You are on page 1of 10

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 25 (2007) 517–526
www.elsevier.com/locate/ijproman

Causes and effects of delays in Malaysian construction industry


Murali Sambasivan *, Yau Wen Soon
Graduate School of Management, Universiti Putra Malaysia, 43400 UPM, Serdang Selangor, Malaysia

Received 21 April 2006; received in revised form 27 June 2006; accepted 21 November 2006

Abstract

The problem of delays in the construction industry is a global phenomenon and the construction industry in Malaysia is no exception.
The main purpose of this study is to identify the delay factors and their impact (effect) on project completion. Earlier studies either con-
sidered the causes or the effects of project delays, separately. This study takes an integrated approach and attempts to analyze the impact
of specific causes on specific effects. A questionnaire survey was conducted to solicit the causes and effects of delay from clients, consul-
tants, and contractors. About 150 respondents participated in the survey. This study identified 10 most important causes of delay from a
list of 28 different causes and 6 different effects of delay. Ten most important causes were: (1) contractor’s improper planning, (2) con-
tractor’s poor site management, (3) inadequate contractor experience, (4) inadequate client’s finance and payments for completed work,
(5) problems with subcontractors, (6) shortage in material, (7) labor supply, (8) equipment availability and failure, (9) lack of commu-
nication between parties, and (10) mistakes during the construction stage. Six main effects of delay were: (1) time overrun, (2) cost over-
run, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment. This study has also established an empirical relationship
between each cause and effect.
Ó 2006 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Delay causes; Delay effects; Construction industry; Malaysia; Correlational analysis

1. Introduction tors contributing to delay and cost overruns in Ghana


groundwater construction projects. Chan and Kumarasw-
The problem of delays in the construction industry is a amy [8] studied delays in Hong Kong construction industry.
global phenomenon. In Saudi Arabia, Assaf and Al-Hejji They emphasized that timely delivery of projects within
[6] found that only 30% of construction projects were com- budget and to the level of quality standard specified by
pleted within the scheduled completion dates and that the the client is an index of successful project delivery. Failure
average time overrun was between 10% and 30%. In Nige- to achieve targeted time, budgeted cost and specified quality
ria, Ajanlekoko [2] observed that the performance of the result in various unexpected negative effects on the projects.
construction industry in terms of time was poor. Odeyinka Normally, when the projects are delayed, they are either
and Yusif [16] have shown that seven out of ten projects sur- extended or accelerated and therefore, incur additional cost.
veyed in Nigeria suffered delays in their execution. Ogunl- The normal practices usually allow a percentage of the pro-
ana and Promkuntong [17] conducted a study on ject cost as a contingency allowance in the contract price
construction delays in Thailand. Al-Momani [5] carried and this allowance is usually based on judgment [3].
out a quantitative analysis on construction delays in Jor- Although the contract parties agreed upon the extra time
dan. Frimpong et al. [10] conducted a survey to identify and cost associated with delay, in many cases there were
and evaluate the relative importance of the significant fac- problems between the owner and contractor as to whether
the contractor was entitled to claim the extra cost. Such sit-
*
Corresponding author. Tel.: +60 389467698; fax: +60 389434019. uations, usually involved questioning the facts, causal fac-
E-mail address: murali@econ.upm.edu.my (M. Sambasivan). tors and contract interpretation [4]. Therefore, delays in

0263-7863/$30.00 Ó 2006 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2006.11.007
518 M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526

construction projects give rise to dissatisfaction to all the 2. Previous studies


parties involved and the main role of the project manager
is to make sure that the projects are completed within the Many researchers have studied the causes and few
budgeted time and cost. The construction sector in Malay- researchers have studied the effects of project delays in
sia, a fast developing country in South-East Asia has not the construction industry. We have broken the studies into
escaped the problem of delays. In 2005, about 17.3% (of two parts: (1) Studies on causes of delay and (2) Studies on
417 government contract projects in Malaysia) were consid- effects of delay.
ered sick (more than 3 months of delay or abandoned).
The Construction Sector is one of the important sectors 2.1. Studies on causes of delay
that contribute to Malaysia’s economic growth. The sector
accounted for nearly 3.3% of GDP in the year 2005 and Mansfield [14] identified 16 major factors that caused
employed about 600,000 workers including 109,000 foreign delays and cost overruns in Nigeria. A questionnaire sur-
workers (MALBEX [12]). The huge volume and complexity vey was carried out with contractors, consultants and client
of projects in Malaysia’s construction sector pose a great organizations in Nigeria. They presented that the causes of
challenge and provide a wealth of opportunities to various delay and cost overruns in Nigerian construction projects
companies in the construction industry. The construction were attributed to finance and payment arrangements,
sector in Malaysia can be divided into four broad catego- poor contract management, shortages in materials, inaccu-
ries: office, retail, residential and infrastructure. This sector rate estimation, and overall price fluctuations.
suffered a temporary crisis between 1997 and 2000 (ASEAN Assaf et al. [7] identified 56 main causes of delay in
crisis) and now it has started to improve. However, the Saudi large building construction projects and their relative
delays in the projects continue to occur. The main purpose importance. Based on the contractors surveyed the most
of this study is to identify the delay factors and their impact important delay factors were: preparation and approval
(effect) on project completion. Earlier studies either consid- of shop drawings, delays in contractor’s progress, payment
ered the causes or the effects of project delays, separately. by owners and design changes. From the view of the archi-
This study takes an integrated approach and attempts to tects and engineers the cash problems during construction,
analyze the impact of specific causes on specific effects. the relationship between subcontractors and the slow deci-
Some causes and effects of delays in construction projects sion making process of the owner were the main causes of
can be country-specific. The logical question at this point delay. However, the owners agreed that the design errors,
is: Why is it necessary to link the causes and effects of delays labor shortages and inadequate labor skills were important
and how can the link help the practitioners to prevent or delay factors.
remedy future delays? In this research, we identified major Ogunlana and Promkuntong [17] conducted a study on
causes of delay and categorized them as client-related, con- construction delays in Thailand. They found that the prob-
tractor-related, consultant-related, material-related, labor- lems faced by the construction industry in developing econ-
related, contract-related, contract relationship-related, omies like Thailand could be: (a) shortages or inadequacies
and external factors. We have also identified major effects in industry infrastructure (mainly supply of resources); (b)
of delay as: time overrun, cost overrun, dispute, arbitration, caused by clients and consultants and (c) caused by con-
litigation, and total abandonment. Identification of causes tractor’s incompetence/inadequacies. They recommended
and effects alone does not help the project managers to take that there should be concerted effort by economy managers
appropriate remedial or preventive steps. The project man- and construction industry associations to provide the nec-
agers need to understand, for example, what causes or fac- essary infrastructure for efficient project management.
tors result in time overrun or cost overrun. Once these Chan and Kumaraswamy [8] conducted a survey to
factors become clear, the managers can take proactive steps determine and evaluate the relative importance of the sig-
to avoid such situations. For example, if it is known that nificant factors causing delays in Hong Kong construction
time overruns are predominantly caused by client-related projects. They analyzed and ranked main reasons for
factors, the project manager can: (1) make sure that pay- delays and classified them into two groups: (a) the role of
ments for the completed work are paid on time, (2) reduce the parties in the local construction industry (i.e. whether
owner interference, (3) speed up the decision-making pro- client, consultants or contractors) and (b) the type of pro-
cess, and (4) avoid unrealistic contract duration and jects. Results indicated that five major causes of delays
requirements. Therefore, the link between causes and effects were: poor site management and supervision, unforeseen
of delays need to be established. ground conditions, low speed of decision making involving
This paper is organized as follows. Section 2 deals with all project teams, client initiated variations and necessary
the previous studies on causes and effects of delays in pro- variations of works.
jects. Section 3 explains the methodology of research. Sec- Odeyinka and Yusif [16] have addressed the causes of
tion 4 discusses the analysis the data using statistical delays in building projects in Nigeria. They classified the
procedures. Section 5 discusses the results. Section 6 pre- causes of delay as project participants and extraneous
sents the strategies for reducing delays in construction pro- factors. Client-related delays included variation in orders,
jects and Section 7 presents the conclusions. slow decision-making and cash flow problems. Contrac-
M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526 519

tor-related delays identified were: financial difficulties, Manavazhia and Adhikarib [13] conducted a survey to
material management problems, planning and scheduling investigate material and equipment procurement delays in
problems, inadequate site inspection, equipment manage- highway projects in Nepal. Delay in the delivery of materi-
ment problems and shortage of manpower. Extraneous als and equipment to construction sites is often a contribu-
causes of delay identified were: inclement weather, acts of tory cause to cost overruns in construction projects in
nature, labor disputes and strikes. developing countries. An assessment of the causes of the
Al-Momani [5] carried out a quantitative analysis on delays and the magnitude of their impact on project costs
construction delays in Jordan. The result of his study indi- were also made. The survey method was used in conducting
cated that the main causes of delay in construction of pub- this research involving 22 highway projects. The main
lic projects were related to designers, user changes, causes of material and equipment procurement delays were
weather, site conditions, late deliveries, economic condi- found to be (in rank order) organizational weaknesses, sup-
tions and increase in quantity. Similarly, Odeh and Battai- pliers’ defaults, governmental regulations and transporta-
neh [15] also conducted a survey aimed at identifying the tion delays. However, the actual impact of these delays
most important causes of delays in construction projects on project costs was found to be on average, only about
with traditional type of contracts from the viewpoint of 0.5% of the total budgeted cost of the projects. Among
construction contractors and consultants. Results of the materials, delays in the supply of aggregates and equipment
survey indicated that contractors and consultants agreed were found to occur most frequently.
that owner interference, inadequate contractor experience, Chan and Kumaraswamy [9] explored strategies of com-
financing and payments, labor productivity, slow decision pressing construction durations of various types of build-
making, improper planning, and subcontractors were ing projects on the basis of the lessons learned from
among the top ten most important factors. Hong Kong based surveys and other research findings.
Frimpong et. al., [10] conducted a survey to identify and The literature from different countries on the factors affect-
evaluate the relative importance of significant factors con- ing construction durations, reasons for project delays and
tributing to delay and cost overruns in Ghana groundwater existing statistical models for duration forecasts were
construction projects. A questionnaire with 26 factors was reviewed. A regression-based model developed from Hong
carefully designed from preliminary investigations con- Kong public housing construction project data was used
ducted in groundwater drilling projects between 1970 and for predicting the durations of the primary work packages
1999 in Ghana. The questionnaire was directed towards in the building process and the overall completion period.
three groups in both public and private organizations: And finally, a survey was conducted by the researchers to
owners of the groundwater projects, consulting offices, explore the construction time performance of projects in
and contractors working in the groundwater works. The three building sub-sectors (i.e. public housing, public
questionnaire was distributed to a random sample of 55 non-residential and private sector). Based on the factors
owners, 40 contractors and 30 consultants. The result of identified as significant from the above research, specific
the study revealed the main causes of delay and cost over- technological and managerial strategies for reducing con-
runs in construction of groundwater projects: monthly struction periods in particular building sub-sectors were
payment difficulties from agencies; poor contractor man- formulated in order to improve the construction time per-
agement; material procurement; poor technical perfor- formance of Hong Kong building projects.
mance; and escalation of material prices. Terry Williams [19] studied the standard methods cur-
Assaf and Al-Hejji [6] conducted a survey on time per- rently available for assessing extension of time delays on
formance of large construction projects in Saudi Arabia. major projects, and issues around such assessment. He used
The survey had 73 different causes of delay. He studied network causal mapping and system dynamics approach to
the importance of various causes from the viewpoint of study the impact of delays on a project.
contractors, consultants, and owners. The most common Based on the above studies, it can be inferred that the
cause of delay identified by all the parties was ‘‘change earlier studies concentrated on either the causes or the
order’’. He also found that about 70% of the projects expe- effects. However, some studies have alluded to the probable
rienced time overruns. link between the causes and effects of delays without a sys-
tematic analysis. Manavizha and Adhikarib [13] linked the
2.2. Studies on effects of delay material-related causes to the probable cost overruns in
construction projects in Nepal. Assaf and Al-Hejji [6] linked
Aibinu and Jagboro [1] studied and evaluated the effects the contractor-related and labor-related causes to the prob-
of construction delays on project delivery in Nigerian con- able time overruns in construction projects in Saudi Arabia.
struction industry. They found that the six effects of con- Odeh and Battaineh [15] linked the contract-linked causes
struction delay were: time overrun, cost overrun, dispute, to the probable disputes occurring in construction projects
arbitration and litigation and total abandonment. The in Jordan. Chan and Kumaraswamy [8] linked the consul-
questionnaires were sent to three groups of construction tant-related and client-related causes to the probable time
practitioners: quantity surveyors, architects and engineers, overruns in construction projects in Hong Kong. Mansfield
and contractors. et al. [14] and Frimpong et al. [10] linked the client-related,
520 M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526

consultant-related, and material-related factors to the prob- ranging from 1 (not important) to 5 (extremely important)
able cost and time overruns. In this research, we take an was adopted to capture the importance of causes and
integrated approach and attempt to link the causes and effects of delays.
the effects of delays in Malaysian construction industry Before distributing the questionnaire, a small pilot study
through a systematic analysis. was conducted using 10 consultants, 10 clients, and 10 con-
tractors. The basic purpose of the pilot study was to verify
3. Methodology the completeness of the questionnaire in capturing the fac-
tors relevant for Malaysia. All the respondents agreed that
A questionnaire was developed to assess the perceptions the questionnaire was sufficient to capture the causes and
of clients, consultants, and contractors on the relative effects of delays. Therefore, we did not make any modifica-
importance of causes and effects of delay in Malaysian con- tion to the causes of delay identified by Odeh and Battai-
struction industry. The questionnaire was divided into neh [15] and effects of delay identified by Aibinu and
three parts. The first part requested background informa- Jagboro [1].
tion about the respondents. The sampling method used in this study was conve-
The second part of the questionnaire focused on causes nience and snowball sampling. This sampling comes under
of construction delay. The respondents were asked to indi- the class of non-probability sampling techniques. As the
cate their response category on 28 well-recognized con- name implies, sample elements are identified by conve-
struction delay factors identified by Odeh and Battaineh nience (friends) and through referral networks. This
[15]. These causes were categorized into the following eight method of sampling is preferred when it is difficult to get
major groups: response from sample elements selected at random [18].
We distributed the questionnaires through our friends
1. Client related factors: finance and payments of com- working in Public Works Department of Malaysia, devel-
pleted work, owner interference, slow decision making opers, consultants and construction firms. Our friends in
and unrealistic contract duration imposed by owners. turn distributed to their friends. This sampling method
2. Contractor related factors: delays caused by subcontrac- enabled us to obtain a large number of completed question-
tor, site management, improper construction methods, naires quickly and economically. Two hundred sets of
improper planning and errors during construction, and questionnaires were distributed to the potential respon-
inadequate contractor experience. dents at all levels in the organizations within the construc-
3. Consultant related factors: contract management, prep- tion industry. One hundred sets were distributed to clients
aration and approval of drawings, quality assurance and (50 sets to Public Works Department of Malaysia and 50
waiting time for approval of test and inspection. sets to private developers), 50 sets to consultants and 50
4. Material related factors: quality of material and short- sets to the contractors. Of the 200 questionnaires, 150 sets
age in material. (75%) were returned and there were 67 sets (67%) from cli-
5. Labor and equipment related factors: labor supply, ents, 48 sets (96%) from consultants and 35 sets (70%) from
labor productivity and equipment availability and contractors.
failure.
6. Contract related factors: change orders and mistakes or 3.1. Calculation of relative importance of factors
discrepancies in contract document.
7. Contract relationship related factors: major disputes Kometa et al. [11] used the relative importance index
and negotiations, inappropriate overall organizational method to determine the relative importance of the various
structure linking to the project and lack of communica- causes and effects of delays. The same method was adopted
tion between the parties. in this study within various groups (i.e. clients, consultants
8. External factors: weather condition, regulatory changes, or contractors). The five-point scale ranged from 1 (not
problem with neighbors and unforeseen site condition. important) to 5 (extremely important) was adopted and
transformed to relative importance indices (RII) for each
The respondents were asked to highlight their recom- factor as follows:
mendations to improve the performance of Malaysian con- P
W
struction industry through an open-ended question at the RII ¼ ð1Þ
end of second part of the questionnaire. AN
Third part of the questionnaire focused on the effects of where W is the weighting given to each factor by the
construction delay in Malaysian construction industry. The respondents (ranging from 1 to 5), A is the highest weight
six effects of construction delay identified were: time over- (i.e. 5 in this case), and N is the total number of respon-
run, cost overrun, dispute, arbitration, litigation, and total dents. The RII value had a range from 0 to 1 (0 not inclu-
abandonment [1]. Similar to the second part of the ques- sive), higher the value of RII, more important was the
tionnaire, the respondents were asked to highlight their rec- cause or effect of delays.
ommendation to minimize the effects of construction delays The RII was used to rank (R) the different causes. These
through an open-ended question. A five-point Likert scale rankings made it possible to cross-compare the relative
M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526 521

importance of the factors as perceived by the three groups Table 1


of respondents (i.e. clients, consultants and contractors). Demographic characteristics of respondents
Each individual cause’s RII perceived by all respondents Demographic characteristic Frequency Percent
were used to assess the general and overall rankings in Age
order to give an overall picture of the causes of construc- Less than 20 2 1.3
tion delays in Malaysian construction industry. The same 20–29 71 47.3
30–39 43 28.7
procedure was adopted for ranking the effects. The indices 40–49 24 16.0
(RII) were then used to determine the rank of each item 50 and above 10 6.7
(effect). These rankings made it possible to cross compare
Sex
the relative importance of the items as perceived by the Male 96 64.0
three groups of respondents. The weighted average for each Female 54 36.0
item for the three groups of respondents was determined
Education
and ranks (R) were assigned to each item representing the Lower secondary (Form 1– 3) 1 0.7
perception of the three groups. Upper secondary (Form 4–5) 12 8.0
Pre-university (Form 6) 19 12.7
4. Analysis of data University 90 60.0
Post graduate 28 18.7

The demographic characteristics of the respondents are Type of organization


given in Table 1. Clients (government or developer) 67 44.7
Consultants 48 32.0
Contractors 35 23.3
4.1. Causes of delay
Occupational level
Non-executive 23 15.3
The primary data collected from the second part of the Executive 99 66.0
questionnaire was analyzed from the perspective of clients, Managerial 28 18.7
consultants and contractors. Each individual cause’s RII Number of years working experience
perceived by all respondents was computed for overall Less than 2 years 20 13.3
analysis. 2–5 years 43 28.7
The relative importance index, RII, was computed for 6–10 years 42 28.0
each cause to identify the most significant causes. The More than 10 years 45 30.0
causes were ranked based on RII values. From the ranking Fields of specializations
assigned to each cause of delays, we were able to identify Building 60 40.0
Infrastructure 41 27.3
the most important factors or causes of delays in Malay-
Mechanical and electrical 19 12.7
sian construction industry. Others 30 20.0
Based on the ranking, the five most important causes of
Largest project involved based on contract sum
construction delays as perceived by clients were: (1) con- Less than RM 10 millions 27 18.0
tractor’s improper planning (RII = 0.821); (2) contractor’s RM 10 millions–RM 50 millions 47 31.3
site management (RII = 0.779); (3) inadequate contractor More than RM 50 millions 76 50.7
experience (RII = 0.770); (4) labor supply problems (RII
= 0.770) and (5) subcontractor problems (RII = 0.758).
The five most important causes of construction delays as
perceived by consultants were: (1) contractor’s improper clients and contractors are: contractor’s site management,
planning (RII = 0.842); (2) contractor’s site management inadequate contractor experience, and subcontractors.
(RII = 0.821); (3) shortage in material (RII = 0.804); (4) The clients blame contractor’s improper planning and
inadequate contractor experience (RII = 0.770), and (5) labor supply as other important causes of delay. The con-
inadequate client’s finance and payments of completed tractors’ inability to plan can be attributed to contractor’s
work (RII = 0.792). The five most important causes of con- inexperience. A significant portion of the labor force in the
struction delays as perceived by contractor were: (1) con- construction industry is from neighboring countries like
tractor’s poor site management (RII = 0.869); (2) Indonesia. It is quite difficult to prevent the movement of
inadequate client’s finance and payments of completed these laborers from one construction company to another
work (RII = 0.823); (3) subcontractors (RII = 0.789); (4) causing disruption of work. The contractors blame client’s
inadequate contractor experience (RII = 0.783), and (5) inability to pay for the completed work and equipment
equipment availability and failures (RII = 0.777). From availability and failures as other important causes of delay.
the above list, it is interesting to compare the causes as per- These causes can be attributed to the client’s financial posi-
ceived by clients and contractors. Most of the disputes that tion and contractor’s improper planning. In government
arise in the construction industry in Malaysia are between related projects, payments to the contractors take relatively
clients and contractors, most often, one party blaming the longer time. It is the responsibility of the contractors to fac-
other. Three of the causes perceived common between tor in this time during the planning process. Table 2 gives
522 M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526

Table 2
Ranking of causes (based on overall)
Causes of delays Percentage of respondents scoring RII Rank
1 2 3 4 5
Client related causes
Finance and payments of completed work 3.3 4.0 23.3 38.0 31.3 0.780 4
Owner Interference 3.3 8.7 40.0 37.3 10.7 0.687 20
Slow decision making 2.0 7.3 31.3 41.3 18.0 0.732 13
Unrealistic contract duration and requirements imposed 5.3 10.7 42.0 32.0 10.0 0.661 24
Contractor related causes
Subcontractors 0.0 7.3 25.3 42.0 25.3 0.771 5
Site management 0.7 2.0 20.0 44.7 32.7 0.813 2
Construction methods 2.0 9.3 32.0 44.0 12.7 0.712 15
Improper planning 1.3 4.0 15.3 44.7 34.7 0.815 1
Mistakes during construction stage 0.0 8.0 31.3 36.7 24.0 0.753 10
Inadequate contractor experience 0.0 7.3 25.3 36.0 31.3 0.783 3
Consultant related causes
Contract management 0.7 17.3 34.7 31.3 16.0 0.689 19
Preparation and approval of drawings 0.0 6.7 48.0 31.3 14.0 0.705 16
Quality assurance/control 0.0 14.7 44.7 31.3 9.3 0.671 22
Waiting time for approval of tests and inspection 1.3 14.0 44.0 30.0 10.7 0.669 23
Material related causes
Quality of material 0.0 9.3 29.3 46.7 14.7 0.733 12
Shortage in material 0.0 7.3 28.0 36.7 28.0 0.771 6
Labor and equipment category causes
Labor supply 2.7 7.3 18.0 52.7 19.3 0.757 7
Labor productivity 1.3 10.7 24.7 40.7 22.7 0.745 11
Equipment availability and failure 0.7 9.3 27.3 37.3 25.3 0.755 8
Contract related causes
Change orders 0.7 14.0 38.7 38.0 8.7 0.680 21
Mistakes and discrepancies in contract document 0.0 16.0 29.3 41.3 13.3 0.704 17
Contract relationships related causes
Major disputes and negotiations 0.7 10.0 36.7 36.7 16.0 0.715 14
Inappropriate overall organizational structure linking to the project 0.0 14.7 48.0 29.3 8.0 0.661 25
Lack of communication between the parties 0.0 7.3 28.7 43.3 20.7 0.755 9
External causes
Weather condition 2.7 20.0 34.0 38.0 5.3 0.647 27
Regulatory changes 3.3 20.0 34.0 30.0 12.7 0.657 26
Problem with neighbors 4.0 20.7 44.7 26.7 4.0 0.612 28
Unforeseen site condition 1.3 13.3 33.3 42.7 9.3 0.720 18

the ranking of causes based on response of all respondents Based on the ranking, the important effects of construc-
(clients, contractors and consultants). Table 3 summarizes tion delays as perceived by clients were: time overrun
RII and ranking of the categories of causes of delay as per- (RII = 0.821), cost overrun (RII = 0.782), dispute
ceived by all respondents. (RII = 0.687), arbitration (RII = 0.621), litigation
In order to test the degree of agreement between the (RII = 0.591), and total abandonment (RII = 0.585). The
three groups of respondents as to the causes of delays, a important effects of construction delays as perceived by
correlation analysis using Spearmen’s rank correlation contractors and consultants were exactly the same as those
coefficient was done [6]. Table 4 gives the results of the of clients and therefore, a separate analysis using Spear-
analysis. High correlation indicates that there is a high men’s Rank correlation was not done to test the agreement
degree of agreement between the respondents. between the three groups of respondents. Table 5 gives the
ranking of effects based on response of all respondents (cli-
4.2. Effects of delay ents, contractors and consultants).
The next step in the analysis was to identify the empiri-
The primary data collected from the third part of the cal relationships between the causes and the effects. Empir-
questionnaire was analyzed from the perspective of cli- ical relationships are based on observations and
ents, consultants and contractors. The calculation of RII propositions that are based on sense experience and are
and ranking were done as explained in the previous derived from methods of inductive logic, including mathe-
section. matics and statistics [18]. In short, empirical relationships
M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526 523

Table 3
RII and ranking of categories of causes of delay
Category Clients Consultants Contractors Overall
RII Rank RII Rank RII Rank RII Rank
Client-related 0.674 6 0.742 4 0.757 3 0.715 4
Contractor-related 0.758 1 0.791 2 0.783 1 0.774 1
Consultant-related 0.664 7 0.697 7 0.703 6 0.684 7
Material-related 0.721 3 0.792 1 0.757 2 0.752 2
Labor and equipment-related 0.741 2 0.768 3 0.752 4 0.752 3
Contract-related 0.679 5 0.708 6 0.694 7 0.692 6
Contract relationships-related 0.694 4 0.735 5 0.709 5 0.710 5
External-related 0.637 8 0.655 8 0.674 8 0.652 8

Table 4
Spearman’s rank correlation coefficients of the ranking of clients, consultants and contractors for causes of delay (28 causes)
Ranking Client Consultant Contractor
Client q 1.000 0.867a 0.772a
Significance probability – 0.000 0.000
N (number of causes) 28 28 28
Consultant q 0.867a 1.000 0.896a
Significance probability 0.000 – 0.000
N (number of causes) 28 28 28
Contractor q 0.772a 0.896a 1.000
Significance probability 0.000 0.000 –
N (number of causes) 28 28 28
a
Correlation is significant at the 0.01 level of significance – if significance probability is lesser than the level of significance, correlation is significant.

Table 5
Ranking of effects (based on overall)
Effects of delays Percentage of respondents scoring RII Rank
1 2 3 4 5
Time overrun 0.0 0.7 20.7 56.0 22.7 0.801 1
Cost overrun 0.7 2.7 29.3 37.3 30.0 0.787 2
Dispute 0.7 14.7 41.3 38.0 5.3 0.665 3
Arbitration 2.0 22.0 46.0 24.7 5.3 0.619 4
Litigation 4.7 21.3 48.7 22.7 2.7 0.595 5
Total abandonment 6.7 36.0 29.3 21.3 6.7 0.571 6

Table 6
Correlation between the categories of causes and effects of delays
Effects Causes of delay
Client Contractor Consultant Material Labor Contract related Contract relationship External
Time overrun 0.164 0.277 0.045 0.092 0.046 0.019 0.134 0.007
Cost overrun 0.145 0.148 0.097 0.024 0.037 0.165 0.087 0.004
Dispute 0.171 0.001 0.042 0.067 0.155 0.222 0.251 0.165
Arbitration 0.172 0.051 0.050 0.033 0.096 0.146 0.203 0.104
Litigation 0.170 0.019 0.103 0.152 0.204 0.273 0.288 0.214
Total abandonment 0.165 0.129 0.216 0.093 0.294 0.287 0.159 0.301
Highlighted coefficients are significant at 0.05 significance level.

attempt to describe, explain, and make predictions through Correlation analysis is a powerful method to study the rela-
observation. In this research, we attempt to establish rela- tionship between variables that have interval data [18].
tionship between causes and effects through observable Therefore, a correlation analysis was done to study the
data. Since the data we have collected through survey is empirical relationships between the categories of causes
based on Likert-scale, it can be considered as interval data. and effects. Table 6 gives the results of the analysis.
524 M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526

5. Discussion of results are delayed. Work progress can be delayed due to the late
payments from the clients because there is inadequate cash
This section discusses the results obtained in the earlier flow to support construction expenses especially for those
section. First, we discuss the results obtained by analyzing contractors who are not financially sound.
the causes of delays. Second, we discuss the results
obtained by analyzing the effects of the delays. Third, we 5.5. Problems with subcontractors
link each of the effect with the causes of delay.
The ten most important causes of delays (based on all Typically in huge projects, there are many subcontrac-
respondents) as shown in the Table 2 were: (1) contractor’s tors working under main contractors. If the subcontractor
improper planning (RII = 0.815), (2) contractor’s poor site is capable, the project can be completed on time as
management (RII = 0.813), (3) inadequate contractor planned. The project can be delayed if the subcontractor
experience (RII = 0.783), (4) inadequate client’s finance under performs because of inadequate experience or capa-
and payments for completed work (RII = 0.792), (5) prob- bility. High degree of subcontracting in Malaysia leads to
lems with subcontractors (RII = 0.771), (6) shortage in high risk of delays and this leads to inefficiencies in the
material (RII = 0.771), (7) labor supply (RII = 0.757), (8) Malaysian construction industry.
equipment availability and failure (RII = 0.755), (9) lack
of communication between parties (RII = 0.755), and 5.6. Shortage in material
(10) mistakes during the construction stage (RII = 0.753).
Shortages in basic materials like sand, cement, stones,
5.1. Contractor’s improper planning bricks, and iron can cause major delays in projects. Since
Malaysia is a country that is developing very fast, often
Local contractors often fail to come out with a practical times demand exceeds the supply and this causes prices
and workable ‘‘work program’’ at the initial planning to increase. The contractors postpone the purchase activi-
stage. This failure is interrelated with lack of systematic site ties until the prices decrease. Manavazhia and Adhikarib
management and inadequate contractor’s experience [13] investigated material and equipment procurement
towards the projects. The consultant only checks and delays in highway projects in Nepal and found these delays
reviews the work program submitted by the contractors to cause cost overrun.
based on experience and intuitive judgment. Improper
planning at the initial stages of a project manifests through- 5.7. Labor supply
out the project and causes delays at various stages. Only a
project that is well planned can be well executed. The quality and quantity of labor supply can have major
impact on the projects. About 20% of the workers in the
5.2. Contractor’s poor site management Malaysian construction industry are foreign workers,
mainly from Indonesia and Vietnam (MALBEX [12]). A
Contractor’s poor site management is one of the most few of them are illegal workers and their work quality is
significant causes in causing the construction delays. The relatively low when compared to local laborers. The low
results of this research indicate that local contractors face quality and productivity of the foreign workers have
deficiency in site planning, implementation and controls. impact on the project progress and efficiency. The illegal
A poor site management results in delays in responding workers are frequently caught by the Malaysian immigrant
to the issues that arise at the site and causes negative officials and deported and this causes shortage of labor
impact on the overall work progress. pool in the construction industry.

5.3. Inadequate contractor experience 5.8. Equipment availability and failure

Odeh and Battaineh [15] indicated that inadequate con- Many of the contractors do not own equipments that
tractor experience was an important factor and this could are required for the construction work. They rent the
be linked to the contract awarding procedure where most equipments when required. During the season when there
projects were awarded to the lowest bidder. A contractor are many construction projects, the equipments are in short
with inadequate experience cannot plan and manage the supply and are poorly maintained. This leads to failure of
projects properly and this can lead to disastrous the equipments causing the progress to be hampered.
consequences.
5.9. Lack of communication between parties
5.4. Client’s finance and payments for completed work
Since there are many parties involved in a project (client,
Construction works involve huge amounts of money consultant, contractor, sub-contractors), the communica-
and most of the contractors find it very difficult to bear tion between the parties is very crucial for the success of
the heavy daily construction expenses when the payments the project. Proper communication channels between the
M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526 525

various parties must be established during the planning that arise during the course of the project. Factors such
stage. Any problem with communication can lead to severe as delay in the payments for completed work, frequent
misunderstanding and therefore, delays in the execution of owner interference, changing requirements, lack of com-
the project. munication between the various parties, problems with
neighbors, and unforeseen site conditions give rise to dis-
5.10. Mistakes during the construction stage putes between the various parties. The disputes, if not
resolved amicably, can lead to arbitration or litigation.
The mistakes during the construction stage can be due
to accidents, inadequate planning, or miscommunication 5.14. Arbitration
between the parties. Whatever the reason, the mistakes
can have impact on the progress of the project. Client-related and contract relationship-related factors
While analyzing the effects of delays, all respondents escalate disputes to be settled by arbitration process. A
were unanimous in ranking the effects. The time and cost competent third-party can settle the disputes amicably
overruns were ranked highly by the respondents. Any delay without going to the court.
in a project can lead to cost and time overruns and these
two are linked. Whenever there are delays, there are dis- 5.15. Litigation
putes as to who should bear the responsibility and the cost.
These disputes often lead to an arbitration process by third Client-related, labor-related, contract-related, contract
parties and failure in this process leads to litigation where relationship-related, and external factors escalate disputes
the disputes are settled by the court. In extreme cases, some to be settled by the litigation process. The parties involved
projects might be totally abandoned. About 17% of the in the projects use litigation as a last resort to settle
projects in Malaysia are abandoned (MALBEX [12]). disputes.
In the following paragraphs, we analyze the impact of
causes on each effect of delay. Correlation analysis results 5.16. Total abandonment
given in Table 6 establish the link between them. From
the table, we can identify the causes for each of the effects Client-related, consultant-related, labor-related, con-
of delay. tract-related, and external factors contribute to the total
abandonment of the projects. In Malaysia, many projects
5.11. Time overrun were temporarily abandoned during the financial crisis
between 1997 and 2000. Promoters of various projects
Client-related and contractor-related factors have backed out because of poor cash flow and economic condi-
impact on the time overrun. Out of the ten most important tions. Many of these projects have now become so prohib-
causes of delay discussed earlier, six causes belong to client- itive that they have been abandoned permanently
related and contractor-related factors. Factors such as (MALBEX [12]).
inadequate planning by the contractors, improper site Based on the discussions above, the next step is to pro-
management by the contractors, inadequate project han- vide suggestions to clients, contractors, and consultants to
dling experience of contractors, and delay in the payments reduce delays. These suggestions, we hope, will alleviate the
for the work completed directly affect the completion of the problems faced by the construction industry in Malaysia.
project and cause time overrun.
6. Prescriptions to reduce delays
5.12. Cost overrun
We divide the prescriptions to adopted into three
Contract-related factors such as change orders (changes groups: (1) prescriptions for the clients, (2) prescriptions
in the deliverables and requirements) and mistakes and dis- for the consultants, and (3) prescriptions for the
crepancies in the contract document result in cost overrun. contractors.
Mistakes and discrepancies in the contract document can
be in scope, deliverables, resources available and allocated, 6.1. Prescriptions for the clients
payment terms, achievement of various milestones, and the
project duration. In most of the instances, time overrun (1) While selecting the contractors, clients have to make
leads to cost overrun. Correlation analysis between cost sure that the contractors are not selected based only on the
and time overruns indicated a strong linkage (correlation lowest bid. The selected contractor must have sufficient
coefficient = 0.487, significant at 0.01 level of significance) experience, technical capability, financial capability, and
sufficient manpower to execute the project, (2) clients
5.13. Disputes should not interfere frequently during the execution and
keep making major changes to the requirements. This can
Client-related, contract-related, contract relationship- cause inordinate delays in the project, (3) clients should
related, and external factors have impact on the disputes have the finances in time to pay the contractors after com-
526 M. Sambasivan, Y.W. Soon / International Journal of Project Management 25 (2007) 517–526

pletion of a work. Therefore, clients should work closely reduce the incidences of delays. The academicians can con-
with the financing bodies and institutions to release the duct similar studies in other parts of world and identify
payment on schedule, and (4) clients must make quick deci- causes and effects of delays. As mentioned earlier, some
sions to solve any problem that arise during the execution. causes and effects may be unique to certain countries.

6.2. Prescriptions for the consultants References

(1) While drawing the contract between the client and [1] Aibinu AA, Jagboro GO. The effects of construction delays on
contractor, the consultant must include items such as dura- project delivery in Nigerian construction industry. Int J Project
tion of contract, mechanism to solve disputes, mechanism Manage 2002;20:593–9.
[2] Ajanlekoko JO. Controlling cost in the construction industry. Lagos
to assess the causes of delay, if there are any and risk man- QS Digest, Lagos 1987;1(1):8–12.
agement plans, (2) consultants should prepare and approve [3] Akinsola AO. Neural network model for predicting building projects’
drawings on time, and (3) consultants should monitor the contingency. In: Conference: proceedings of association of research-
work closely by making inspections at appropriate times. ers in construction management, ARCOM 96, Sheffield Hallam
University, England, 11–13 September 1996. p. 507–16.
[4] Alkass S, Mazerolle M, Harris F. Construction delay analysis
6.3. Prescriptions for the contractors techniques. Construction Manage Econ 1996;14(5):375–94.
[5] Al-Momani A. Construction delay: a quantitative analysis. Int J
(1) Contractors should not take up the job in which they Project Manage 2000;20:51–9.
do not have sufficient expertise, (2) contractors should have [6] Assaf SA, Al-Hejji S. Causes of delay in large construction projects.
Int J Project Manage 2006;24(4):349–57.
able site-managers for the smooth execution of work, (3)
[7] Assaf SA, Alkhalil M, Al-Hazmi M. Causes of delay in large building
contractors must plan their work properly and provide construction projects. J Manage Eng, ASCE 1995;11(2):45–50.
the entire schedule to the clients, and (4) contractors must [8] Chan DWM, Kumaraswamy MM. A comparative study of causes of
make sure they have a sound financial backing. time overruns in Hong Kong construction projects. Int J Project
Manage 1997;15(1):55–63.
7. Conclusions [9] Chan DWM, Kumaraswamy MM. Compressing construction dura-
tions: lessons learned from Hong Kong building projects. Int J Project
Manage 2002;20:23–35.
We investigated the causes and effects of delays facing in [10] Frimpong Y, Oluwoye J, Crawford L. Causes of delay and cost
the Malaysian construction industry. A questionnaire was overruns in construction of groundwater projects in a developing
designed and distributed among the three major groups countries; Ghana as a case study. Int J Project Manage
2003;21:321–6.
of participants (clients, consultants and contractors). We
[11] Kometa ST, Olomolaiye PO, Harris FC. Attributes of UK construc-
identified main causes of delay and ten most important tion clients influencing project consultants’ performance. Construc-
causes were: (1) contractor’s improper planning, (2) con- tion Manage Econ 1994;12:433–43.
tractor’s poor site management, (3) inadequate contractor [12] MALBEX, 2005. Market watch – construction industry, Kuala
experience, (4) inadequate client’s finance and payments Lumpur Exhibition Center Report. p. 1–8.
for completed work, (5) problems with subcontractors, [13] Manavazhia MR, Adhikarib DK. Material and equipment procure-
ment delays in highway projects in Nepal. Int J Project Manage
(6) shortage in material, (7) labor supply, (8) equipment 2002;20:627–32.
availability and failure, (9) lack of communication between [14] Mansfield NR. Causes of delay and cost overruns in Nigerian
parties, and (10) mistakes during the construction stage. construction projects. Int J Project Manage 1994;12(4):254–60.
We identified main effects of delay and they were: (1) time [15] Odeh AM, Battaineh HT. Causes of construction delay: traditional
overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5) contracts. Int J Project Manage 2002;20:67–73.
[16] Odeyinka HA, Yusif A. The causes and effects of construction delays
litigation, and (6) total abandonment. As an important on completion cost of housing project in Nigeria. J Financial Manage
contribution, we also studied the empirical relationships Property Construction 1997;2(3):31–44.
between the causes and effects of delays. We isolated the [17] Ogunlana SO, Promkuntong K. Construction delays in a fast growing
causes of delay for each of the six effects. We believe that economy: comparing Thailand with other economies. Int J Project
Manage 1996;14(1):37–45.
the results of this study can be of immense help to the prac-
[18] Sekaran Uma. Research methods for business: a skill building
titioners (clients, contractors and consultants) and acade- approach. 3rd ed. New York: John Wiley; 2000.
micians. The practitioners can better understand the [19] Terry Williams. Assessing extension of time delays on major projects.
dynamics of project management and make efforts to Int J Project Manage 2003;21:19–26.

You might also like