor failures that were REFJZRENCES
caused by harmonics. A better guide to problems inside
D. Stymiest, W.Henry, “Power Prognosis: Swgery Required!,’’ Con-
medical facilities can be found in [9] and [IO]. sulting4pecifjtingEngineer, no. 3, September 1998,pp. 71-76.
The main recommendation of this study is to establish a Power Qual@ for Healthcare, Industrial and Agricultural Business
routine or periodic power quality assessment at the hospital. Area, Electric Power Research Institute, Palo Alto, 1997.
The study described in this paper should be repeated to en- P. Hall, B. Bailey, E. Camm, “Power Quality Evaluation at Medical
Center,” Proceedings of the 1999 Tronsmission and Distribution Con-
sure compliance to codes/regulations and also as a preventive ference, vol. 2,pp. 560-565.
measure. The cost of such measure is low compared to the Hospitol Accreditotion Standards, Joint Commission on Accreditationof
benefits that will be obtained. Overall system &ciency may HealthcareOrganizations,Oakbrook Terrace, Illinois, 1999.
Power QirolityAnolyzer-Applicotions Guide, Rev. 2, Fluke Corporation,
be improved, resulting on less repairs, reduced loss-of-life Evere*, WA,June 1998.
and better maintenance records. This kind of study would G.T.Hey&, Electric Power Quality, 2“ ed., Stars in a Circle Publica-
give an ability to identify and prevent power quality events. tiom, Scottsdale, 1991.
S. Lugo, D. Ramirez,G. Rivera, E. Vekques, Idennificotion and Cor-
This study will serve as a guide far installations of new rection ofHormonics in an Indusrria~Focility, Elec~ricaland Computer
equipment and future expansions in the hospital. Engineering Department, University of Puerto Rico-hhyaglleq May
Further analytical investigation of harmonic propagation 1999.
and unbalance conditions is required. At this point, the use Recommended Practices and Requirements for harmonic Control in
Electrical Power Systems, IEEE Standard 519,N Y , 1992.
of tuned filters and other expensive solutions is not recom- Recommended Practice for E1ecm.c Systems in Healthcare Facilities,
mended to mitigate the problems encountered. As a first IEEE Standard 602 (White Book), NY, 1996.
step, we recommend the improvement of the grounding “Electrical Systems for Healthcare,” &fiv“zement ond Compliance
Series, American Society of Hospital Engineers, vol. 7,1992,pp. 65-76.
bonding in the fkilities. A detailed study of the hospital
grounding is required to implement this recammendation.
- 624 -
BIOGRAPElES
David Rnmfrez4hh-a is h m Aguadiua, Puerto Rico. He holds a BSEE
h m the university of Puerto Rico-Maya&uez(UPRM). Mr.Ramfrez is the
Diredor oftbe Eagiwering Department at the Bella Vista Hospital in haay-
agaez, Puerto Rico. He also has mdushial expnicnCe with local amdting
firms, and various g o v e r n " agencies Mr. Ramirez is Currently working
towards 811 MSEE at UPRM.

Efinh 0'NcWC.rrillo (S '91, M '99)is 6um Rio piedras, Pueato Rico. He


Ii01d-s the BSEE 5om the UniveSity of Puerto h M a y a @ e z (1994), and the
MSEE from pllrdueUniversity (1 995). He aaaincda PhD. degree m Electrical

-
Engkming hul Ariurna state univasity (1999). Dr. meillcanill0 is
currentlyan Assistant F % o hofElearical Engimering at the University of
Puerto Rico-Mayaagllez He has idwbial eq"e wah CPI del C a r i i
Dorado, Pu- Rico, and TOR Engbaeering,P u Arizona h.O'NeiIl-
crurillo's rrsearch intaeras iuclude computer applications in power systems
powaquality, power ekcmmiq systeas mnlioauenalysis and
chaos
Jalio Santbgo-Phz is &om Agoada, hato Rico. He holds the BSEE from
the univasity of hem RiakMayagaezand the WEE hRasselaa Poly-
tshnic Lmbitatc. He is wrcntly a Proitsor of Flectrical Engineering at the
university of Puerto Rico-Mayagaez. He also has exteusive iudmaid e x p i -
ence with the Puerto Rico Uectric Power Authority. Prof Saatiago's research
and- iutemts includecomputmapplicatiansm power systws, distri-
bution syskms, atmoqhericsardies.

You might also like