50 ~100 mtr upstream of tank, velocity to be reduced to less than 1 m/s to limit risk
of static charge (where ever applicable)
Specific services velocity to be based on case by case.
Gas
Pressure <20 Barg Note-1 6000
Pressure 20 to 50 Barg Note-1 7500
Pressure 50 to 80 Barg Note-1 10000
Pressure > 80 Barg Note-1 15000
Note-1
it should be verified that following
velocity is not exceed
Pressure Max Vel
Barg m/s
0.1 or lower 60
Upto 1 40
Upto 5 30
>5 20
EROSIONAL SERVICES
Line Size Max Vel
m/s
Mixed phase condensate
(Vertical and horizontal lines should not be afected 10 to 20
by slug flow
rv 5000 to 10000 , max 15000
C Values C