You are on page 1of 1

(A) Amount Claimed for RB - 11 1437 tn

(B) Amount Certified by HSCC 1247 tn


(C) (A) less (B) 190 tn

(D) Waste 71.85 tn (Cumulative Value)


Chairs 37 tn
Pedestals
Raft (Including Water tank, Sump and lift)
Ground Floor
First Floor
Clip Spacer for Retaining Wall
Top and Bottom RC Wall
STP
Roof Slab including Porch
Upper roofs
Extra Lap 19 tn
Column Raft to Ground Floor
Column Ground Floor to First Floor
Column First Floor to Roof
Retaining Wall
Ground Floor and First Floor Slab
Raft
Roof
STP

(C) - (D) 62.15 (Amount not certified due to % of Work)

(D) Not yet Claimed(Work not yet done)


STP Wall (18tn out of 63 tn certified) 45
Staircase (15tn out of 30 tn certified) 15
Boundary Wall (17tn out of 66 tn certified) 49
Porch (GL 9-10 & J-M) 7
Other Small Items 20
(Claim for Next RB -12 with 100% work) 136