Professional Documents
Culture Documents
Masterclass
Foundation and
Practitioner
Sampler
Foundation and Practitioner Exam Sampler PRINCE2
Copyright
All rights reserved. No part of this book may be reproduced in any form or by any electronic or
mechanical means including information storage and retrieval systems – except in the case of
brief quotations in articles or reviews – without the permission in writing from its publisher,
David Geoffrey Litten
All brand names and product names used in this book are trademarks, registered trademarks,
or trade names of their respective holders.
A. 1, 2, and 3
B. 1, 2, and 4
C. 1, 3, and 4
D. 2, 3, and 4
A. Substituting the term project charter for the Project Initiation Documentation
B. Making the programme management team responsible for asking the question “is this
project worthwhile and viable?”
C. Combining issues and risks into one register
D. Referring to the organization’s quality management process in the Quality Management
Approach
3. Which of the following options does NOT show how the PRINCE2 roles can be tailored?
A. Allow the Project Manager to carry out the role of Team Manager
B. In a program, provide project support of a programme wide level
C. On a large project, have several Executives
D. On a small project, combine the roles of the Senior User and the Executive
4. Which of the following supports the PRINCE2 principle of ‘tailor to suit the project
environment’?
5. Amending the project’s progress reports so that they add here to the organization’s internal
communication standards is an example of which of the following?
6. After Initiation and the production of the project Initiation documentation (PID), the
Project Brief is:
A. No longer maintained
B. Used as a baseline for checks at the end to see whether the project satisfied its original
objectives
D. Held in the Daily Log and kept up to date to serve as the Project Managers overview
7. Weighing a project’s benefits against ongoing operational and maintenance costs is one
aspect of _____________
A. Sensitivity Analysis
B. Investment Appraisal
D. Cost Planning
B. The Project Manager is normally from the customer side, not the supplier side
D. The Project Manager role is all optional and need not be filled
10. Which of the following options represents a good candidate for Senior User?
1. someone who can assess and confirm the viability of the project approach
2. someone who will represent those who maintain the projects products in their
operational life
3. someone who can represent those who will by the project products once they have
been developed
4. someone who will oversee marketing the projects products once they have been
developed
A. 1, 3, 4
B. 1, 2, 3
C. 1, 2, 4
D. 2, 3, 4
11. Which of the following roles does PRINCE2 say might be given some authority to authorize
requests for change?
1. Corporate or program management
2. The project board
3. The project manager
4. The team manager
A. 1, 2, 3
B. 1, 3, 4
C. 1, 2, 4
D. 2, 3, 4
14. The Business Case refers to a timescale. What does this timescale refer to?
A. The timescale of the project and the period over which benefits will be realized
15. What is meant by the term ‘Business Justification’ from a PRINCE2 point of view?
17. Which of the following is NOT used as an input to the activity Prepare the Risk
Management Approach?
A. Project Mandate
B. Project Brief
C. Lessons Log
D. Daily Log
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
20. Which of the following options is a fundamental aspect that must be in place and
remain in place for a plan to succeed?
A. Schedule
B. Plan prerequisite
C. Planning assumption
D. Customer quality expectation
A. 1
B. 1 and 4
C. 2 and 3
D. 3
22. Which of the following events can trigger the process Managing a Stage Boundary?
1. The current stage looks like it is nearly finished
2. The project board want an Exception Plan
3. Starting Up a Project process nears completion
4. Project tolerance is forecast to be exceeded
E. 1, 2, and 3
F. 1, 2, and 4
G. 1, 3, and 4
H. 2, 3, and 4
23. If the Project Manager notices that a stage is deviating from its plan, what should they
do if controlled action is within the authorities’ limits delegated by the Project Board?
E. Take corrective action and continue with the stage, adjusting any Work Packages as
necessary
F. Record a recommended action and before taking it, confirm that the board is happy for
the delegated allowance to be used in this manner
G. Implement the controlled action but inform the board off two words of the exact nature
of the problem and the action implemented to correct it
H. Plan a preferred action and get approval from Project Assurance before taking it, to be
quite sure that required standards and controls are complied with
24. When performing the activity Review Work Package Status, the Project Manager
updates the Stage Plan. Why is this?
A. To check whether the team has any further Work Packages to do in the stage, in order
to start preparing the next Work Package, if there is one, for the team
B. To update the plan with actual time taken and money spent, to date, forecasts and
adjustments, using progress information from the Team Manager
C. To monitor whether the project remains likely to finish within the tolerances set by
corporate or programme management
D. To record details of Project Assurance checks carried out on the related Work Package,
and the time and cost of performing those checks
25. Which management products does the Project Manager use to review the progress of
Work Packages?
1. Checkpoint Reports
2. Quality Register
3. Lessons Log
4. Configuration Item Records
E. 1, 2, 3
F. 1, 3, 4
G. 1, 2, 4
H. 2, 3, 4
26. Why does the Project Manager check the Benefits Management Approach from time to
time during a delivery stage?
To see whether any benefit reviews are due, and if so, arrange them
27. If the stage is projected to go only vary slightly outside stage cost tolerance, but this will
not affect project cost tolerance, what should the Project Manager do?
28. If the Team Manager calculates that the work of a Work Package will exceed the
maximum time limit (tolerance) set by the Project Manager, what should the Team
Manager do?
A. Report the matter as a lesson identified when the Work Package is delivered, to help
with more accurate estimation on future projects
B. Send an issue to the Project Manager, unless some of the notification procedure has
been specified in the Work Package
C. Do nothing until the next Checkpoint Report is due, at which point the details of the
problem and the new estimated completion date should be put on record
D. Do nothing for the time being but tried to make time savings during the remaining work
to minimize the delay
29. Which of the following are part of the objectives of the process Managing Product
Delivery?
1. To ensure that work on products allocated to the team is authorized and agreed
2. To ensure that accurate progress information is provided to the Project Manager at an
agreed frequency, to ensure that expectations are managed
3. To ensure Team Managers, team members and suppliers are clear as to what is to be
produced and what is the expected effort, cost and timescales
4. To ensure that any delays in executing a Work Package do not impact the agreed
delivery targets at the stage of the project, as set down in the plans
A. 1, 2, and 3
B. 1, 2, and 4
C. 1, 3, and 4
D. 2, 3, and 4
30) What is defined when deciding how to tailor PRINCE2 to suit the project?
During the Starting Up a Project process, which of the following would be the most
appropriate types of information?
A A preferred supplier contract should be placed with the electrical contractor company
to repair and maintain all BodyPrimer Plc electrical equipment
B Nick Nathan had asked for suggestions to increase and improve revenue from the city-
center gymnasium
C The new gymnasium site project will have a timeframe of 4 months and the expected
revenue benefits will repay the project costs within 48 months
D The project will have an initiation stage plus two delivery stages
A The design of the new changing rooms will be done by BodyPrimer Plc staff, but the
electrical installation will be outsourced
B After consultation with specialists, the estimated time frame for the opening of the new
gymnasium site was twelve weeks
C BodyPrime Plc have never used internal staff for refurbishing before
D One of our gymnasium equipment suppliers frequently ships incorrect items and should
be removed from our preferred suppliers list
A When Nick had previously asked staff to take on extra duties, the gym staff and their
union asked for double overtime rates
B This is the first time BodyPrime Plc has expanded beyond their current building
C The quality and reliability of the subcontractor is not known to Nick or his staff
D The new gymnasium manager has made it clear that there must be no drop in changing
room standards in the new gym facility
4. Which statement is an appropriate entry for the Stage Plan for the initiation stage?
A The plan is based on the local council Health and Safety consultant being available
during the initiation stage
B The project management team will consist of the new center manager with the Head
Coach Brian Burch as Senior User
C A new risk has been identified while creating the Initiation Stage Plan
D The initial project cost estimate will have tolerances of plus £5K and minus £2K.
E Staff annual holiday choices may impact the new gymnasium opening day
A During preparation of the Project Brief, the Daily Log was updated with newly identified
risks
B The plan is based on the availability of a suitable skills and experience required for the
construction of both changing rooms
D The Gym Manager wants the new gymnasium completed in time for the peak new
memberships during next January
6. During the End Stage report preparation for stage four, the Project Manager noted the
team that gained valuable experience on designing and installing electrical ventilation
systems. Realizing this could be useful for future projects, particularly new ventilation
installations, he created a Lessons Report detailing this experience as part of the End Stage
Report.
A Lessons Reports are only created at the end of each stage during the Managing a Stage
Boundary process
B The Project Manager should pass on any useful experience learned during the stage
within the End Stage Report
C This is not so; the Project Manager should use the Lessons Log to pass on expertise to
relevant people
D The Lessons Report is a management product that should only be created at the end of
the project during the Closing a Project process
7. During the Managing a Stage Boundary process at the end of the second stage, the
Project Manager worked with the third-party company who is to install the new ventilation
system. The Project Manager created Work Packages for them and authorize them to carry
out their work. Next, the Project Manager requested authorization from the Project Board
for the Stage Plan containing this work.
C It is the Project Board that should authorize the Stage Plan before the Project Manager
authorizes Work Packages for the delivery of work within that stage
D It is the Project Board that makes all the authorizations within the project, so it is they
who should authorize the Work Packages
8. Which two PRINCE2 management products would be, or might be, updated by the
project manager for this project on a stage boundary?
C Risk register to show any changes in the risk status of the risk review
D Risk register to show any changes in the risk status of the risk review
E Project approach to record any changes in constraints for the final deliverable, all the
way that the project must be run
F Project mandate to keep the overview of the project up to date with any changes
9. Which two items of information would be relevant to include in the end stage report?
C This summary of daily log entries for the stage that is just finishing
D A list of all the issues received in the stage that is just finishing
10. During stage four, the sales and marketing director has requested that all internal
walls of the new gymnasium to match the brand colors of the existing premises. This is a
relatively small change since the emulsion paint has yet to be ordered. The marketing
director is responsible for all outward communication for the company, and so the project
manager amends the Work Package and instructs the decoration team to implement the
change.
A The Project Manager has the authority or to rise all changes to the projects products
B The marketing director is responsible for communication and has the authority to
initiate this change
C This is not allowed since the product has been baselined and therefore cannot be
changed
D Requests to change baselined products should be recorded in the issue register and be
subject to an impact analysis before being authorized by the appropriate change authority
11. Towards the end of the first delivery stage, the Executive attended a senior
management briefing where Nick Nathan raised concerns about excessive e-mail and paper
Communications throughout the organization. Nick has instructed that Highlight Reports
should not be produced at set intervals but only when requested by him. What should the
Project Manager do?
A Inform Nick that the request is refuse because it does not comply with the chosen
PRINCE2 project method
B Refer the matter to Quality Assurance, which has responsibility for organizational
standards including project standards and put an entry in the Risk Register
C Explain the functioning of the Highlight Report to Nick and advise that there are no
regular progress meetings in PRINCE2. If Nick still insists, make a note in the Daily Log and also
update the Communications Management Strategy.
D Ignore the request has the PRINCE2 method is a published “best practice” authority
12. After the start of the first delivery stage a team member has found a faster way of
doing preparation work on the walls and ceilings of the gymnasium and changing rooms
without reducing quality and has suggested this on an issue. What one action should the
Project Manager take?
A Ignore the issue as the work is the responsibility of the team manager
B Record the issue in the Issue Register or Daily Log and investigated further
C Refer the matter on to the Senior Supplier for a decision and any necessary action
D As it is a minor matter, send the issue back to the team member without recording it
and tell them to go ahead as suggested if they are sure it will work
Colum 1 contains a list of events that occurred in stage four of the project. For each event in
column one, select from column two the appropriate PRINCE2 Theme that should have been
used to deal with it. Each selection from column two can be used once, more than once, or
not at all
13. The third-party electrical installation team needs official A. Business Case
instructions from the Project Manager to start their work B. Organization
14. One of the buyers from purchasing department has lost their C. Quality
copy of the requirements document for electrical fittings. He D. Plans
needs a new copy. E. Risk
15. The third-party electrical installation contractor has found a F. Change
new cable ducting system which will reduce project costs and G. Progress
save installation time. The Project Manager needs to assess this
possibility
16. The new shower rooms within the changing facility has been
completed and is ready for review
Answer the following questions about the project to prepare
for the new gymnasium. For each item in column one, select
the correct PRINCE2 product in column two where that
information would be recorded first. Each selection from
column two can be used once, more than once, or not at all
17. The manager of the new gymnasium has said that due to the A. Checkpoint
success since its launch of the online membership website, the report
changing rooms could be needed a week earlier than originally
planned. B. Issue report
18. The Senior User has been checking the last Highlight Report C. Highlight report
and now wants to ask the Project Manager a question about the
forecast stage timing. D. Exception report
19. A Team Manager has assembled information on the progress E. Daily log
of his current Work Package and it is time to pass this
information back to the Project Manager. F. Lessons log
G. Risk register
H. None of the
products A to G
above
20. In a regular check of the stage status, a Project Manager has discovered that costs
have risen because of essential overhead lighting fittings were slightly more expensive than
originally budgeted. Because of other smaller overspends on earlier items, this will take the
stage over the cost tolerance limits set by the project board. The projected over spend is only
£4.80 over tolerance, but at this point in the stage it is unlikely that any further purchases will
be cheaper to offset is over spend. What should the Project Manager do?
B Monitor the spend and only report it if the over-spend get significantly worse on
remaining things to be purchased in this stage
C Do nothing for the moment but report the matter on the next Highlight Report
impact analysis, and then authorize the change at the right level of
Change Authority (the Project Board or their representatives).
11 D The Project Manager must do as the Executive instructs, and it makes
sense to talk about it first to explain the function of the Highlight
Report. The strategies outlined in the Project Initiation Documentation
can be modified during the project although this would more normally
happen at a stage boundary.
12 B The Project Manager should record the issue in either the Issue Register
or Daily Log, and then check it out. It should not be ignored or passed
on to a Project Board member. The Project Manager should not send it
back to the team member advising them to get on with it as the team
member might be wrong. As a minimum, the Project Manager would
be likely to talk to the Team Manager about the issue, as part of the
“examine” function of the activity “Capture and examine issues and
risks”.
13 G The Progress Theme describes how the Project Manager uses the Work
Package as a way of controlling the work of the teams. The Work
Package gives authorization for the teams to start creation of the
specialist products and ensures that they start work at the correct time.
14 F The Change Theme covers configuration management. Configuration
management is used to administer the storage, security, and issuing of
project products and these include both specialist and management
documents.
15 E The electrical installation contractor has identified what PRINCE2 calls
an “opportunity”. Opportunities are types of risks that may affect the
project in a positive way. All risks are assessed using the Risk Theme.
16 C Reviewing products are they have been created is a quality control the
activity that is covered by the Quality Theme.
17 B This is an issue rather than a risk and would be initially treated that
way.
18 H Any small inquiry from the Senior User need not be handled as an issue
at all. It could be dealt with over the phone or face to face rather than
formally recorded. Beware of turning PRINCE2 into a paper trail where
even thoughts or general dialogue must be written down!
19 A The Checkpoint Report is the progress report from a Team Manager to
the Project Manager so do not confuse this with the Highlight Report
which gives progress to the Project Board from the Project Manager.
20 A If the Project Manager calculates that a stage will finish outside
tolerance and cannot adjust it to bring it back within those limits, then
the stage is in exception. The Project Manager has no discretion and
must report the exception immediately. It would be pointless to return
the items which are described as “essential” so their absence would
stop the project from being completed successfully.
Projex Academy |prince2_exam_sampler_v1.0|© David Geoffrey Litten 2018 25
Foundation and Practitioner Exam Sampler PRINCE2