c

Waktu Kerja
Bulan Tanggal Jadwal Kerja
(Jam)
11 08.00-12.00 4
13.00-18.00 5
12 08.00-12.00 4
13.00-17.00 4
13 08.00-12.00 4
13.00-17.00 4
14 08.00-12.00 4
13.00-17.00 4
15 08.00-12.00 4
13.00-17.00 4
16 08.00-12.00 4
13.00-17.00 4
17 08.00-12.00 4
13.00-18.00 5
18 08.00-12.00 4
13.00-18.00 5
19 08.00-14.30
14.30-17.00 2.5
20 08.00-12.00 4
13.00-15.00 2
21 08.00-12.00 4
Januari
13.00-15.00 2
22

23 10.00-12.00 2
13.00-17.00 4
24 08.00-12.00 4
13.00-17.00 4
25 08.00-12.00 4
13.00-17.00 4
26 08.00-12.00 4
13.00-17.00 4
27 08.00-12.00 4
13.00-17.00 4
28 08.00-12.00 4
13.00-17.00 4
29 08.00-12.00 4
13.00-17.00 4
30 08.00-12.00
13.00-17.00
31 08.00-12.00 4
13.00-17.00 4
total jam kerja januari 143.5
Tanggal
1 08.00-12.00 4
13.00-17.00 4
2

8 08.00-12.00 4
Februari 13.00-17.00 4
9 08.00-12.00 4
13.00-17.00 4
10

11 08.00-12.00 4
13.00-16.00 3
12 08.00-12.00 4
13.00-17.00 4
13 08.00-12.00 4
13.00-17.00 4
14 08.00-12.00 4
13.00-17.00 4
15 08.00-12.00 4
13.00-16.30 3.5
total jam kerjaa februari 62.5
Keterangan

Penataan dan penyetingan kedudukan crane


Penataan dan penyetingan kedudukan crane
Penyusunan dan Penataan peralatan Crusher
Penyusunan dan Penataan peralatan Crusher
Perapihan dan penataan peralatan crusher
Perapihan dan penataan peralatan crusher
penataan peralatan crusher
penataan peralatan crusher
penataan peralatan crusher
penataan peralatan crusher
setting conveyor
bongkar muatan mobil trailer
bongkar muatan mobil trailer
bongkar muatan mobil trailer
setting conveyor
setting conveyor
breakdown
setting penataan alat crusher
setting conveyor
setting conveyor
setting peralatan crusher
setting peralatan crusher
Breakdown
Breakdown
setting conveyor
angkat peralatan jaw
membantu pengangkatan jaw di unit crusher
membantu pengangkatan jaw di unit crusher
membantu pengangkatan jaw di unit crusher
membantu pengangkatan jaw di unit crusher
membantu pengangkatan jaw di unit crusher
membantu pengangkatan jaw di unit crusher
setting conveyor
setting conveyor
setting conveyor
setting conveyor
setting conveyor
setting conveyor
Standby Tidak ada kegiatan
Standby Tidak ada kegiatan
setting conveyor
setting conveyor
Setting conveyor
Setting Panel
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
Breakdown
setting conveyor
setting conveyor
Setting ayakan
Setting ayakan
Libur
Libur
setting conveyor
setting conveyor
setting conveyor
setting conveyor
setting screen
setting screen
setting screen
setting screen
setting screen
setting screen
Waktu Kerja
Bulan Tanggal Jadwal Kerja
(Jam)
23 08.00-12.00 4
13.00-17.00 4
24 08.00-12.00 4
13.00-17.00 4
25 08.00-12.00 4
13.00-17.00 4
26 08.00-12.00 4
13.00-17.00 4
27 08.00-12.00 4
Januari
13.00-17.00 4
28 08.00-12.00 4
13.00-17.00 4
29 08.00-12.00 4
13.00-18.00 5
30 08.00-12.00 4
13.00-17.00 4
31 08.00-12.00 4
13.00-17.00 4
Tanggal
1 08.00-12.00 4
13.00-17.00 4
2 08.00-12.00 4
13.00-17.00 4
3

4 08.00-12.00 4
13.00-17.00 4
5 08.00-12.00 4
13.00-17.00 4
6 08.00-12.00 4
13.00-17.00 4
7 08.00-12.00 4
13.00-17.00 4
8 08.00-12.00 4
Februari
13.00-17.00 4
9 08.00-12.00 4
13.00-17.00 4
10

11 08.00-12.00 4
13.00-17.00 4
12 08.00-12.00 4
13.00-17.00 4
13 08.00-12.00 4
13.00-17.00 4
14 08.00-12.00 4
13.00-17.00 4
15 08.00-12.00 4
13.00-17.00 4
total jam kerja excavator komatsu pc 200 177
Keterangan

Angkat Hopper
Setting Hopper
Angkat Kaki Hopper
Loading besi kaki hopper
transfer hopper
angkat rolling
angkat hopper
Transfer Hbeam
cut area crane
transfer Hbeam
setting dudukan jaw
setting corong
setting hopper
Setting Hopper
setting hopper
setting kaki Screen
setting ayakan
setting kaki hopper

setting kaki hopper


setting kaki hopper
setting kaki hopper
setting kaki ayakan
LIBUR
LIBUR
setting kaki hopper
transfer Hbeam
setting kaki hopper
transfer Hbeam
setting lantai jaw
setting h beam
transfer Hbeam
Setting dudukan jaw
setting kaki screen
transfer Hbeam
setting kaki screen
transfer Hbeam
LIBUR
LIBUR
setting dudukan screen
transfer Hbeam
setting dudukan screen
setting kaki ayakan
kumpulkan roll
setting corong dan transfer Hbeam
setting corong dan kumpulkan roll
transfer Hbeam ayakan
transfer besi flat
Setting kaki ayakan