Professional Documents
Culture Documents
Group 3 Appraisal BE Costing
Group 3 Appraisal BE Costing
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
SUMMARY
CP01
m2 ft
CFA 89,729.33 965,847
GFA 81,665.75 879,050
efficiency 53% NFA 43,249.41 465,537
Cost Cost Estimated
C.P. Cost Plans CFA (m2) CFA (ft2) Total Units Cost/Unit per m2 per ft2 Construction Cost
of CFA of CFA
(RM) (RM) (RM)
A CONSTRUCTION COSTS
1 Cost Plan for Basement Carpark 8,010.50 86,225.00 290 111,176.53 4024.87 373.92 32,241,194.45
2 Cost Plan for Podium Carpark (including Ground Floor) 29,567.89 318,269.00 477 80,925.84 1305.53 121.29 38,601,626.16
3 Cost Plan for Service Apartment Tower A 26,199.01 282,006.00 216 490,282.68 4042.18 375.53 105,901,059.78
4 Cost Plan for Service Apartment Tower B 25,951.90 279,346.00 216 485,658.14 4042.18 375.53 104,902,157.54
TOTAL CONSTRUCTION ESTIMATED COST FOR BASED BUILDING: 89,729.30 965,846.00 3641.68 338.32 326,765,681.70
8 Cost Escalation (Assuming tender to be called in one year's time) 89,729.30 965,846.00 109.25 10.15 9,802,970.45
3%
TOTAL CONSTRUCTION ESTIMATED COST FOR BASED BUILDING AFTER COST ESCALATION: 3,750.93 348.47 336,568,652.15
Asummption/Exclusion
1) Site Preparation including Site clearance and earthwork,temporary works and instrumentation and monitoring
2) Bored Piles and pile caps are included in Piling
3) Foundation assumed as Work Below Lowest Floor Level
4) Contiguous Bored Pile, Strutting and Sheet Pile including 1000mm diameter contiguous bored piles with skin wall and capping beam
5) Reinforced Concrete Walls are included in Frame
6) Transfer Structures assumed as Transfer Beam and Slabs
7) Assume there is no roof at Basement Carpark
8) Staircase and Railing including ramps
9) Roof Trusses assumed as RC Roof Slab
10) Roofing including Rainwater Goods
11) Internal Wall assumed as RC Infill Load Bearing Wall
12) Curtain Walling system based on Aluminium Works which included powder coated 8.93mm thick laminated (+ Low E) glass window
13) Recreational Facilities including Swimming Pool, Gym Facilities, Cafe and Garden
14) Ancillary Building including Security Guard House
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA LUMPUR, WILAYAH
PERSEKUTUAN KUALA LUMPUR.
26199.03 25951.91
Estimated Cost Estimated Cost Estimated Cost Estimated Cost Estimated Cost
Construction per m2 Construction per m2 Construction per m2 Construction per m2 Construction per m2
Cost (RM) of CFA (RM) Cost (RM) of CFA (RM) Cost (RM) of CFA (RM) Cost (RM) of CFA (RM) Cost (RM) of CFA (RM)
1 SUB - STRUCTURE PRO-RATES OF CFA
0.01
1.01 SITE PREPARATION 1,447,770.28 16.13 1,447,770.28 180.73 0.00 0.00 0 0.00 0 0.00 BASEMENT PODIUM TOWER A TOWER B
8.93% 32.95% 29.20% 28.92%
1.02 PILING 4,968,813.21 55.38 4,968,813.21 620.29 0.00 0.00 0 0.00 0 0.00 0.0956 0.3485 0.2884 0.2675
1.03 FOUNDATIONS 2,722,836.52 30.35 990,873.39 123.70 1,731,963.13 58.58 0 0.00 0 0.00
1.04 BASEMENT CARCASS 6,356,294.35 70.84 6,356,294.35 793.50 0.00 0.00 0 0.00 0 0.00
1.05 CONTIGUOS BORED PILE,STRUTTING AND SHEET PILE 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0 0.00
Group Element Total 15,495,714.36 172.69 13,763,751.22 1,718.21 1,731,963.13 58.58 0.00 0.00 0.00 0.00
2 STRUCTURAL FRAME
2.01 FRAME 58,870,381.53 656.09 8,033,678.32 1,002.89 15,120,201.88 511.37 17,942,872.94 684.87 17,773,628.40 684.87
2.02 TRANSFER STUCTURES 5,266,559.45 58.69 0.00 0.00 4,073,580.28 137.77 599,316.08 22.88 593,663.09 22.88
2.03 STAIRCASE & RAMPS 1,594,080.51 17.77 228,785.37 28.56 800,748.80 27.08 283,610.74 10.83 280,935.61 10.83
Group Element Total 65,731,021.49 732.55 8,262,463.69 1,031.45 19,994,530.96 676.22 18,825,799.76 718.57 18,648,227.09 718.57
3.01 WALLS 4,417,508.63 49.23 201,229.30 25.12 704,302.56 23.82 1,764,309.23 67.34 1,747,667.54 67.34
3.02 EXTERNAL FINISHES 5,392,886.38 60.10 0.00 0.00 247,974.14 8.39 2,584,645.84 98.65 2,560,266.40 98.65
3.03 CURTAIN WALLING 699,719.25 7.80 0.00 0.00 253,173.74 8.56 224,330.74 8.56 222,214.76 8.56
3.04 DOORS 501,307.46 5.59 111,401.66 13.91 389,905.80 13.19 0.00 0.00 0.00 0.00
3.05 WINDOWS 17,939,855.55 199.93 0.00 0.00 1,105,711.55 37.40 8,456,956.75 322.80 8,377,187.26 322.80
Group Element Total 28,951,277.27 322.65 312,630.96 39.03 2,701,067.79 91.35 13,030,242.56 497.36 12,907,335.96 497.36
4.01 ROOFING 3,067,874.94 34.19 0.00 0.00 0.00 0.00 1,541,206.11 58.83 1,526,668.83 58.83
4.02 RAINWATER GOODS 1,417,121.27 15.79 0.00 0.00 0.00 0.00 711,918.19 27.17 705,203.08 27.17
Group Element Total 4,484,996.21 49.98 0.00 0.00 0.00 0.00 2,253,124.30 86.00 2,231,871.91 86.00
5 INTERNAL WALLING
5.01 WALLS 5,377,792.42 59.93 112,602.43 14.06 455,838.24 15.42 2,416,070.56 92.22 2,393,281.19 92.22
5.02 DOORS 7,256,076.22 80.87 92,035.65 11.49 167,102.49 5.65 3,515,046.72 134.17 3,481,891.36 134.17
Group Element Total 12,633,868.64 140.80 204,638.08 25.55 622,940.72 21.07 5,931,117.29 226.39 5,875,172.55 226.39
6 INTERNAL FINISHES
6.01 FLOORS 22,589,363.97 251.75 340,397.21 42.49 1,640,442.60 55.48 10,353,089.37 395.17 10,255,434.79 395.17
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA LUMPUR, WILAYAH
PERSEKUTUAN KUALA LUMPUR.
26199.03 25951.91
Estimated Cost Estimated Cost Estimated Cost Estimated Cost Estimated Cost
Construction per m2 Construction per m2 Construction per m2 Construction per m2 Construction per m2
6.02 WALLS Cost (RM)
17,119,134.05 of 190.79
CFA (RM) Cost (RM)
417,556.29 of CFA (RM)
52.13 Cost (RM)
1,541,167.08 of CFA (RM)
52.12 Cost (RM)
7,616,124.54 of CFA (RM)
290.70 Cost (RM)
7,544,286.13 of 290.70
CFA (RM)
6.03 CEILINGS 7,169,740.51 79.90 24,073.65 3.01 1,206,841.57 40.82 2,983,483.36 113.88 2,955,341.92 113.88
6.04 STAIRCASES AND RAILINGS 1,633,098.38 18.20 79,462.39 9.92 278,118.38 9.41 640,780.86 24.46 634,736.75 24.46
Group Element Total 48,511,336.92 540.64 861,489.55 107.55 4,666,569.64 157.83 21,593,478.14 824.21 21,389,799.59 824.21
7 FITTINGS,ETC.
7.01 SANITARY WARES & FITTINGS 19,067,630.49 212.50 118,713.56 14.82 166,093.47 5.62 9,435,913.44 360.16 9,346,910.03 360.16
7.02 SIGNAGES 62,041.39 0.69 0.00 0.00 0.00 0.00 31,167.69 1.19 30,873.70 1.19
7.03 MAIL BOX 156,756.88 1.75 0.00 0.00 156,756.88 5.30 0.00 0.00 0.00 0.00
7.04 LIFT CAR FINISHES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Group Element Total 19,286,428.77 214.94 118,713.56 14.82 322,850.35 10.92 9,467,081.13 361.35 9,377,783.73 361.35
8 SERVICES
8.01 CHILLER PLANT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8.02 HVAC 10,835,920.66 120.76 4,191,252.33 523.22 102,225.67 3.46 3,286,722.19 125.45 3,255,720.48 125.45
8.03 Fire Protection 10,754,140.13 119.85 1,226,708.00 153.14 1,840,062.00 62.23 3,861,898.57 147.41 3,825,471.56 147.41
8.04 Hot, Cold Water & Sanitary Plumbing 11,283,961.16 125.76 108,651.28 13.56 380,279.48 12.86 5,423,091.61 207.00 5,371,938.79 207.00
8.05 Natural Gas 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8.06 BMS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8.07 Pool Filtration System 347,567.27 3.87 0.00 0.00 347,567.27 11.75 0.00 0.00 0.00 0.00
8.08 Electrical HV & Genset 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8.09 Electrical LV 33,877,585.92 377.55 698,201.30 87.16 3,411,270.50 115.37 14,954,585.96 570.81 14,813,528.16 570.81
8.10 Telecom, telephone services 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8.11 Metering Utilities 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8.12 Vertical Transportation 12,605,885.06 140.49 584,146.67 72.92 2,044,513.33 69.15 5,012,251.34 191.31 4,964,973.73 191.31
8.13 Security 204,574.31 2.28 100,258.01 12.52 28,085.16 0.95 38,296.18 1.46 37,934.96 1.46
8.14 Building Maintenance Units 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8.15 Waste Collection System 2,520,264.80 28.09 1,393,170.39 173.92 0.00 0.00 566,217.60 21.61 560,876.80 21.61
8.16 Profits and Attendance 1,648,597.99 18.37 166,047.76 20.73 163,080.07 5.52 662,861.27 25.30 656,608.89 25.30
8.17 BWICS 2,472,896.98 27.56 249,071.64 31.09 244,620.10 8.27 994,291.90 37.95 984,913.33 37.95
Group Element Total 86,551,394.27 964.58 8,717,507.39 1,088.26 8,561,703.57 289.56 34,800,216.62 1,328.30 34,471,966.69 1,328.30
Estimated Cost Estimated Cost Estimated Cost Estimated Cost Estimated Cost
Construction per m2 Construction per m2 Construction per m2 Construction per m2 Construction per m2
Cost (RM) of CFA (RM) Cost (RM) of CFA (RM) Cost (RM) of CFA (RM) Cost (RM) of CFA (RM) Cost (RM) of CFA (RM)
9.01 Soft Scape and Hard Scape 2,395,807.45 26.70 0.00 2,395,807.45 81.03 0.00 0.00 0.00 0.00
9.02 Ancillary Works 102,225.67 1.14 0.00 102,225.67 3.46 0.00 0.00 0.00 0.00
SUB TOTAL ESTIMATED CONSTRUCTION COST 284,144,071.04 32,241,194.45 38,601,626.16 105,901,059.78 104,902,157.54
GRAND TOTAL ESTIMATED CONSTRUCTION COST 336,568,652.15 32,241,194.45 38,601,626.16 105,901,059.78 104,902,157.54
233320205.3
52,424,581.11
Amount(RM) RM/m2 Amount(RM) RM/m2 Amount(RM) RM/m2 Amount(RM) RM/m2 Amount(RM) RM/m2
a. Structure 81,226,735.85 905.24 22,026,214.91 2,749.67 21,726,494.09 734.80 18,825,799.76 718.57 18,648,227.09 718.57
b. Architectural 113,867,907.82 1,269.02 1,497,472.15 186.94 8,313,428.50 281.16 52,275,043.41 1,995.30 51,781,963.75 1,995.30
c. M&E 86,551,394.27 964.58 8,717,507.39 1,088.26 8,561,703.57 289.56 34,800,216.62 1,328.30 34,471,966.69 1,328.30
Analysis of Percentage
Structure 28.59%
Architectural 40.07%
M&E 30.46%
External 0.88%
1.00 SUBSTRUCTURE
1.01 Site Preparation ( 672,718.42) 0.51% ( - ) 0.00% ( - ) 0.00% ( 672,718.42)
1.02 Piling Jacquelyn ( 2,308,800.08) 1.76% ( - ) 0.00% ( - ) 0.00% ( 2,308,800.08)
1.04 Basement Carcass ( 2,953,504.65) 2.26% ( - ) 0.00% ( - ) 0.00% ( 2,953,504.65)
Group Element Total ( 6,395,440.64) 4.89% ( 804,770.97) 0.61% ( - ) 0.00% ( 7,200,211.61) 5.50% 15,495,714.36
2.03 Staircase and Ramps ( 106,307.01) 0.08% ( 372,074.54) 0.28% ( 262,321.12) 0.20% ( 740,702.67)
Group Element Total ( 3,839,221.97) 2.93% ( 9,290,623.89) 7.10% ( 17,412,615.97) 13.31% ( 30,542,461.83) 23.34% 65,731,021.49
3.02 External Finishes ( - ) 0.00% ( 115,223.23) 0.09% ( 2,390,625.95) 1.83% ( 2,505,849.18)
Jacquelyn
3.03 Curtain Walling System ( - ) 0.00% ( 117,639.27) 0.09% ( 207,491.06) 0.16% ( 325,130.33)
Group Element Total ( 145,266.56) 0.11% 1,255,073.45 0.96% 12,052,110.01 9.21% ( 13,452,450.02) 10.28% 28,951,277.27
4.02 Rainwater Goods ( - ) 0.00% ( - ) 0.00% ( 658,477.10) 0.50% ( 658,477.10)
Michelle
Group Element Total ( - ) 0.00% ( - ) 0.00% ( 2,083,990.52) 1.59% ( 2,083,990.52) 1.59% 4,484,996.21
( - )
5.00 INTERNAL WALLING ( - )
( - )
5.01 Walls ( 52,321.65) 0.04% ( 211,809.00) 0.16% ( 2,234,705.00) 1.71% ( 2,498,835.65)
Michelle
( - )
5.02 Doors ( 42,765.12) 0.03% ( 77,645.55) 0.06% ( 3,251,185.05) 2.48% ( 3,371,595.72)
( - )
( - )
Group Element Total ( 95,086.77) 0.07% ( 289,454.55) 0.22% ( 5,485,890.05) 4.19% ( 5,870,431.37) 4.49% 12,633,868.64
6.02 Walls Michelle ( 194,020.98) 0.15% ( 716,116.01) 0.55% ( 7,044,409.99) 5.38% ( 7,954,546.98)
6.04 Staircases and Railings ( 36,922.86) 0.03% ( 129,230.00) 0.10% ( 592,679.79) 0.45% ( 758,832.65)
Group Element Total ( 400,298.23) 0.31% ( 2,168,360.11) 1.66% ( 19,972,534.88) 15.26% ( 22,541,193.22) 17.22% 48,511,336.92
7.01 Sanitary Wares & Fittings ( 55,161.24) 0.04% ( 77,176.70) 0.06% ( 8,727,594.00) 6.67% ( 8,859,931.94)
7.03 Mail Box Michelle ( - ) 0.00% ( 72,838.38) 0.06% ( - ) 0.00% ( 72,838.38)
7.04 Lift Car Finishes ( - ) 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
7.05 Counter top and cabinet 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
Group Element Total ( 55,161.24) 0.04% ( 150,015.08) 0.11% ( 8,756,422.05) 6.69% ( 8,961,598.36) 6.85% 19,286,428.77
Alwin
8.00 SERVICES
8.01 Chiller Plant ( - ) 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
8.03 Fire Protection ( 570,000.00) 0.44% ( 855,000.00) 0.65% ( 3,572,000.00) 2.73% ( 4,997,000.00)
8.04 Hot, Cold Water & Sanitary Plumbing ( 50,485.71) 0.04% ( 176,700.00) 0.14% ( 5,016,000.00) 3.83% ( 5,243,185.71)
8.05 Natural Gas ( - ) 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
8.08 Electrical HV & Genset ( - ) 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
8.10 Telecom, telephone services ( - ) 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
8.11 Metering Utilities ( - ) 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
8.12 Vertical Transportation ( 271,428.57) 0.21% 950,000.00 0.73% ( 4,636,000.00) 3.54% ( 5,857,428.57)
8.14 Building Maintenance Units ( - ) 0.00% ( - ) 0.00% ( - ) 0.00% ( - )
8.15 Waste Collection System ( 647,348.13) 0.49% ( - ) 0.00% ( 523,713.72) 0.40% ( 1,171,061.85)
8.16 Profits and Attendance 2% ( 77,155.46) 0.06% 75776.5 0.06% ( 613,102.70) 0.47% ( 766,034.67)
( - )
Group Element Total ( 4,050,661.78) 3.10% ( 3,978,266.25) 3.04% ( 32,187,891.91) 24.60% ( 40,216,819.94) 30.73% 86,551,394.27
9.01 Soft and Hard Scape ( - ) 0.00% ( 1,113,231.71) 0.85% ( - ) 0.00% ( 1,113,231.71)
9.02 Ancillary Works ( - ) 0.00% ( 47,500.00) 0.04% ( - ) 0.00% ( 47,500.00)
Group Element Total ( - ) 0.00% ( 1,160,731.71) 0.89% 0.00% ( 1,160,731.71) 0.89% 2,498,033.11
Estimated
Construction Cost per m2
No. Element Cost (RM) Percentage of CFA (RM)
BASEMENT CARPARK
Structure 22,026,214.91 68% 2,749.67
1 Architectural 1,497,472.15 5% 186.94
M&E 8,717,507.39 27% 1,088.26
TOTAL 32,241,194.45 100% 4,024.87 4,024.87
PODIUM CARPARK
Structure 21,726,494.09 56% 734.80
2 Architectural 8,313,428.50 22% 281.16
M&E 8,561,703.57 22% 289.56
TOTAL 38,601,626.16 100% 1,305.53 1,305.53
TOWER A
Structure 21,078,924.06 20% 804.57
3 Architectural 50,021,919.11 47% 1,909.30
M&E 34,800,216.62 33% 1,328.30
TOTAL 105,901,059.78 100% 4,042.17 4,042.17
TOWER B
Structure 20,880,099.00 19.90% 804.57
4
4 Architectural 49,550,091.84 47% 1,909.30
M&E 34,471,966.69 33% 1,328.30
TOTAL 104,902,157.54 100% 4,042.17 4,042.17
EXTERNAL WORKS
Others 2,498,033.11 100.00% 96.26
4
3138.840309
4024.866669
1305.525222
4042.174835
4042.174836
3353.685391
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
Estimated
Construction Cost per m2
No. Element Cost (RM) Percentage of CFA (RM)
BASEMENT CARPARK
Structure 22,026,214.91 68% 2,749.67
1 Architectural 1,497,472.15 5% 186.94
M&E 8,717,507.39 27% 1,088.26
TOTAL 32,241,194.45 100% 4,024.87 4,024.87
PODIUM CARPARK
Structure 21,726,494.09 56% 734.80
2 Architectural 8,313,428.50 22% 281.16
M&E 8,561,703.57 22% 289.56
TOTAL 38,601,626.16 100% 1,305.53 1,305.53
TOWER A
Structure 18,825,799.76 18% 718.57
3 Architectural 52,275,043.41 49% 1,995.30
M&E 34,800,216.62 33% 1,328.30
TOTAL 105,901,059.78 100% 4,042.17 4,042.17
TOWER B
Structure 18,648,227.09 17.78% 718.57
4
4 Architectural 51,781,963.75 49% 1,995.30
M&E 34,471,966.69 33% 1,328.30
TOTAL 104,902,157.54 100% 4,042.17 4,042.17
EXTERNAL WORKS
Others 2,498,033.11 100.00% 96.26
4
3138.840309
4024.866669
1305.525222
4042.174835
4042.174836
3353.685391
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR BASEMENT CARPARK
1 SUBSTRUCTURE
1.05 Contiguous Bored Pile, Strutting and Sheet Piles 0.00 0 N/A
2 STRUCTURAL FRAME
2.04 Staircase & Ramps 228,785.37 28.56 Including ramp to upper floors
3.01 Walls 201,229.30 25.12 Allow for 230mm thick cement and sand
brick.
3.02 External Finishes 0.00 0.00 Allow for skim coat and weathershield paint
as external wall finishes; cement and sand
paving as external floor finishes.
3.03 Curtain Walling 0.00 0.00 Allow for vertical aluminium fins.
5 INTERNAL WALLING
5.01 Walls 112,602.43 14.06 RC Infill Load Bearing Wall ,half brick thick
clay brickwall and RC concrete lintel
6 INTERNAL FINISHES
6.01 Floors 340,397.21 42.49 Allowances made for PU paint for driveway
and carpark; 25mm thick cement render for
M&E rooms, staircase, loading area and
back of house (BOH); 300mm x 600mm
homogenous tiles for staircase lobby and
800mm x 800mm granite for lift lobby and
lounge.
6.02 Walls 417,556.29 52.13 Allowances made for 19mm thick plaster
and emulsion Paint for driveway and
carpark, M&E Rooms, staircase, staircase
lobby, loading area and back of house
(BOH);800mm x 800mm Granite for lift
lobby and lounge.
6.03 Ceilings 24,073.65 3.01 Allowances made for skim coat and paint
for driveway, carpark, M&E rooms,
staircase, staircase looby, loading area and
back of house (BOH); 12mm thick fibrous
plasterglass boards for lift lobby and 12mm
thick moisture resistance for lounge.
6.04 Staircases and Railings 79,462.39 9.92 Allowances made for concrete Grade 25
staircase finished with cement render with
nosing tiles and mild steel railings
7.01 Sanitary Wares & Fittings 118,713.56 14.82 Allowances according to benchmark made
for kitchen sink, sink tap, water closet and
counter top basin; toilet roll holder,
chromium plated bib tap, shower set, hand
bidet, wall hung urinal, bathtub and floor
trap
7.02 Signages 0.00 0.00 Allow for Corridor toilet signs and exit signs
8.02 HVAC 4,191,252.33 523.22 Allow for air-cool air conditioning unit
complete with refregerant pipe, insulation
and control wiring
8.03 Fire Protection 1,226,708.00 153.14 Allow for sprinkler, risers,fire extinguisher,
hose reel and fire alarm
8.04 Hot, Cold Water & Sanitary Plumbing 108,651.28 13.56 Allow for hot, cold water, sanitary plumbing
system and water unit metering utilities
8.09 Electrical LV 698,201.30 87.16 Allowance made for electrical utilities for
residential unit and connection to existings
8.12 Vertical Transportation 584,146.67 72.92 Allowances made for lift and conveyor
installation, lift car finishes deem included
8.16 Profits and Attendance 2% 166,047.76 20.73 Allow 2% for profit and attendance
1 SUBSTRUCTURE
1.03 Foundations 1,731,963.13 58.58 Work Below Lowest Floor Level which
includes reinforced concrete raft slab, lift pit
and sump pit
2 STRUCTURAL FRAME
2.01 Frame 15,120,201.88 511.37 Included Reinforced lift core wall,beams,
columns,shear wall,concrete wall for water
tank, carpark parapet wall
2.02 Transfer Structures 4,073,580.28 137.77 Include all transfer beam and slabs
2.04 Staircase & ramps 800,748.80 27.08 Grade 25 concrete for staircase structure &
ramp to upper floors
3.01 Walls 704,302.56 23.82 Allow for 230mm thick cement and sand
brick.
3.02 External Finishes 247,974.14 8.39 Allow for skim coat and weathershield paint
as external wall finishes; cement and sand
paving as external floor finishes.
3.03 Curtain Walling System 253,173.74 8.56 Allow for vertical aluminium fins.
4.03 Rainwater Goods 0.00 0.00 Assume roof falls under lvl 7 facility floor,
therefore all waterproofing inclluded in
Frame
5 INTERNAL WALLING
5.01 Walls 455,838.24 15.42 RC Infill Load Bearing Wall ,half brick thick
clay
brickwall and RC concrete lintel
6 INTERNAL FINISHES
6.01 Floors 1,640,442.60 55.48 Allow for PU paint for driveway and carpark;
25mm thick cement render for M&E rooms,
staircase, loading area and back of house
(BOH); 300mm x 600mm homogenous tiles
for staircase lobby and 800mm x 800mm
granite for lift lobby and lounge.
6.02 Walls 1,541,167.08 52.12 Allow for 19mm thick plaster and emulsion
Paint for driveway and carpark, M&E
Rooms, staircase, staircase lobby, loading
area and back of house (BOH);800mm x
800mm Granite for lift lobby and lounge.
6.03 Ceilings 1,206,841.57 40.82 Allow for skim coat and paint for driveway,
carpark, M&E rooms, staircase, staircase
looby, loading area and back of house
(BOH); 12mm thick fibrous plasterglass
boards for lift lobby and 12mm thick
moisture resistance for lounge.
6.04 Staircases and Railings 278,118.38 9.41 Allow for concrete Grade 25 staircase
finished with cement render with nosing tiles
and mild steel railings
7 FITTINGS, ETC.
7.01 Sanitary Wares & Fittings 166,093.47 5.62 Allowances according to benchmark made
for kitchen sink, sink tap, water closet and
counter top basin; toilet roll holder,chromium
plated bib tap, shower set, hand bidet, wall
hung urinal, bathtub and floor trap
7.02 Signages 0.00 0.00 Allow for Corridor toilet signs and exit signs
8.03 Fire Protection 1,840,062.00 62.23 Allow for sprinkler, risers,fire extinguisher,
hose reel and fire alarm
8.04 Hot, Cold Water & Sanitary Plumbing 380,279.48 12.86 Allow for hot, cold water, sanitary plumbing
system and water unit metering utilities
8.07 Pool Filtration System 347,567.27 11.75 Lump Sum refer to benchmark cost estimate
8.09 Electrical LV 3,411,270.50 115.37 Allowance made for electrical utilities for
residential unit and connection to existings
8.12 Vertical Transportation 2,044,513.33 69.15 Allowances made for lift and conveyor
installation, lift car finishes deem included
RM/m2 RM/sqft
Structure 21,726,494.09 734.80 68.26
Architectural 8,313,428.50 281.16 26.12
M&E 8,561,703.57 289.56 26.90
38,601,626.16 1305.53 121.29
0.00 0.00 0.00
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER A
1 SUBSTRUCTURE
2 STRUCTURAL FRAME
2.01 Frame 17,942,872.94 684.87 Allow for Concrete Grade 30 for beam,
column, slab, RC wall, lift shear wall.
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER A
2.02 Transfer Structures 599,316.08 22.88 Allowances for transfer beam & transfer slab
2.04 Staircase & Ramps 283,610.74 10.83 Grade 25 for staircase structure
3.01 Walls 1,764,309.23 67.34 RC Shear Load Bearing Wall, half brick thick
clay
brickwall and RC concrete lintol
3.02 External Finishes 2,584,645.84 98.65 Allow for Skim Coat with weathershield paint
as external wall finishes; cement and sand
paving as external floor finishes,
waterproofing and plaster and Skim Coat
with Paint Finish as ceiling finishes for AC
ledge.
3.03 Curtain Walling System 224,330.74 8.56 Allowances made for vertical aluminium fins
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER A
4.01 Roofing 1,541,206.11 58.83 Allowances made for RC flat roof with
waterproofing system, protectives topping
and structural steelwork properiatary
prefabricated cold formed steel roof truss
system including rainwater goods
5 INTERNAL WALLING
5.01 Walls 2,416,070.56 92.22 Allow for clay bricks 115mm thick
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER A
6 INTERNAL FINISHES
6.01 Floors 10,353,089.37 395.17 Allow for timber strips in living & dining room,
bedrooms, maid room and study room;
800mm x 800mm granite in bathroom,
powder room and lift lobby; 300mm x 600mm
homogeneous tiles in kitchen and yard;
cement render for M&E Rooms and
waterproofing to wet areas
6.02 Walls 7,616,124.54 290.70 Allow for 19mm thick plaster and emulsion
paint for M&E room, living & dining room,
bedroom, maid room, study room and yard;
800mm x 800mm granite in bathroom,
powder room and lift lobby; 300mm x 600mm
homogeneous tiles in kitchen.
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER A
6.03 Ceilings 2,983,483.36 113.88 Allowances made for 12mm thick fibrous
plasterglass boards in living and dining room,
bedroom, maid room, study room, kitchen
and yard; 12mm thick moisture resistance
plasterglass board in bathroom and powder
room.
6.04 Staircases and Railings 640,780.86 24.46 Allowances made for concrete Grade 25
staircase finished with cement render with
nosing tiles and mild steel railings
7 FITTINGS, ETC.
7.01 Sanitary Wares & Fittings 9,435,913.44 360.16 Allowances according to benchmark made
for kitchen sink, sink tap, water closet and
counter top basin; toilet roll holder,chromium
plated bib tap, shower set, hand bidet, wall
hung urinal, bathtub and floor trap
7.02 Signages 31,167.69 1.19 Allow for Unit Label, Corridor toilet signs and
exit signs
7.03 Mail Box 0.00 0.00 Allow for one unit of mail box for each unit
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER A
8.02 HVAC 3,286,722.19 125.45 Allow for air-cool air conditioning unit
complete with refregerant pipe, insulation
and control wiring
8.03 Fire Protection 3,861,898.57 147.41 Allow for sprinkler, risers,fire extinguisher,
hose reel and fire alarm
8.04 Hot, Cold Water & Sanitary Plumbing5,423,091.61 207.00 Allow for hot, cold water, sanitary plumbing
system and water unit metering utilities
8.09 Electrical LV 14,954,585.96 570.81 Allowance made for electrical utilities for
residential unit and connection to existings
8.12 Vertical Transportation 5,012,251.34 191.31 Allowances made for lift and conveyor
installation, lift car finishes deem included
8.16 Profit and Attendance 662,861.27 25.30 Allow 2% for profit and attendance
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER A
RM/m2 RM/sqft
Structure 18,825,799.76 718.57 66.76
Architectural 52,275,043.41 1995.31 185.37
M&E 34,800,216.62 1328.30 123.40
105,901,059.78 4042.18 375.53
0.00 0.00 0.00
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER B
1 SUBSTRUCTURE
2 STRUCTURAL FRAME
2.01 Frame 17,773,628.40 684.87 Allow for Concrete Grade 30 for beam,
column, slab, RC wall, lift shear wall.
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER B
2.02 Transfer Structures 593,663.09 22.88 Allowances for transfer beam & transfer slab
2.04 Staircase & Ramps 280,935.61 10.83 Grade 25 for staircase structure
3.01 Walls 1,747,667.54 67.34 RC Shear Load Bearing Wall, half brick thick
clay
brickwall and RC concrete lintol
3.02 External Finishes 2,560,266.40 98.65 Allow for Skim Coat with weathershield
paint as external wall finishes; cement and
sand paving as external floor finishes,
waterproofing and plaster and Skim Coat
with Paint Finish as ceiling finishes for AC
ledge.
3.03 Curtain Walling System 222,214.76 8.56 Allowances made for vertical aluminium fins
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER B
4.01 Roofing 1,526,668.83 58.83 Allowances made for RC flat roof with
waterproofing system, protectives topping
and structural steelwork properiatary
prefabricated cold formed steel roof truss
system including rainwater goods
5 INTERNAL WALLING
5.01 Walls 2,393,281.19 92.22 Allow for clay bricks 115mm thick
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER B
6 INTERNAL FINISHES
6.01 Floors 10,255,434.79 395.17 Allow for timber strips in living & dining
room, bedrooms, maid room and study
room; 800mm x 800mm granite in bathroom,
powder room and lift lobby; 300mm x
600mm homogeneous tiles in kitchen and
yard; cement render for M&E Rooms and
waterproofing to wet areas
6.02 Walls 7,544,286.13 290.70 Allow for 19mm thick plaster and emulsion
paint for M&E room, living & dining room,
bedroom, maid room, study room and yard;
800mm x 800mm granite in bathroom,
powder room and lift lobby; 300mm x
600mm homogeneous tiles in kitchen.
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER B
6.03 Ceilings 2,955,341.92 113.88 Allowances made for 12mm thick fibrous
plasterglass boards in living and dining
room, bedroom, maid room, study room,
kitchen and yard; 12mm thick moisture
resistance plasterglass board in bathroom
and powder room.
6.04 Staircases and Railings 634,736.75 24.46 Allowances made for concrete Grade 25
staircase finished with cement render with
nosing tiles and mild steel railings
7 FITTINGS, ETC.
7.01 Sanitary Wares & Fittings 9,346,910.03 360.16 Allowances according to benchmark made
for kitchen sink, sink tap, water closet and
counter top basin; toilet roll holder,chromium
plated bib tap, shower set, hand bidet, wall
hung urinal, bathtub and floor trap
7.02 Signages 30,873.70 1.19 Allow for Unit Label, Corridor toilet signs and
exit signs
7.03 Mail Box 0.00 0.00 Allow for one unit of mail box for each unit
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER B
8 SERVICES
8.02 HVAC 3,255,720.48 125.45 Allow for air-cool air conditioning unit
complete with refregerant pipe, insulation
and control wiring
8.03 Fire Protection 3,825,471.56 147.41 Allow for sprinkler, risers,fire extinguisher,
hose reel and fire alarm
8.04 Hot, Cold Water & Sanitary Plumbing 5,371,938.79 207.00 Allow for hot, cold water, sanitary plumbing
system and water unit metering utilities
8.09 Electrical LV 14,813,528.16 570.81 Allowance made for electrical utilities for
residential unit and connection to existings
8.12 Vertical Transportation 4,964,973.73 191.31 Allowances made for lift and conveyor
installation, lift car finishes deem included
8.16 Profit and Attendance 656,608.89 25.30 Allow 2% for profit and attendance
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR TOWER B
RM/m2 RM/sqft
Structure 18,648,227.09 718.57 66.76
Architectural 51,781,963.75 1995.31 185.37
M&E 34,471,966.69 1328.30 123.40
104,902,157.54 4042.18 375.53
0.00 0.00 0.00
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
COST PLAN FOR EXTERNAL WORK
1 EXTERNAL WORK
1.01 Soft scape and Hard scape (Lvl7 & 2,395,807.45 12.15 Turfing, decoration, water feature, pool
Roof)
tennis court, handrail, waterproofing,
sauna
etc stated in cost breakdown
BRIEF SPECIFICATION
ELEMENT BRIEF SPECIFICATION
Budgetary allowance made to cover insurance,
contractor's organisation and administration,
Preliminaries
plant and equipment and other preliminaries to the
contract.
Work Below Lowest Floor Level Reinforced concrete raft slab,lift pit and sump pit.
Reinforced concrete lift core wall.
Reinforced concrete lintel, half and one clay brick partywall and
External Walls half cement and sand brickwall.
Half and one clay brick partywall and half cement and sand
Internal Walls brickwall.
Builder's Works in Connection Budgetary allowance made to cover Builder's Works in connection
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (432) UNIT DI ATAS 7 TINGKAT PODIUM BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, 2 TINGKAT
BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
1 Driveway / Carpark PU paint 19mm thick Plaster and Emulsion Paint Skim Coat with Paint Finish
2 M&E Rooms 25mm thick Cement Render 19mm thick Plaster and Emulsion Paint Skim Coat with Paint Finish
3 Staircase 25mm thick Cement Render with Nosing Tiles 19mm thick Plaster and Emulsion Paint Skim Coat with Paint Finish
4 Staircase Lobby 300mm x 600mm Homogeneous tiles 19mm thick Plaster and Emulsion Paint Skim Coat with Paint Finish
5 Lift Lobby 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Fibrous Plasterglass Boards
6 Loading Area & BOH 25mm thick Cement Render 19mm thick Plaster and Emulsion Paint Skim Coat with Paint Finish
7 Lounge 800mm x 800mm Granite 800mm x 800mm Granite 12mm thick Moisture Resistance Plasterglass Board
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED
PUTRA, MUKIM KUALA LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
Cost
GFA Cost Reference Total Cost CFA Total Cost
Reference
Ref from JUBM & Ref from JUBM
Arcadis Cost & Arcadis Cost
(m2) (Area x RM/m2) (m2) (Area x RM/m2)
Handbook Handbook
(RM/m2) (RM/m2)
Basement Basement
Basement 2 3925.93 3,512.50 13,789,829.13 3983.40 3,512.50 13,991,692.50
Basement 1 3970.39 3,512.50 13,945,994.88 4027.10 3,512.50 14,145,188.75
Total 7,896.32 27,735,824.00 8,010.50 28,136,881.25
Podium Podium
Ground Floor 3,909.31 3,650.00 14,268,981.50 5,855.26 3,650.00 21,371,699.00
Podium 1 3,476.44 3,175.00 11,037,697.00 3,539.27 3,175.00 11,237,175.90
Podium 2 3,301.06 3,175.00 10,480,865.50 3,357.15 3,175.00 10,658,951.25
Podium 3 3,300.69 3,175.00 10,479,690.75 3,355.85 3,175.00 10,654,823.75
Podium 4 3,266.99 3,175.00 10,372,693.25 3,319.42 3,175.00 10,539,158.50
Podium 5 3,324.93 3,175.00 10,556,652.75 3,375.85 3,175.00 10,718,323.75
Podium 6 3,323.70 3,175.00 10,552,747.50 3,374.23 3,175.00 10,713,180.25
Podium 7 2,396.11 3,650.00 8,745,801.50 3,390.86 3,650.00 12,376,639.00
Total 26,299.23 86,495,129.75 29,567.89 98,269,951.40
Tower Tower A Tower B Tower A Tower B Tower A Tower B Tower A Tower B
Level 8 729.76 718.64 3,512.50 2,563,282.00 2,524,223.00 1,011.57 1,056.43 3,512.50 3,553,139.63 3,710,710.38
Level 9-15 5,108.32 5,030.48 3,512.50 17,942,974.00 17,669,561.00 5,518.24 5,441.80 3,512.50 19,382,818.00 19,114,322.50
Level 16 732.35 725.02 3,512.50 2,572,379.38 2,546,632.75 790.97 783.36 3,512.50 2,778,282.13 2,751,552.00
Level 17 740.34 727.59 3,512.50 2,600,444.25 2,555,659.88 798.29 786.02 3,512.50 2,803,993.63 2,760,895.25
Level 18 740.34 734.07 3,512.50 2,600,444.25 2,578,420.88 797.99 791.84 3,512.50 2,802,939.88 2,781,338.00
Level 19-21 2,228.97 2,218.17 3,512.50 7,829,267.66 7,791,311.59 2,402.78 2,381.50 3,512.50 8,439,747.19 8,365,004.70
Level 22 745.53 739.39 3,512.50 2,618,670.61 2,597,103.86 803.51 793.83 3,512.50 2,822,318.34 2,788,334.90
Level 23 742.74 739.39 3,512.50 2,608,877.76 2,597,103.86 800.70 793.83 3,512.50 2,812,448.21 2,788,334.90
Level 24 742.64 739.39 3,512.50 2,608,530.03 2,597,103.86 800.72 793.83 3,512.50 2,812,521.98 2,788,334.90
Level 25 737.89 736.48 3,512.50 2,591,838.63 2,586,871.95 796.36 791.13 3,512.50 2,797,214.50 2,778,833.59
Level 26 734.41 724.18 3,512.50 2,579,618.64 2,543,668.20 794.13 783.04 3,512.50 2,789,395.68 2,750,442.05
Level 27 727.96 723.84 3,512.50 2,556,941.94 2,542,480.98 788.38 780.51 3,512.50 2,769,198.80 2,741,551.91
Level 28 737.16 719.23 3,512.50 2,589,267.48 2,526,309.43 797.51 779.62 3,512.50 2,801,260.90 2,738,401.20
Level 29 737.16 719.23 3,512.50 2,589,267.48 2,526,309.43 797.51 779.62 3,512.50 2,801,260.90 2,738,401.20
Level 30 740.28 724.38 3,512.50 2,600,233.50 2,544,370.70 798.84 783.80 3,512.50 2,805,918.48 2,753,111.55
Level 31 743.79 734.01 3,512.50 2,612,555.35 2,578,203.10 803.08 790.97 3,512.50 2,820,832.55 2,778,292.66
Level 32-34 2,233.70 2,209.41 3,512.50 7,845,864.23 7,760,552.63 2,410.43 2,381.71 3,512.50 8,466,638.89 8,365,763.40
Level 35 766.85 768.20 3,512.50 2,693,543.06 2,698,302.50 825.89 822.35 3,512.50 2,900,952.68 2,888,493.84
Level 37 762.19 763.71 3,512.50 2,677,195.89 2,682,520.84 821.28 817.85 3,512.50 2,884,735.46 2,872,701.64
Level 36&38 1,547.92 1,538.53 3,512.50 5,437,054.95 5,404,079.60 1,658.17 1,647.36 3,512.50 5,824,329.15 5,786,337.95
Roof Facilities Level 770.35 763.09 3,650.00 2,811,777.50 2,785,278.50 817.37 809.66 3,650.00 2,983,400.50 2,955,259.00
Lift Motor Room 112.12 111.06 3,512.50 393,821.50 390,098.25 122.97 121.81 3,512.50 431,932.13 427,857.63
Roof Top 0.00 0.00 3,512.50 0.00 0.00 242.32 240.03 3,512.50 851,149.00 843,105.38
23,862.76 23,607.47 83,923,850.06 83,026,166.76 26,199.02 25,951.90 92,136,428.56 91,267,380.51
Total GFA 47,470.23 Total Construction Cost 281,180,970.58 Total CFA 89,729.30 Total Construction Cost 309,810,641.73
SUMMARY SUMMARY
Construction Construction Construction Construction
Based on Cost Including Cost Excluding Based on Cost Including Cost Excluding
GFA CFA
GFA 10% 10% CFA 10% 10%
Preliminaries Preliminaries Preliminaries Preliminaries
Basement 7,896.32 27,735,824.00) 25,214,385.45) Basement 8,010.50 28,136,881.25) 25,578,982.95)
Podium 26,299.23 86,495,129.75) 78,631,936.14) Podium 29,567.89 98,269,951.40) 89,336,319.45)
Tower A 23,862.76 83,923,850.06) 76,294,409.15) Tower A 26,199.02 92,136,428.56) 83,760,389.60)
Tower B 23,607.47 83,026,166.76) 75,478,333.42) Tower B 25,951.90 91,267,380.51) 82,970,345.92)
Total 47,470.23 281,180,970.58) 255,619,064.16) Total 89,729.30 309,810,641.73) 281,646,037.93)
CADANGAN PEMBANGUNAN 2 BLOK 31 TINGKAT PANSAPURI SERVICE (404) UNIT DI ATAS 7 TINGKAT PODIUM
BERSERTA 2 TINGKAT BASEMEN DI ATAS LOT 160, JALAN ROBSON OFF JALAN SYED PUTRA, MUKIM KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR.
RATE BREAKDOWN
A Signages
0.8571428571
Cost Estimation for External Works
A Guard House
B Playground
C Water Feature
D Water Curtain
E Sauna
F Tennis Court
H Fencing
Material Cost
Supply and install 2400mm high anti-climb fencing "PLYTEC 580 series" m 160 143.00 22,880.00 Qs Online
22,880.00
Gymnasium
A Security
4 INTERNAL FINISHES
4.01 Staircase and Railings 0.58% 145,793) 538,144) 476,829) 472,332) 1,633,098)
(a) 900mm Mild Steels
Railing, Wall Mounted
Railing, 25mm thick
Cement Render With
Nosing Tiles, 19mm thick
Plaster and Emulsion
Paint, Skim Coat With
Paint Finish
5 SERVICES
5.01 Chiller Plant 0 0) 0) 0) 0) 0)
5.04 Hot, Cold Water & 4.01% 1,007,365) 3,718,327) 3,294,672) 3,263,597) 11,283,961)
Sanitary Plumbing
(a) Hot, Cold Water and
Sanitary Plumbing
system, water unit
metering utilities
5.07 Pool Filtration Sytem 0.12% ( 31,029) ( 114,531) ( 101,482) ( 100,525) ( 347,567)
5.13 Security ( -) ( -) ( -) ( -) ( -)
5.16 Profits and Attendance 0.59% ( 147,177) ( 543,251) ( 481,355) ( 476,815) ( 1,648,598)
6 OTHERS
6.01 Soft and Hard Scape 0.00% ( -) ( -) ( -) ( -) ( -)
Works
6.02 External Works and 0.00% ( -) ( -) ( -) ( -) ( -)
Ancillary Works
UNIT RATE BASEMENT PODIUM TOWER A
1 Door
7 Internal Finishes
7.01 Floors #REF! #REF! #REF!
(a) 600mm x 600mm Granite m2 #REF! 166.00 #REF! #REF! #REF! #REF! #REF!
Tiles
(b) PU Paint m2 #REF! 7,334.00 #REF! #REF! #REF! #REF! #REF!
25mm thick Cement m2 #REF! 35.00 #REF! #REF! #REF! #REF! #REF!
(c)
Render
25mm thick Cement m2 #REF! 115.00 #REF! #REF! #REF! #REF! #REF!
(d)
Render With Nosing Tiles
300mm x 600mm m2 #REF! 9.00 #REF! #REF! #REF! #REF! #REF!
(e)
Homogenous Tiles
(f) Timber Strips m2 #REF! 0.00 #REF! 0.00 #REF! #REF! #REF!
waterproofing system to m2 15.00 325.00 4,875.00 1,035.00 15,525.00 4,820.00 72,300.00
(g)
floor of wet areas
waterproofing system to m 6.00 587.20 3,523.20 3,369.96 20,219.76 801.35 4,808.10
(h)
scupper drain
(i) floor hardener m2 9.60 7,334.00 70,406.40 #REF! #REF! 0.00 0.00
Based on nearby High Class Luxury Apartments with same amenities Conversion sq ft to sq m = X 10.764
Selling Price at launch per square ft. (RM) Selling Price at launch per square metre (RM)
Project Name Location Distance Lowest Highest Avg Lowest Highest Avg
Setia Sky Seputeh Taman Seputeh 0.8 m 1416 1464 1440 15241.824 15758.496 15500.16
The Estabishment Bangsar 1.2 km 1020 1388 1204 10979.28 14940.432 12959.856
Sentral Suites KL Sentral 1.9 km 608 1215 912 6544.512 13078.26 9811.386
The Sloth Residency Jalan Robson 0 km 1041 1341.75 1191.375 11205.324 14442.597 12823.9605
Projected Revenue
Tower A Tower B Price per m2 Cost
Sellable Area 21,735.00 21,514.00 12823.9605 278,728,781.47 275,894,686.20
Expected Turnout Rate Percentage Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Onwards
Turnout at 50% 0.5 109,027,407.76
Turnout at 20% 0.2 43,610,963.10
Turnout at 10% 0.1 21,805,481.55
Turnout at 8% 0.08 17,444,385.24
Turnout at 6% 0.06 13,083,288.93
Turnout at 4% 0.04 8,722,192.62
Turnout at 2% 0.02 4,361,096.31
Total 1 c