Productivity norms

S.N0 Activity
Qty Units
ELECTRICAL/ELV
1 Conduit 16 Rm/man/day
2 Wiring 30-40 Rm/man/day
3 Cable tray 5-6 Rm/man/day
4 Trunking 8-10 sq.m/man/day
5 DB Installation 1 Nos/man/day
6 DB Termination 1 Nos/man/day
7 Final Fix Accessories 8 Nos/man/day
8 Light points 8 Nos/man/day