Field Installation Rev. No.

MRL Elevator Doc. No. 695-311

FOD Page 1/3


Overseas Support Team
Preliminaries Date July. 2003

1. Building structure survey.


1.1 Check list
1) Floor finish level at each floor
2) Machine beam base sill and DEH beam sill.
Check if machine and DEH beam can be installed with referring site drawing. If this space is
not enough, it may require additional chipping.
3) Pit depth and waterproofing
As referring the site drawing, check if pit depth is enough or not.
4) Main power & Light power cable hole.
Pipe arrangement for main power (3 phases, neutral, earth) and light should be prepared at
top floor.
5) Window for air- ventilating
6) Hook.
7) Hoistway inclination
Consider the real square measure of hoistway that is effected by hoistway inclination
8) Hall entrance and button.
Check entrance height, width and hall button & lantern position
9) Overhead and traveling stroke
10) Piping arrangement and wiring from security room to pit
a. Emergency supervisory instrument( In case SVP is not applied, Option)
0.75mm2 × 10 wires
b. In case SVP panel is applied(Option)
0.75mm2 × 16 wires
c. Interphone
0.75mm2 × 7 wires for sigle lift
0.75mm2 × 9 wires for duplex lifts
d. In case CCTV is applied (Option)
0.75mm2 × 16 wires
Field Installation Rev. No. 0

MRL Elevator Doc. No. 695-311

FOD Page 2/3


Overseas Support Team
Preliminaries Date July. 2003

Air-Ventilating
Beam space: Hook window
430mm

Sill for M/C


Base

Sill for DEH


Beam

Over Head

Floor finish Line


Power Cable hole

Entrance Size

Hoistway
Pit Inclination
Depth Hoistway size

Waterproofing

Pic. 1-a Building check point


Field Installation Rev. No. 0

MRL Elevator Doc. No. 695-311

FOD Page 3/3


Overseas Support Team
Preliminaries Date July. 2003

2. General setting of MRL elevator

DEH Beam
Governor

Motor
E&I panel

CP

Car

CWT

Pic 1-b MRL elevator structure