1) Define Distribution Keys

IMG > Production Planning for Process Industries > Master Data > Material List > Item Data >
Item Data from related areas > Define Distribution Keys
2) Determine Person responsible for Resource u2013
IMG > Production Planning for Process Industries > Master Data > Resource > General Data >
Determine Person responsible
3) Define Planner Group-
IMG > Production Planning for Process Industries > Master Data > Master Recipe > Define
Capacity Planner
4) Define Capacity Planner u2013
IMG > Production Planning for Process Industries > Master Data > Resource > Capacity
Requirement Planning > Determine Capacity Planner
5) Determine Standard Value Parameter u2013
IMG > Production Planning for Process Industries > Master Data > Resource > General Data >
Standard Value > Define Parameter
6) Define Setup Groups and Setup Group Categories
Define set up groups and set up categories u2013
IMG > Production Planning for Process Industries > Master Data > Master Recipe > Data for
operations and phases > Define set up groups and set up group categories
7) Define copy setting between plants-Process
IMG > Production Planning for Process Industries > Process Management > Tools > Define copy
setting between plants
8) Define Set Up Control Recipe destination u2013
IMG > Production Planning for Process Industries > Process Management > Control Recipe/PI
sheet > Set up control recipe destination
9Define MRP controller u2013
IMG > Material Management > Consumption based Planning > Master Data > Define MRP
controller
10) Special Procurement u2013
IMG > Material Management > Consumption based Planning > Master Data > Define Special
procurement types
11) Define Floats (Scheduled Margin Key)-
IMG > Material Management > Consumption based Planning > Planning > Define Floats
(Scheduled Margin Key)
12Define Splitting of Forecast requirements for MRP-
IMG > Material Management > Consumption based Planning > Evaluation > Forecast > Define
Splittng of forecast requirements of MRP
13) Maintain Correction Factors for Forecast
IMG > Material Management > Consumption based Planning > Planning > Procurement >
Maintain Correction factors for forecast
14 Carry Out Overall Maintenance of Plant Parameters
Maintaining plant parameters in MRP u2013
IMG > Material Management > Consumption based Planning > Plant Parameters > Carry out
overall maintenance of plant parameters
15) Define Planning Horizon
Define Planning Horizon u2013
IMG > Material Management > Consumption based Planning > Planning > MRP calculation >
Define Planning Horizon
16) Activate Requirement Planning u2013
IMG > Material Management > Consumption based Planning > Planning > Activate Requirement
Planning
17) Define Range of Coverage Profiles (Dynamic Safety Stock)
Range of coverage profile u2013
IMG > Material Management > Consumption based Planning > Planning > MRP calculation >
Define range of coverage profile (Dynamic Safety Stock)
18) Define Stock in Transfer and Blocked Stock Availability
IMG > Material Management > Consumption based Planning > Planning > MRP calculation >
Stocks > Define Stock in transfer and blocked stock
19) Define MRP Areas
IMG > Material Management > Consumption based Planning > Master Data > MRP areas >
Define MRP areas
20) Carry out maintenance of MRP groups
IMG > Material Management > Consumption based Planning > MRP groups> Carry out
maintenance of MRP groups
21) Define Scope of total Planning - MRP
IMG > Material Management > Consumption based Planning > Planning > Define Scope of total
Planning
22 Define Order Types
Define Order Type-
IMG > Production Planning for Process Industries > Process Order > Master Data > Order >
Define Order Type
23Define Order Type Dependent parameters u2013
IMG > Production Planning for Process Industries > Process Order > Master Data > Order >
Define Order Type Dependent parameters
24) Define Production Scheduler u2013
IMG > Production Planning for Process Industries > Process Order > Master Data > Bill of
Material > Define Production Scheduler
25 Define Checking Control - Process Order
Define Availability Check u2013 Define Checking Control u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Availabilty
Check > Define Checking Control
26) Define Checking Rule for backorder processing u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Availabilty
Check > Define Checking rule for back order processing
27Define Stock and batch determination for good movement u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Define Stock
and batch determination for good movement
28) Specify Scheduling Parameters
Specify Scheduling Parameters u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling >
Specify Scheduling Parameters
29) Define Reduction Strategies
Define Reduction Strategy u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling >
Resource data > Define Reduction Strategy
30) Define Confirmation Parameters
Define Order Confirmation u2013
IMG > Production Planning for Process Industries > Process Order > Operations >
Confirmation > Define Confirmation Parameters
31) Define Valuation of Goods Received
Define valuation of goods receive u2013
IMG > Production Planning for Process Industries > Process Order > Integration > Define
Valuation of goods received
32) MRP creation indicator u2013
IMG > Material Management > Consumption based Planning > Planning > Define creation
indicator
33) Define safety stock u2013
IMG > Material Management > Consumption based Planning > Planning > MRP calculation >
Stocks > Define Safety Stocks
34) Define alternative determination of Production u2013
IMG > Production Planning for Process Industries > Process Order > Operations > BOM selection
> Define alternate determination of production
35) Define no. ranges u2013
IMG > Production Planning for Process Industries > Process Order > Master data > Order >
Number Ranges > Define number ranges for orders
Further you need to do Manual Configuration in PP after Transport Request transfer in
Production Server:
1) Define Distribution Keys
2) Determine Person responsible for Resource
3Define Planner Group-
4) Define Capacity Planner
5) Determine Standard Value Parameter u2013
6) Define Setup Groups and Setup Group Categories
7) Define copy setting between plants-Process
8) Define Set Up Control Recipe destination
9Define MRP controller u2013
10) Special Procurement
11) Define Floats (Scheduled Margin Key)
12Define Splitting of Forecast requirements for MRP
13) Maintain Correction Factors for Forecast
14 Carry Out Overall Maintenance of Plant Parameters
15) Define Planning Horizon
16) Activate Requirement Planning
17) Define Range of Coverage Profiles (Dynamic Safety Stock)
18) Define Stock in Transfer and Blocked Stock Availability
19) Define MRP Areas
20) Carry out maintenance of MRP groups
21) Define Scope of total Planning - MRP
22 Define Order Types
23Define Order Type Dependent parameters
24) Define Production Scheduler
25 Define Checking Control - Process Order
26) Define Checking Rule for backorder processing
27Define Stock and batch determination for good movement
28) Specify Scheduling Parameters
29) Define Reduction Strategies
30) Define Confirmation Parameters
31) Define Valuation of Goods Received
32) MRP creation indicator
33) Define safety stock
34) Define alternative determination of Production
35) Define no. ranges
Following Number ranges you need to define:
In OPPQ you need to define Number Ranges for:
Planned Orders
Reservations / Dependent Requirements
Purchase Requisitions
MRP Lists
Simulative Dependent Requirements
Similarly you need to define Number Range for :
Production Order in CO82
Confirmations in CO80
Reservations in CO83
Operations in CO81
Capacity Requirements in CO84