Professional Documents
Culture Documents
A Famous Example: “Put a man on the moon and return him safely to
Earth by the end of the decade at a cost of $9 billion.”
Scope – “Put a man on the moon and return him safely to Earth.”
Schedule – “By the end of the decade.”
Resources –”At a cost of $9 billion.”
The advantage in keeping it short and simple: Longer statements
offer greater opportunity for people to come away with different
understanding of what the project will accomplish while mistakenly
assuming they have reached agreement
WHAT’S IN/OUT LIST FOR PROJECT WORK PRODUCTS
What’s In/Out List
Objective statements
Organization definitions and roles
Issue checklists
Etc.
THE WORK BREAKDOWN STRUCTURE
Need to identify all of the work required by a project
Identify tasks and sub-tasks
Assign “owners” for each task
Estimate how long each task will take
Important questions:
• Are all tasks identified?
• Do all tasks have owners?
• How long will it take to do each task?
WBS – WORK BREAKDOWN STRUCTURE
Work breakdown structure, or the WBS = hierarchical structure
defining tasks that can be completed independently of other tasks,
facilitating resource allocation, assignment of responsibilities, and
measurement and control of the project.
Task 1 Subtask 1.1 Work package 1.1.1
Work package 1.1.2
Work package 1.1.3
Subtask 1.2 Work package 1.2.1
Work package 1.2.2
Task 2 Subtask 2.1 Work package 2.1.1
Work package 2.1.2
Work package 2.1.3
Work package 2.1.4
Subtask 2.2 Work package 2.2.1
Subtask 2.3 Work package 2.3.1
Work package 2.3.2
Terminology for Different Levels
-tasks, sub-tasks, and work packages
-phases, entries, and activities.
Level of Detail
facilitates resource allocation and the assignment of individual responsibilities.
! Beware: micro-management OR tasks too large to manage effectively.
Defining tasks so that their duration is between several days and a few months
works well for most projects.
THE 100% RULE
The 100% rule states that
the WBS includes 100% of the work defined by the project scope and
captures all deliverables – internal, external, interim – in terms of the
work to be completed, including project management.
The rule applies at all levels within the hierarchy: the sum of the work at the “child”
level must equal 100% of the work represented by the “parent” and the WBS should
not include any work that falls outside the actual scope of the project, that is, it
cannot include more than 100% of the work…
It is important to remember that the 100% rule also applies to the activity level.
The work represented by the activities in each work package must add up to 100%
of the work necessary to complete the work package.
TOP DOWN VS. BOTTOM UP
You can create a WBS top down or bottom up
Overall
Productivity
Number of people
DEVELOPING A PROJECT SCHEDULE
Given what you need to do, figure out when things will happen
and when you’ll be finished (when you’ll deliver project results)
Identify dependencies between tasks (e.g., task A must be
done before task B can be started)
Use task time estimates and dependencies to create a
schedule, typically by generating a “Gantt Chart”
Important questions:
Have all dependencies been identified?
Is there a way to eliminate dependencies?
Does estimated completion fit with project objectives?
PERT – PROGRAM EVALUATION AND REVIEW TECHNIQUE
PERT
• 1957 - the Critical Path Method (CPM) was developed as a network
model for project management.
• a deterministic method that uses a fixed time estimate for each
activity
• does not consider the time variations that can have a great impact
on the completion time of a complex project.
If the critical path is not immediately obvious, it may be helpful to determine the
following four quantities for each activity:
ES - Earliest Start time
EF - Earliest Finish time
LS - Latest Start time
LF - Latest Finish time
STEPS IN THE PERT PLANNING PROCESS – CRITICAL PATH
ES - Earliest Start time EF - Earliest Finish time
LS - Latest Start time LF - Latest Finish time
• These times are calculated using the expected time for the relevant
activities.
• The earliest start and finish times of each activity are determined by working
forward through the network and determining the earliest time at which an
activity can start and finish considering its predecessor activities.
• The latest start and finish times are the latest times that an activity can start
and finish without delaying the project. LS and LF are found by working
backward through the network.
• The difference in the latest and earliest finish of each activity is that
activity's slack.
• The critical path then is the path through the network in which none of the
activities have slack.
CRITICAL PATH - EXAMPLE
Source: syque.com
STEPS IN THE PERT PLANNING PROCESS – CRITICAL PATH
The variance in the project completion time can be calculated by summing the
variances in the completion times of the activities in the critical path.
Given this variance, one can calculate the probability that the project will be
completed by a certain date assuming a normal probability distribution for the
critical path.
The normal distribution assumption holds if the number of activities in the path is
large enough for the central limit theorem to be applied.
Since the critical path determines the completion date of the project, the project
can be accelerated by adding the resources required to decrease the time for the
activities in the critical path.
Limitations
The activity time estimates - subjective and depend on judgement.
Even if the activity times are well-estimated, PERT assumes a beta distribution for these time
estimates, but the actual distribution may be different.
Even if the beta distribution assumption holds, PERT assumes that the probability distribution
of the project completion time is the same as the that of the critical path.
Because other paths can become the critical path if their associated activities are delayed,
PERT consistently underestimates the expected project completion time.
The underestimation of the project completion time due to alternate paths becoming critical
is perhaps the most serious of these issues. To overcome this limitation, Monte Carlo
simulations can be performed on the network to eliminate this optimistic bias in the expected
project completion time.
CRITICAL PATH “WHAT IF” ANALYSIS
The results of this process for arriving at a project schedule are often poorly
received
“That project completion date is far too late!”
So a “what if” exercise ensues
To shorten a project’s overall duration (to be “done” sooner), you must
shorten tasks on the Critical Path (“What if task 14, on the critical
path, could be done faster?) or remove tasks from the Critical Path
(Does task 15 really depend on task 14 – what if we can, by making an
adjustment, do them at the same time, thus moving task 14 off the
Critical Path?)
Sometimes when you shorten the Critical Path, a different sequence of
tasks becomes the new Critical Path (the “bottleneck” shifts) – that is,
you’ve shortened the old Critical Path to a point where it is no longer
the Critical Path
ASSIGNING PROJECT RESOURCES
With tasks and dependencies identified, assign people and other resources
(e.g., specialized equipment) to tasks
Allocate resources across tasks
Make sure resources available can cover tasks
Make sure key there are no conflicts for key resources (same
person/machine can’t be two places at once)
Analyze the merits of different ways of allocating resources
Re-examine scope, schedule, and resources
Important questions:
Is work spread reasonably across resources?
Should we make adjustments to scope, schedule, or resources?
Assigning more resources is one way of shortening the CP
KEY RESOURCES AND “SWITCHING COST”
A very common problem: Some resources are over allocated while others are
under allocated
People working on some tasks are overwhelmed, while others have nothing
much to do
Over allocated resources end up being asked to multi-task
Literally, work on more than one task at once
Their time gets allocated in smaller and smaller fractions
But there are big hidden costs in doing this…
Switching tasks takes effort
People work more hours
Value-add
Burn out, morale issues time on
Worst for key people each task
Number of tasks
THE GANTT CHART – EXAMPLE A SHEDULE
THE GANTT CHART – AN EXCEL EXAMPLE
GANTT CHARTS
Gantt charts illustrate the start and finish dates of the terminal elements and
summary elements of a project.
Terminal elements and summary elements comprise the work breakdown
structure of the project.
Some Gantt charts also show the dependency (i.e., precedence network)
relationships between activities.
Pitfalls:
Attempt to define the project work breakdown structure at the same time that
they define schedule activities. the WBS should be fully defined to follow the
100% Rule, then the project schedule can be designed.
Difficult to grasp for projects with more than 30 activities
The equal horizontal dimension of activities does not take into consideration the
resource load of each activity
MAKING TRADEOFFS
With tasks, CP, and resource assignments in place, you are positioned to make
explicit planning tradeoffs
Analyze the impact on schedule of different feasible allocations of available
resources
Determine impact on schedule and budget of adding (or subtracting)
resources (keeping in mind Brooks’s Law)
Determine impact of changes in project scope
Important questions:
Are schedule and cost consistent with project objectives?
If not, can they be made so?
Or should we change the objectives?
Can we eliminate dependencies by working differently?
Are we trying to do too much?
PROJECT STRUCTURE – HOW MANY “CHUNKS”?
In considering scope, resource, and schedule tradeoffs, often the question of
how you might “chunk” the project comes up
Can also have budget implications – dividing a project up into smaller chunks can
make it appear more expensive
Although it can sometimes turn out cheaper if the smaller projects have
fewer problems than the big one would have…
Which brings us to…
PLANNING FOR PROJECT RISKS
As much as possible during planning stages of a project, draw attention to project
risks and develop plans for managing them.
Identify likely sources of risk
Develop plans to minimize probability that risks will materialize
Might result in new tasks being identified, which will require additional
resource requirements
Develop plans to minimize impact if risks do materialize
Important questions:
Have we identified all the risks we can?
Which should we worry most about (because the are very likely or would have
major impact on the project)?
PROJECT STRUCTURE AND RISK
There is a relationship between project structure and risk
In general, larger projects involve greater risks than a series of smaller projects
(smaller projects are less complex and constitute smaller failures even when
something does go wrong)
An additional advantage in “chunking” large projects into smaller ones: Can
incorporate learning from early chunks into later chunks
Certain projects have characteristics that make risks harder to anticipate and make
smaller chunks more beneficial
If project outcomes are difficult to specify in advance (thus must be
“discovered” to some extent – such as when a user of a product can’t easily
envision how the product might be used differently)
If project objectives are likely to change while the project is in progress (due to
changes in technology, moves by competitors, etc.)
ONGOING STATUS MONITORING
The challenge is to keep the PM and project team focused on areas that that
provide the best indication of project progress, and to maintain access to high
quality information about the progress of the project
Important questions:
How will status information be collected?
What will be monitored and how?
Are we confident in the quality of our measures of progress?
The problem of open communication: To do a good job of collecting status
information, you need people to be really honest about the problems they’re seeing
“SWEEPING THINGS UNDER THE RUG”
A very common sequence of events on projects
Team members discover problems that will delay the project
PM and senior managers are not happy to hear of the delay and convey the
impression (often unintentionally) that the person who discovered the
problem is to blame for the delay
People get the idea that identification of problems that result in project
delays is an unwelcome behavior
They start “sweeping things under the rug”
After problems accumulate “under the rug” for some time, something goes
terribly wrong with the project…
IN PROGRESS ADJUSTMENT AND ADAPTATION…
In every project, there is a need to adjust the ongoing project to account for
unexpected problems (or opportunities)
A continuation of the process of making planning tradeoffs
Change scope, eliminate dependencies, or add resources
Manage “scope creep” – enlarging project scope without really acknowledging
that the project is getting bigger, and without assigning additional resources or
otherwise accounting (e.g., moving deadline later) for the increase in work that
accompanies the increase in scope
Important questions:
Are mid-project requests for changes really requirements?
Should we make adjustments to the project?
Should we abandon the project?
LEARNING FROM PROJECT EXPERIENCES
Important to capture key learning that will improve management of future projects
Conduct “post mortem” meetings
Capture and communicate key learning to others on other projects and
throughout the larger organization
Often not done, so learning gets lost
Important questions:
What worked?
What didn’t?
Have we acknowledged and celebrated good work?
THE THREE MAIN “LEVERS” OF PM
Scope
Adjust what is included in the project
e.g., decide to drop Feature 7 from the project objectives
Resources
Adjust who is working on a project
e.g., decide to add two more people to the project
Schedule
Adjust target completion target
e.g., decide to allow another month to complete the project
You decide these things as you plan, then revisit during a project
COSTS AND SCHEDULE
PROJECT CONTROL COST BASELINE
Develop a project cost control baseline from the project cost
estimate
Important questions:
+ How many individual cost elements can the office and field
personnel be expected to break actual project costs into for
reporting purposes?
+ How many individual cost elements can the project
management team effectively review and monitor?
+ How can Pareto’s Law be taken into account—that 80
percent of the total project cost is probably represented by
only 20 percent of the cost items?
2. Incremental milestones:
When the work task involves a sequential series of subtasks, the percentage of completion may
be estimated by assigning a proportionate percentage to each of the subtasks.
For example, the installation of a major item of equipment might be broken down as follows:
Construct foundation pad 10 percent
Set equipment on foundation 60 percent
Connect mechanical piping 75 percent
Connect electrical 90 percent
Performance testing and start up 100 percent.
For example, if the actual cost to date for structural steel erection is $18,500 and the
estimated cost to complete the task is $6,500, the percentage of completion is 74%.