(3) Main warehouse

There are one warehouse at the dam area and one powerhouse area.
(4) Main assembling area and car park area
They are in the dam area and powerhouse area. Car park area and simple machine
maintenance room are also planned in the other areas.
(6) Explosive magazines are near the powerhouse area and dam area respectively.
(7) The oil depots are in the dam area and the powerhouse area respectively. Smaller
oil tanks or oil tankers are in the other parts.
(8) The whole area will be divided into several districts in which we will lay out the air
pressure supply system and water supply system respectively.
(9) Construction power supply system.
In the earlier stage, the diesel generator set is used to supply the construction power
directly; after determined with local PLN according to the actual situation, consider
the generator or the local power system.
(10) Spoil bank
The layout of the Spoil banks will be in accordance with the construction needs. For
each construction area, there will be relative spoil banks to satisfy the needs of
disposal of the waste materials from excavation. The detailed layout of spoil banks is
as the drawing shows. (General Layout Drawings of the Temporary Works)
(11) Sewerage system
There will be settling pond in portal of each Adit, Batch plant, and Aggregate
production plant, and sewerage system in each main discharge location (Including
workshop, camp, site office, etc.). Regarding waste water from living areas, they shall
be treated through Septic Tanks.
(12) Layout of potable water system
Potable water for each camp is from the water tank nearby. After the water is
purified with a dedicated treatment system, a piping network transport the water to
each tap water in the camps.
The drinking water of each construction face adopts barreled water. Drinking water
meets the clause 2.5.1 of General Requirements.