MONITORING PROGRES HARIAN

Tanggal : 16 November 2018

Bentang A60 Unit 1


No Item Pekerjaan Rencana Aktual Satuan Progres Persentase Deadline Keterangan
1 Connection Bolt 39/5
- Pelubangan cutting torch 39 2 buah Proses cutting torch 5,13% 17-Nov-18 Monitoring

2 Instal Bearing Pad + Rangka


- Material grouting 1 1 Ls Selesai 100% 17-Nov-18 Closed
- Cek kesesuaian koordinat angkur 10 10 titik Selesai 100% 13-Nov-18 Closed
- Cek metode pemasangan angkur - - - Review Metode 0% 17-Nov-18 Monitoring
- Bearing pad 24 24 buah Setting Cetakan 20% 23-Nov-18 Monitoring

3 Hand Railing 1 - Ls Proses Persiapan 0% 17-Nov-18 Monitoring

4 Instal Reflector 36 0 buah Proses Pengadaan 0% 17-Nov-18 Monitoring

5 Perbaikan Instal Rambu 12 12 buah Proses Pengiriman 80% 17-Nov-18 Monitoring

6 Cutting & Filler Slab 159 60 m' Filler As Jembatan 38% 17-Nov-18 Monitoring

7 Pengambilan Asphalt 1 1 Ls Selesai 100% 17-Nov-18 Closed


Bentang A60 Unit 2
No Item Pekerjaan Rencana Aktual Satuan Progres Persentase Deadline Keterangan
1 Torsi baut 18652 18577 buah Proses Torsi 99,60% 17-Nov-18 Monitoring

2 Kekurangan Baut 75 0 buah Proses Torsi 0% 14-Nov-18 Monitoring

3 Pemadatan Tanah 150 0 m2 Persiapan 0% 16-Nov-18 Monitoring


Trotoar A60 Unit 2
No Item Pekerjaan Rencana Aktual Satuan Progres Persentase Deadline Keterangan
1 Check List 1 1 Ls Selesai 100% 13-Nov-18 Closed

2 Bekisting 1 1 Ls Selesai 100% 16-Nov-18 Closed

3 Instal Pipa Utilitas 1 1 Ls Selesai 100% 13-Nov-18 Closed

4 Pengecoran 34,97 0 m3 Persiapan 0% 17-Nov-18 Monitoring


Bentang A80
No Item Pekerjaan Rencana Aktual Satuan Progres Persentase Deadline Keterangan
1 Komponen Utama
- DG6 = 4, BC4 = 4, BC5 = 4, CG5 = 2, DG7 = 4, TC3 = 4, DG8 = 4, DG9 = 4, TC4 = 4 34 31 batang Erection 91,18% 14-Nov-18 Monitoring
- CG6 = 2, DG10 = 4, TC5 = 4, DG7 = 4, DG11 = 4 18 15 batang Erection 83,33% 15-Nov-18 Monitoring

- DG6 = 4, BC4 = 4, BC5 = 4, CG5 = 2, DG7 = 4, TC3 = 4, DG8 = 4, DG9 = 4, TC4 = 4 9 6 batang Erection 67% 16-Nov-18 Monitoring
- CG6 = 2, DG10 = 4, TC5 = 4, DG7 = 4, DG11 = 4 8 5 batang Erection 63% 17-Nov-18 Monitoring

2 Pengencangan Baut 13416 9368 buah Proses Torsi 69,83% 14-Nov-18 Monitoring

3 Pemadatan Tanah 150 0 m2 Persiapan 0% 16-Nov-18 Monitoring


Oprit ABT 1
No Item Pekerjaan Rencana Aktual Satuan Progres Persentase Deadline Keterangan
1 Agregat Kelas S 150 0 m3 Pengadaan 0% 11-Nov-18 Monitoring

2 Timbunan Tanah 160 160 m3 Selesai 100% 10-Nov-18 Closed

3 Pemadatan Agregat Kelas S 240 0 m2 Persiapan 0% 15-Nov-18 Monitoring

4 Finish Delineator 18 18 buah Pek. Reflekor 80% 19-Nov-18 Monitoring

5 Penanaman Gebalan Rumput 1 0 Ls Review 0% Monitoring


Oprit ABT 2
No Item Pekerjaan Rencana Aktual Satuan Progres Persentase Deadline Keterangan
1 Agregat Kelas S 110 0 m3 Pengadaan 0% 11-Nov-18 Monitoring

2 Timbunan Tanah Bongkar & Pasang Saluran 26,4 0 m3 Persiapan 0% 15-Nov-18 Monitoring

3 Pemadatan Agregat Kelas S 240 0 m2 Persiapan 0% 15-Nov-18 Monitoring

4 Finish Delineator 18 18 buah Pek. Tiang Beton 20% 19-Nov-18 Monitoring

Dibuat Oleh :
PT. AMARTA KARYA (Persero)

Construction Manager