Professional Documents
Culture Documents
Sample UDS Document PDF
Sample UDS Document PDF
Certified by:_________________________________________________
Title and areas of
responsibility:__________________________________
Date: _______________
REVISION DETAILS
TABLE OF CONTENTS
1. INTRODUCTION 4
2. INSTALLATION SITE 5
2.1 Location
2.2 Jurisdictional Authority
2.3 Environmental Conditions
3. VESSEL IDENTIFICATION 5
3.1 Vessel identification
3.2 Service Fluid
4. VESSEL CONFIGURATION 5
4.1 Outline Drawings
4.2 Vessel Orientation
4.3 Vessel openings & Identification
4.4 Principal Component Dimensions
4.4 Support Methods
5. DESIGN CONDITIONS 6
5.1 Specified Design Pressure
5.2 Design Temperature
5.3 Minimum Design Metal Temperature
5.4 Dead, Live & Other Loads
6. OPERATING CONDITIONS 7
8. MATERIALS OF CONSTRUCTION 9
1 INTRODUCTION
This specification, together with the related drawings, codes and standards constitutes a complete
“User’s Design Specification” as required by ASME VIII Div 2 Ed. 2007, Add 2008 Code.
1.1 PURPOSE
This specification covers all the requirements outlined in ASME VIII, Div 2 Code, Part 2.2.2 for the
design and construction of Air Buffer Vessel (Item No AB-001).
Any proposed deviation from this specification by the Supplier is to be made by written request for
approval by the User and for a revision of this specification including recertification when this
document is revised.
1.2 DEFINITIONS
The following terms and definitions shall be used:
ENGINEERING CONTRACTOR: party which carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation / maintenance of a
company facility.
SUPPLIER: organization supplying equipment, materials or services as per the terms of this document
and company purchase order
The USER, as referred to in the ASME code, is ABC CONSULTANTS, the firm or organization
who will own and/or operate the vessel.
The INSPECTOR is the person who carries out all the inspections as specified in ASME Sec VIII Div. 2.
The word CODE indicates the ASME VIII Div.2, Ed. 2007/Add 2008 & other reference Codes
2. INSTALLATION SITE
2.1 LOCATION
Company’s facility at ______________ located at _____________ in ___________ country
3. VESSEL IDENTIFICATION
5. DESIGN CONDITIONS
5.4.1 Nozzle Load: Except for the manhole and nozzles of size DN 50(2”) NPS or less (vent & drain), all
nozzles shall be designed for the additional loads as per Attachment 1 of this document:
Weight Fabricated Kg
Weight Operating Kg
Weight Hydrostatic (Shop) Kg
5.4.3 All loads and load case combinations are detailed in 9.0 below
6. OPERATING CONDITIONS
8. MATERIALS OF CONSTRUCTION
Design
Applicability /
Load Description
Remarks
Parameter
P Internal Maximum Allowable Working Pressure Applicable
External Maximum Allowable Working Pressure Not Applicable
Ps Static head from liquid or bulk materials (e.g. catalyst) Not Applicable
D Dead Weight of the vessel , Contents and Appurtenances ,
including the following:
• Weight of vessel including internals, supports. Applicable
• Weight of vessel contents under operating & test conditions. Applicable
• Refractory Linings, Insulation. Not Applicable
• Static Reactions from weight of attached equipment. Not Applicable
L • Appurtenances Live Load Not Applicable
• Effect of Fluid Flow Not Applicable
E Earthquake Loads Applicable
W Wind Loads Applicable
S Snow Loads Not Applicable
9.1 Applicable Design Load Combinations (As per Table 4.1.2 of Code) :
General Primary
SR.
Design Load Combinations Membrane Allowable
NO.
Stress
1 P + Ps + D S
2 0.9 P + Ps + D + (W or 0.7 E) S
3 0.9 P + Ps + D + 0.75 (W or 0.7 E) + 0.75 L + 0.75 S S
Notes:
1) 0.9 P is an Operating Pressure Condition.
2) S is Allowable Stress of material at applicable Temperature (Design / Operating).
10.1 Company shall be responsible for design, construction and installation of Pressure Relief Valve &
meeting the requirement of the Code.
10.2 Pressure Relief Valve suitable for Compressed Air Service shall be provided on Nozzle N2.
Type of over-pressure protection system: Pressure Relief Valve.
10.3 Requirement of any Jurisdictional Acceptance: Being a normal Air Buffer Tank in compressed
air service, any Jurisdictional Acceptance is not required before operation of the vessel.
11. ADDITIONAL REQUIREMENTS:
Additionally all welds shall be visually examined on internal & external surface as per 7.5.2 of Code.
Post Weld Heat Treatment is required for complete vessel as per Part 6.4.2 & Table 6.8 of the Code.
Impact testing requirements for materials and welds shall be evaluated by the supplier as per 3.11 of the
Code. Impact testing is however mandatory for the hub type forgings. Impact test shall be carried out at
MDMT or colder temperature and shall meet the Code requirements.
All material shall comply with applicable material specifications and Part 3 of the Code.
Code marking shall comply with Part 2.F.1 of Code. Additionally the supplier shall provide a
name plate showing name of the company, name of the supplier, Item number and date of
hydrostatic test.
Vessel shall be Hydro tested at supplier’s facility before dispatch. Hydrostatic test media shall
be water and metal temperature during test shall not be less that 17 deg C. After Hydro test
vessel shall be fully drained, cleaned & dried.
Complete external surface of vessel including saddle assembly & bottom of base plate shall be
painted as per the painting specification provided with the contract.
ORIGINATOR: ABC CONSULTANTS DOCUMENT NUMBER: UDS-AB-001 (REV 0)
1.0 GENERAL
1.1 The criteria specified shall apply to nozzles above 2 in. NB for vessels constructed of carbon
steel and low alloy steels.
1.2 The forces contained herein are considered minimum criteria in order to allow for an
economical design of the connecting piping.
1.3 Nozzle loading geometry is shown below for reference
ORIGINATOR: ABC CONSULTANTS DOCUMENT NUMBER: UDS-AB-001 (REV 0)
150 0.6
300 0.7
600 0.8
900 0.9
1500 1.0
STEP 1: The following loading history has been provided in the UDS
The vessel normally operates in the static state condition. However the following loading history can be
considered for the purpose of fatigue evaluation:
• Planned annual shutdown requiring full depressurization: 2 per year
• Unplanned shutdown requiring full depressurization during first year of operation: 6
• Unplanned shutdown requiring full depressurization after first year of operation: 2 per year
• Automatic shut down requiring full depressurization due to fire/emergency condition: 2 per year
• The vessels normal operating pressure is 4.481 MPa. The actual pressure variation shall be
within ±10% of this pressure. However the HP compressor may trip during the operation and
can cause pressure variation exceeding 20% of operating pressure. Such trips are not expected
to be more than 6 per year.
• The vessels normal operating temperature is 50oC and no fluctuations in temperature are
expected during normal operation. However the shutdown conditions may cool down the vessel
to ambient temperature of not less than 5oC.
• The vessel is of carbon steel and has no metals which have different coefficient of thermal
expansion.
STEP 2: The expected pressure cycles N ΔFP are estimated on the following basis:
i) As per operating procedure, this plant does require annual shutdown. Consider 2 shutdowns in a year.
Therefore total cycles for 20 years of plant life will be 40 (Total - 40)
ii) Unplanned shutdown requiring full depressurization of Air Buffer Tank during first year of operation
do not exceed 6 @ 1 per 2 months (Total - 6)
iii) Unplanned shutdown requiring full depressurization of Air Buffer Tank after the first year of
operation do not exceed 2 per year. (Total - 38)
iv) Automatic shutdown requiring full automatic depressurization of the Air Buffer Tank 1 per year
(Total - 40)
v) Total No. of pressure cycles N ΔFP are therefore 40 + 6 + 38 + 40 = 124
STEP 3: The expected operating pressure cycles N ΔPO are estimated on the basis that during normal
operating condition, Air Buffer Tank operates at 4.481 MPa. However when the compressor trips due to
any other faults the pressure exceeds 20% of operating pressure. Total such trips are expected not to
exceed 6 (1 every 2 months) in a year. Hence cycles due to operating condition is 6 X 20 = Total 120
STEP 4: The expected temperature differential cycles N ΔTE are estimated on the basis that there will be
always hot compressed air incoming to the Air Buffer Tank to avoid vessel cool down to ambient
temperature. Only planned & unplanned shutdown may result in a cool down of the Air Buffer Tank.
The temperature differential of 45 °C will result in maximum factor of 1 as per Table 5.8. Total cycles
therefore are estimated to be 124 x 1 = 124.
STEP 5: The expected temperature cycles N ΔTα are zero as there is no weld between metals which have
different coefficient of thermal expansion. Total cycles are therefore estimated to be 0.
ORIGINATOR: ABC CONSULTANTS DOCUMENT NUMBER: UDS-AB-001 (REV 0)
The expected number of cycles per Para 5.5.2.3, Method A, for cycles Step 2 to Step 5 is as follows:
Hence the vessel meets the integral type construction requirements of the Code
As per Table 5.9 of the Code, the maximum number of cycles permitted without carrying out fatigue analysis
for integral type construction with no nozzles in the knuckle region of the head = 1000 which is > 368
Conclusion: No fatigue analysis is required for this vessel as the intended vessel operation satisfies the
Part 5.5.2.3 of ASME code section VIII Div. 2 for the considered vessel design life of 20 years.