PERHITUNGAN KAPASITAS DUKUNG FONDASI TIANG PANCANG BERDASARKAN HAS

UJI LAPANGAN (Nspt)-MAYERHOF'S METHOD

Proyek : DED Drainase Kota Utama


Lokasi : Muara Tebo-Jambi
Bor No : BH-1

Type of foundation : Circle


D : 0.25 m
Ap : 0.049 m2
Fs : 4

Depth (m) Nvalue N60 40Nb Ap As(m2) 0,2NaveAs


0.0 0 0 0 0 0
2.0 3 2 3.68 1.57 0.29
4.0 3 2 3.68 3.14 0.79
6.0 3 2 3.68 4.71 1.33
8.0 2 1 2.45 6.28 1.73
10.0 13 8 15.95 7.85 4.71
12.0 10 6 12.27 9.42 7.30
14.0 22 14 27.00 11.00 13.74
16.0 18 11 22.09 12.57 20.42
18.0 11 7 13.50 14.14 26.15
20.0 11 7 13.50 15.71 28.27
22.0 11 7 13.50 17.28 31.53
24.0 26 16 31.91 18.85 36.29
26.0 26 16 31.91 20.42 43.39
28.0 26 16 31.91 21.99 54.98
30.0 32 20 39.27 23.56 54.78

Hubungan Qall Vs Depth

Qall (ton)

0 10 20 30 40 50 60 70 80
0.0

5.0

10.0
Depth (m)

15.0
Qall (ton)

0 10 20 30 40 50 60 70 80
0.0

5.0

10.0

Depth (m)
15.0

20.0

25.0

30.0
CANG BERDASARKAN HASIL
ETHOD

Qall (ton)
0
1
1
1
1
5
5
10
11
10
10
11
17
19
22
24

Qall (ton)

0 40 50 60 70 80
Qall (ton)

0 40 50 60 70 80