You are on page 1of 31

Data Curah Hujan Maksimum Tahunan

PA 1976 PC 1973
No Tahun St.A St.B St.C St.D No Tahun
1 1973 66 119 120 1 1973
2 1974 51 85 120 27 2 1974
3 1975 66 3 32 49 3 1975
4 1976 18 36 92 4 1976
5 1977 103 34 97 127 5 1977
6 1978 85 21 137 81 6 1978
7 1979 62 17 109 93 7 1979
8 1980 139 99 101 45 8 1980
9 1981 102 1 74 75 9 1981
10 1982 87 7 58 83 10 1982
11 1983 76 22 64 118 11 1983
12 1984 84 81 49 74 12 1984
13 1985 62 1 68 49 13 1985
14 1986 259 126 57 73 14 1986
15 1987 47 22 83 63 15 1987
16 1988 77 200 54 87 16 1988
17 1989 85 73 22 116 17 1989
18 1990 75 46 68 55 18 1990
19 1991 41 13 43 51 19 1991
20 1992 26 1 48 32 20 1992
Jumlah 1527 870 1320 1390 Jumlah

LUAS STA
Sta.A 2477
Sta.B 3038
Sta.C 2497
Sta.D 2900
Total 10912

Menghitung Nilai Koefisien

Luas Sta.A
KTAa = = 0.2270
Luas Total
Luas Sta.B
KTAb = = 0.2784
Luas Total
Luas Sta.C
KTAc = = 0.2288
Luas Total
Luas Sta.D
KTAd = = 0.2658
Luas Total
Tahun St.A St.B St.C St.D Sta A x koef A Sta B x Koef B
1973 66 119 105.5 120 14.9819 33.1307
1974 51 85 120 27 11.5769 23.6648
1975 66 3 32 49 14.9819 0.8352
1976 58 18 36 92 13.1659 5.0114
1977 103 34 97 127 23.3808 9.4659
1978 85 21 137 81 19.2948 5.8466
1979 62 17 109 93 14.0739 4.7330
1980 139 99 101 45 31.5527 27.5625
1981 102 1 74 75 23.1538 0.2784
1982 87 7 58 83 19.7488 1.9489
1983 76 22 64 118 17.2518 6.1250
1984 84 81 49 74 19.0678 22.5511
1985 62 1 68 49 14.0739 0.2784
1986 259 126 57 73 58.7924 35.0795
1987 47 22 83 63 10.6689 6.1250
1988 77 200 54 87 17.4788 55.6818
1989 85 73 22 116 19.2948 20.3239
1990 75 46 68 55 17.0248 12.8068
1991 41 13 43 51 9.3069 3.6193
1992 26 1 48 32 5.9019 0.2784

Parameter Statik

Tahun Curah Hujan Max (Xi) Xi-X (Xi-X)² (Xi-X)³


1973 104.1457 35.2647 1243.598863137 43855.13725033
1974 69.8769 0.9960 0.9919289249 0.9879178487
1975 36.1620 -32.7189 1070.5293448819 -35026.59047746
1976 50.8653 -18.0157 324.5648078839 -5847.256456936
1977 88.7951 19.9141 396.5721664685 7897.3856230379
1978 78.0180 9.1370 83.4846534478 762.7987506529
1979 68.4653 -0.4157 0.1728069929 -0.0718359715
1980 94.1864 25.3054 640.3648934189 16204.710325223
1981 60.2978 -8.5831 73.6701370206 -632.3204336494
1982 57.0281 -11.8528 140.4896746832 -1665.20079778
1983 69.3820 0.5010 0.2509976025 0.1257489478
1984 72.4981 3.6171 13.0834653141 47.3242980677
1985 42.9351 -25.9459 673.1871788261 -17466.41416833
1986 126.3160 57.4350 3298.7808566763 189465.52536089
1987 52.5299 -16.3511 267.3582368523 -4371.599350593
1988 108.6388 39.7579 1580.6882091566 62844.795976729
1989 75.4814 6.6004 43.5656554255 287.5519905295
1990 60.0091 -8.8719 78.7105318833 -698.3116230243
1991 36.3198 -32.5611 1060.2276311311 -34522.21695956
1992 25.6686 -43.2123 1867.3068899727 -80690.71234997
JUMLAH 12857.5989297 140445.64878898

Tahun Curah Hujan Max (Xi) Log Xi' Log Xi'-X' (Log Xi'-X')²
1973 104.1457 2.0176 0.2111 0.0446
1974 69.8769 1.8443 0.0378 0.0014
1975 36.1620 1.5583 -0.2483 0.0616
1976 50.8653 1.7064 -0.1001 0.0100
1977 88.7951 1.9484 0.1418 0.0201
1978 78.0180 1.8922 0.0856 0.0073
1979 68.4653 1.8355 0.0289 0.0008
1980 94.1864 1.9740 0.1674 0.0280
1981 60.2978 1.7803 -0.0262 0.0007
1982 57.0281 1.7561 -0.0505 0.0025
1983 69.3820 1.8412 0.0347 0.0012
1984 72.4981 1.8603 0.0538 0.0029
1985 42.9351 1.6328 -0.1737 0.0302
1986 126.3160 2.1015 0.2949 0.0870
1987 52.5299 1.7204 -0.0861 0.0074
1988 108.6388 2.0360 0.2294 0.0526
1989 75.4814 1.8778 0.0713 0.0051
1990 60.0091 1.7782 -0.0283 0.0008
1991 36.3198 1.5601 -0.2464 0.0607
1992 25.6686 1.4094 -0.3971 0.1577
Rerata Log (X) 1.806546 JUMLAH 0.5829
Data Curah Hujan yang Hilang Dapat Dihitung dengan Rumus

St.A St.B St.C St.D PA 1976


66 119 120
51 85 120 27 r = 1 ( RA x rB + RA x rC + RA
66 3 32 49 n RB RC RD
58 18 36 92
103 34 97 127 1 1527 1527 1527
r = ( x 18 + x 36 +
85 21 137 81 3 870 1320 1390
62 17 109 93
139 99 101 45 = 58
102 1 74 75
87 7 58 83 PC 1973
76 22 64 118
84 81 49 74 r = 1 ( RC x rA + RC x rB + RC
62 1 68 49 n RA RB RD
259 126 57 73
47 22 83 63 1 1320 1320 1320
r = ( x 66 + x 119 +
77 200 54 87 3 1651 870 1390
85 73 22 116
75 46 68 55 = 105.499
41 13 43 51
26 1 48 32
1651 989 1320 1510
Sta C x Koef C Sta D x Koef D Curah Hujan Max (Xi)
24.1416 31.8915 104.1457
27.4597 7.1756 69.8769
7.3226 13.0224 36.1620
8.2379 24.4501 50.8653
22.1966 33.7518 88.7951
31.3498 21.5268 78.0180
24.9425 24.7159 68.4653
23.1119 11.9593 94.1864
16.9335 19.9322 60.2978
13.2722 22.0583 57.0281
14.6452 31.3600 69.3820
11.2127 19.6664 72.4981
15.5605 13.0224 42.9351
13.0433 19.4007 126.3160
18.9929 16.7430 52.5299
12.3569 23.1213 108.6388
5.0343 30.8284 75.4814
15.5605 14.6169 60.0091
9.8397 13.5539 36.3198
10.9839 8.5044 25.6686
Jumlah 1377.6194
Rerata (X) 68.88097

(Xi-X)⁴ Banyak Data = 20


1546538.1323957
0.9839229921
1146033.0782533 º SD =
105342.31451674
157269.48321754 = 25.3550773
6969.6873612999
0.0298622568
º Ck =
410067.19672343
5427.2890886387
19737.348692578 = 3.64922478
0.0629997964
171.1770646257
º Cs =
453180.97773587
10881955.140374
71480.426812758 = 0.50386868
2498575.2145668
1897.9663326522
º Cv =
º Cv =
6195.3478293566
1124082.6298138
3486835.0213395 = 0.3680999
21921759.508904

(Log Xi'-X')³ (Log Xi'-X')⁴ Banyak Data = 20


0.0094 0.0020
0.0001 0.0000
-0.0153 0.0038 º SD =
-0.0010 0.0001
0.0029 0.0004
0.0006 0.0001 = 0.1707138688
0.0000 0.0000
0.0047 0.0008
º Ck =
0.0000 0.0000
-0.0001 0.0000
0.0000 0.0000 = 3.8106104323
0.0002 0.0000
-0.0052 0.0009
º Cs =
0.0256 0.0076
-0.0006 0.0001
0.0121 0.0028 = -0.5173439432
0.0004 0.0000
0.0000 0.0000
º Cv =
-0.0150 0.0037
-0.0626 0.0249
-0.0440 0.0470 = 0.0944973805
tung dengan Rumus

x rD )

x 92 )

x rD )

x 120 )
TABEL Yn

n 0 1 2 3 4 5 6
10 0.4952 0.4996 0.5035 0.5070 0.5100 0.5128 0.5157
20 0.5236 0.5252 0.5268 0.5283 0.5296 0.5300 0.5820
30 0.5362 0.5371 0.5380 0.5388 0.5396 0.5400 0.5410
40 0.5436 0.5442 0.5448 0.5453 0.5458 0.5468 0.5468
50 0.5485 0.5489 0.5493 0.5497 0.5501 0.5504 0.5508
60 0.5521 0.5524 0.5527 0.5530 0.5533 0.5535 0.5538
70 0.5548 0.5550 0.5552 0.5555 0.5557 0.5559 0.5561
80 0.5569 0.5570 0.5572 0.5574 0.5576 0.5578 0.5580
90 0.5586 0.5589 0.5589 0.5591 0.5592 0.5593 0.5595
100 0.5600 - - - - - -

TABEL Sn

n 0 1 2 3 4 5 6
10 0.9496 0.9676 0.9833 0.9971 1.0000 1.0206 1.0316
20 1.0628 1.0696 1.0754 1.0811 1.0864 1.0915 1.0961
30 1.1124 1.1159 1.1193 1.1226 1.1255 1.1285 1.1313
40 1.1413 1.1436 1.1458 1.1480 1.1499 1.1519 1.1538
50 1.1607 1.1623 1.1638 1.1658 1.1667 1.1681 1.1696
60 1.1747 1.1759 1.1770 1.1782 1.1793 1.1803 1.1814
70 1.1854 1.1863 1.1873 1.1881 1.1890 1.1898 1.1906
80 1.1938 1.1945 1.1953 1.1959 1.1967 1.1973 1.1980
90 1.2007 1.2013 1.2020 1.2026 1.2032 1.2036 1.2044
100 1.2065 - - - - - -

TABEL Yt

Return Periode ( T ) Reduced Variate


( years ) YT
2 0.3668
5 1.5004
10 2.2510
20 2.9606
25 3.1993
50 3.9028
100 4.6012
200 5.2960
500 6.2140
1000 6.9190
5000 8.5390
10000 9.9210

Menghitung Hujan Rencana untuk Periode Ulang 2,5, dan 10 Tahun

Rerata = 68.881
Standar Deviasi = 25.3550773

Periode Ulang Faktor Frekuensi


yt yn sn x
(Tahun) (K)
2 0.3668 0.5236 1.06283 -0.1475306493 68.881
5 1.5004 0.5236 1.06283 0.9190557286 68.881
10 2.2510 0.5236 1.06283 1.6252834414 68.881

Intensitas Curah Hujan Rencana dengan Metode Mononobe

R 24
I = X ( )2/3
24 t

Diketahui : R2 = 65.1403 mm
R5 = 92.1837 mm
R10 = 110.0902 mm

Contoh : Untuk t = 1.7889 jam

65.140 24
I2 = x ( )2/3 = 118.3679
24 1.789

92.184 24
I5 = x ( )2/3 = 167.5090
24 1.789

110.090 24
I10 = x ( )2/3 = 200.0471
24 1.789

Perhitungan selanjutnya ditabelkan ;

t Intensitas Curah Hujan (mm/jam)


(jam) I2 I5 I10
1 22.5829 31.9583 38.1661
2 14.2263 20.1325 24.0432
3 10.8567 15.3640 18.3484
4 8.9620 12.6827 15.1462
5 7.7232 10.9296 13.0526
6 6.8393 9.6787 11.5587
7 6.1714 8.7334 10.4299
8 5.6457 7.9896 9.5415
9 5.2194 7.3862 8.8210
10 4.8653 6.8852 8.2226
11 4.5658 6.4613 7.7164
12 4.3085 6.0972 7.2816
13 4.0846 5.7804 6.9032
14 3.8877 5.5017 6.5704
15 3.7129 5.2544 6.2751
16 3.5566 5.0331 6.0108
17 3.4157 4.8338 5.7727
18 3.2880 4.6530 5.5569
19 3.1716 4.4883 5.3601
20 3.0650 4.3374 5.1799
21 2.9669 4.1986 5.0142
22 2.8763 4.0704 4.8610
23 2.7923 3.9515 4.7191
24 2.7142 3.8410 4.5871
7 8 9
0.5181 0.5202 0.5220
0.5882 0.5343 0.5353
0.5418 0.5424 0.5430
0.5473 0.5477 0.5481
0.5511 0.5515 0.5518
0.5540 0.5543 0.5545
0.5563 0.5565 0.5567
0.5581 0.5583 0.5585
0.5596 0.5598 0.5599
- - -

7 8 9
1.0411 1.0493 1.0565
1.1004 1.1047 1.1080
1.1339 1.1363 1.1388
1.1557 1.1574 1.1590
1.1708 1.1721 1.1734
1.1824 1.1834 1.1844
1.1915 1.1923 1.1930
1.1987 1.1994 1.2001
1.2049 1.2055 1.2060
- - -
Hujan Rencana
s
(Xrt)
25.35508 65.1403489828
25.35508 92.183729041
25.35508 110.0901872906

118.3679 mm/jam

167.5090 mm/jam

200.0471 mm/jam

I10
38.1661
24.0432
18.3484
15.1462
13.0526
11.5587
10.4299
9.5415
8.8210
8.2226
7.7164
7.2816
6.9032
6.5704
6.2751
6.0108
5.7727
5.5569
5.3601
5.1799
5.0142
4.8610
4.7191
4.5871
DENAH DAERAH PERENCANAAN

A1
B1
A4 I A2
B4 II
A3

C1 B3

C4 III C2

C3
D1

D4
E1
IV

E4 V E2
D3
E3

SUNGAI

PERHITUNGAN DEBIT RENCANA

Debit Rencana dihitung dengan menggunakan Rumus Rasional


Rumus Rasional ( Metode Rasional ) :
Qs = 0,00278 . Cs.C. I. A

Keterangan :
0.00278 = Faktor konversi dari mm3/jam menjadi m3/det. ( 0.001 m/3600 det ) x 10000
A = Luas areal (Ha)
Ls = Panjang Saluran (m)
Lt = Panjang aliran terjauh diatas lahan (m)
St = Kemiringan Lahan (%)
to = Waktu yang diperlukan untuk mengalir dari permukaan lahan ke saluran ter
td = Waktu pengaliran dalam saluran ( menit )
tc = Waktu pengumpulan air / waktu konsentrasi ( menit )
I = Intensitas curah hujan (mm/jam)
C = Koefisien pengaliran / run off
Cs = Faktor Koefisien Konsentrasi
V = Kecepatan aliran pada saluran

Tabel kecepatan rata - rata ( v ) pada saluran

Kemiringan rata-rata Saluran Kecepatan rata-rata


(%) ( m/det )
<1 0.4
1 sampai 2 0.6
2 sampai 4 0.9

Perhitungan Debit Rencana Untuk Hujan Rencana 15 tahun

Limpasan dari lahan


Direncanakan tidak menerima limpasan dari lahan (berdasarkan kondisi topografi)

Limpasan dari Jalan


Diketahui data-data sebagai berikut :
A1 = 0.4 Ha (Open Space)
A2 = 0.16 Ha (Jalan)
Ls = 200 m
Lt = 201 m
St = 0.0061 % (Kemiringan Jalan menurut standar Bina Marga)
Cj = X
0.8 (Jalan)
Cl = 0.7 (Open Space)
Perhitungan :
Lt 0.77
to = 0.019
( St ) 0.5

201 0.77
= 0.019
0.0061 0.5

= 8.03271907 menit

Ls Diasumsikan v = 0.4
td =
60v
200
td = = 8.33 menit
24

tc = to + td
tc = 8.0327 + 8.33 menit
tc = 16.3661 menit

2 tc 32.7321
Cs = =
2 tc + td 32.7321 +

Cs = 0.7971

Cj . A1 + Cl . A2 0,8 . 0,16 + 0,7 . 0,4


Cr = =
A1 + A2 0,16 + 0,4

Untuk periode ulang 2 tahun (T2)

RT 24 2/3

I= x Untuk T = 2 tahun
24 ( tc/60 )
I= 53.694 mm/menit

Qs = 0.00278 x 0.7971 x 0.7285714 x 53.694

= 3.467359E-02

Periode Ulang Rmax tc I


(tahun) (mm) (jam) (mm/jam)
2 65.14035 16.3661 53.694
5 92.18373 16.3661 75.985
10 110.09019 16.3661 90.745
ANAAN

Diketahui :

Q = 0

a = 20
b = 260
c = 300
d = 300
B2
Lebar jalan + Trotoar

Jalan = 8m

Koefisien run off ( C ) :

C1 = 0.3 Untuk petak II dan IV


C2 = 0.7 Untuk petak I, III dan IV
Cjalan = 0.8
D2
0.001 m/3600 det ) x 10000 m2

mukaan lahan ke saluran terdekat ( menit )

rkan kondisi topografi)

standar Bina Marga)


X X X
m/s

32.7321
8.33

+ 0,7 . 0,4
= 0.7285714
+ 0,4

Untuk T = 2 tahun RT = 65.140 mm

x 0.4

Qs
C A (Ha)
(m/detik)
0.72857 0.4 0.03467
0.72857 0.4 0.04907
0.72857 0.4 0.05860
m3/det

m e = 200 m
m f = 200 m
m g = 200 m
m

Untuk petak II dan IV


Untuk petak I, III dan IV
Menghitung Dimensi Saluran (Trapesium)

Diketahui data - data sebagai berikut :


Q rencana = 0.03467 m3/det
V asumsi = 0.4 m/det
n = 0.017 Saluran Batuan, Vegetasi pad
m = 4

Syarat B + 2h
= h m2+1
2
B + 2h
= h 52+1
2
B + 2h = 2h 17
2
B
= 4.12 h
2
B = 6.246 h

Perhitungan Luas Basah (A)


Q rencana 0.03467
Ad = Ad =
V asumsi 0.4
Ad = 0.09 m2

Ad = (B + ( m x h )) x h
Ad = ( 6.246 h + ( 4.0 h ) ) h
) )
Ad = 10.246 h2

0.09 = 10.246 h2

0.09 0.5
h =
10.246

h = 0.092 m B =

Perhitungan Tinggi Jagaan (W)


W = Ch
= C 0.092 Diambil nilai C =
= 0.14 0.092
= 0.012877
= 0.113 m

Perhitungan Keliling Basah ( P )


P = B + 2 h ( m2 + 1 )0,5
2 0,5
= 0.575 + 2 0.092 ( 4.0 + 1)
)
P = 1.33 m

Perhitungan Jari - jari Hidrolis ( R ) & Kemiringan dasar Saluran (S)


Ad 0.09
R = =
P 1.33
R = 0.065029 m

2 2
Vn 0.4 0.017
S = 2/3
R2/3 0.0650

S = 0.0017682

Perhitungan Lebar Permukaan Saluran ( T )


T = B +2mh
= 0.575 + 2 4.0 0.092
T = 1.310 m

Kontrol Kemiringan Saluran ( S )

Qxn 2 0.035 0.017


S = 2/3
A x R2/3 0.09 0.07

S = 0.001768226
S saluran = S rencana
0.001768226 = 0.001768 m3/det …… OK !!!

Kontrol Debit

1
Q = A x R2/3 x S0.5
n
2/3 0,5
1
Q = 0.09 x 0.065029 x 0.001768226 0,5
0.017
Q = 0.034673585

Q saluran = Q rencana
0.034673585 = 0.034674 m3/det …… OK !!!

Sketsa Saluran
1.310 m
T
htot

0.21 m

0.57 m
B
Saluran Batuan, Vegetasi pada Sisinya

m2+1

52+1

0.575 m

0.14
w 0.113 m

h 0.09 m