You are on page 1of 85

Assessment and Management

of
Equipment Integrity

S.K. Hazra
Process Safety Centre
Indian Chemical Council
Life Cycle Asset Integrity

Mechanical Pressure RBI


Integrity
Integrity
What is Asset Integrity Management
(AIM) and Optimization
 AIMS is the set of discipline, methods, procedures,
and tools to optimize the whole business impact of
Cost, Performance and Risk exposures( associated
with the availability, efficiency, quality, longivity
and regulatory/ safety/environment
compliance) of the Co’s Physical Asset ……
Institute of Asset Management, UK
 AIMS is the systematic and coordinated activities and
procedures through which an organization optimally
manages its physical assets and their associated
performance Risks ……. BS Standard
Pressure Equipment Integrity
Management (PEIM)
 A System for assessment of
Engineering Risk, life and integrity
of pressure containing equipment
used in Energy Production, Chemical
Processing, Storage and Transportation
of Oil/Gas, Refinery and Petrochemicals
must be in place
Pressure Equipment Integrity
Management (PEIM)
 Structured approach by Cos. for best
utilization of Assets in most cost effective
way
 Fundamentals of PEIM should be clearly
outlined
 Stakeholders outside Co. must understand
scope and play their part
 Formal approach to PIEM is through 101
essential elements
PEIM-An Optimization
 Optimize work priority against resource
availability
 Prioritize Issues to be attended by PEIM
 High Risk segments to be attended first
 Total 101 elements to be attended as per
priority to avoid major failure
 Implementation is likely to take substantial
time for complex aged facilities
Essential elements of PEIM
 MOC  Training and Certification
 Positive Material  Inspection Procedures
Identification (PMI)  Welding QA/QC
 Temporary Repairs  Qualified Suppliers
 Temporary Installation  Fabrication QA/QC
 Key/Critical Materials  Inspection Scheduling
degradation variables  Remaining life calculation
 Materials and Corrosion  Equipment Overdue
 Environmental Cracking  Piping Inspection
 Furnace Monitoring  Inspection Points
 Brittle fracture  Deadlegs
 Record Keeping  Thickness Measurement
 Flare Systems  Small bore Piping Insp.
Essential elements of PEIM
 Critical Check Valves
 Soil to Air Interfaces
 Failure Reporting
 Bundle Classification
 Inspection Recommendation  Wire wrapping/Boxing
Tracking
 Relief Valve Propping
 Risk Management  Hydrotesting Safety
 Corrosion under Insulation  On-stream Injection
 External Corrosion  NDE Specialist
Prevention  Carbon -1/2 Molly Inspection
 Hot Spots  Knowledge Transfer
 Bull Plugs  Localized Corrosion
 Fatigue Failures  Hot Tapping
 Flange Gaskets  Grey Zone Equipment
 Fitness for Service  Pressure Relief Valve
Auditing
 Cast Iron
 Tank Bottom Inspection
 Heat Tracing
Essential elements of PEIM
 Water Drop Out Points  Corporate Failure Memorry
 Inspection Staffing  Ammonium Salts
 ERW Pipe and Tubing  Hydrotest Water Quality
 Process Contamination  Pipe Rack Inspections
 Inspection of Tank Roofs  Total Cost of Ownership
 Inspection of Inaccessible  Flange Bolting Procedures
Locations  Valve Quality
 External Chloride Cracking  Surface Cleaning
 Process Creep  Bad Actor Pumps
 Mixed Metallurgy Piping  Plugged Vent on AST’s
Systems  PWHT Problems
 Third Party Equipment  Risk based T/A Planning
 Corrosive Mix Points  Failure Analysis
 Dummy Leg Corrosion
Brittle Fracture

 Carbon Steel exposure to cryogenic


condition to be avoided as all cost
 Potentially susceptible equipment to be
identified and closely monitored
 Effective knowledge transfer to Operating
Personnel
 Esso, Longdord Australia experienced
major accident
L
 API RP 920 or API RP 579 for reference
Carbon – ½ Moly
Inspection

 Highly susceptable to High Temperature


Hydrogen Attack (HTHA)
 Major fire due to failure of HE nozzle,HE being operated
750F below “Nelson Curve”

 API 941 can be used as a guide


 Technique “Automated Ultrasonic
Backscatter Technique (AUBT)” can find
and measure HTHA damage
 Is there a monitoring program in place L
Corrosion Fatigue

 Corrosion-fatigue is
the result of the
combined action of an
alternating or cycling
stresses and a
corrosive
environment. The
fatigue process is
thought to cause
rupture of the
protective passive
film, upon which
corrosion is
accelerated.
L
Corrosion Under Insulation
(CUI)

 Influence of “ Out of Sight” and “Out of


Mind” Syndrome
 CUI rate Monitoring (10 to 40 micron/Yr.)
 API 570 for guidance
 NZ Refinery Hydrocracker incident
 Is effective CUI Inspection Program in
place
L
Corrosion Under Insulation
(CUI)

 Influence of “ Out of Sight” and “Out of


Mind” Syndrome
 CUI rate Monitoring (10 to 40 micron/Yr.)
 API 570 for guidance
 NZ Refinery Hydrocracker incident
 Is effective CUI Inspection Program in
place
L
Critical Check Valves

 To function in a Safe and Reliable


manner in Critical Locations
 Important locations eg. Furnace Outlets
which must close in case of Tube rupture
 A Schedule for Swing Check Valves
operability
 Shell Deer Park Cracker suffered $ 300
million loss in 1997
 Is there a list and inspection Schedule L
Deadlegs

 Often experience varying corrosion


rate
 Differing Detection Methods
necessary
 API 570 for guidence

 Hydroprocess deadleg incident in


1996 –Incident in a Californian
L
Refinery
Environmental cracking refers to a corrosion cracking
caused by a combination of conditions that
can specifically result in one of the
following form of corrosion damage:
Stress Corrosion Cracking (SCC)
Corrosion fatigue

Hydrogen embrittlement

Stresses that cause environmental cracking arise


from residual cold work, welding, grinding, thermal
treatment, or may be externally applied during
service and, to be effective, must be tensile

L
Fatigue Failure
 Faituge failures are generally of serious nature
 Leads generally to sudden full bore rupture
 A phenomena almost un-detectable
 US Petrochemical Plant Reported dislodging
of a 4” Nozzle Valve with a blind flange
caused major fire
 Another PetroChemical Plant had full line
rupture of a 2”line releasing 10 Tons of
Hydrocarbon
 Vibration a major cause
 Awareness Program for Operators to understand
implication and report vibration in place? L
Flange Gasket
Selection and QA

 One of the fundamental of PIEM building


blocks
 Improper /makeshift selection of gaskets
caused innumerable incidents
 Spiral Wound Gasket with CS inner ring failure due
to CREEP

 Is a effective Gasket Selection and QA/QC


Program at Plant?

L
Flare System

 To operate 365 days with total reliability


 Prone to Corrosion and Fouling
 Ultrasonic scanning and radiography for
corrosion/crack detection
 Density radiography for detection of
fouling/plugging
 Non-functional flare line and absence of MOC
caused Bhopal disaster
L
Furnace Monitoring

 Furnace coils structural integrity to be


examined and ensured through scheduled
inspection and maintenance
 Effective inspection and data analysis
necessary (MPC Omega Analysis)
 Haldia and other instances of major
furnace failures L
Heat Tracing
 Vital for prevention of plugging in Safety
Devices and Emergency lines
 Inadvertent shut-off likely to plug vital
exhaust line by solidification of Process
material
 Twilight zone of responsibility between
Process and Maintenance
 Is an Audit with specified responsibility in
place
L
Hotspots

 Furnace and Refractory lined piped are


vulnerable
 Canadian Refinery furnace tube rupture
resulted fatality
 US Refinery line rupture due to Hotspot in
refractory lined flue gas transfer header
 Temperature resistant paints and
Thermographic detection techniques

L
Hydrogen Embrittlement
 The embrittlement of
of metal or alloy by
atomic hydrogen
involves the ingress of
hydrogen into a
component, an event
that can seriously
reduce the ductility
and load-bearing
capacity, cause
cracking and
catastrophic brittle
failures at stresses Hydrogen embrittlement occurs in a
below the yield stress number of forms but the common
of susceptible features are an applied tensile stress
materials and hydrogen dissolvedin the metal
L
Key and Critical (K/C) Materials
Degradation Variables
 K/C Variables not restricted to pressure, temperature,
composition only
 K/C Variables that can cause material degradation to
be
▪ Identified
▪ Documented
▪ Communicated
▪ understood
 Effective Knowledge to Operating Personnel
 Relevant Standards as available eg. API RP 941
(material limit for high temp. Hydrogen attack)
 Establishment of Integrity Operating Windows
L
Establishing Integrity Operating
Window
 Historical operating, maintenance &
inspection records
 Design data; lab data; operating data
 Metallurgical and corrosion data and
modules
 Process chemistry and engineering
knowledge
 Reactive chemistry knowledge
Establishing Integrity Operating
Window
 Recommended practices (industry and
company)
 Process and corrosion modeling tools
 Subject matter expertise and experience
(heavy dose)
 Metallurgical and corrosion data and
modules
Reasonable, practical IOW’s –
Not too conservative
Integrity Operating Windows –
Examples
 Physical
 Limits on pressures and temperatures
(design, operating),
 Partial pressures,

 Dew points,

 Dry points,

 Heating and Cooling rates,

 Delta P, etc.
Integrity Operating Windows –
Examples
 Physical
 Flow rates,
 Injection rates,
 Inhibitor dosage,
 Amperage levels motors,
 Slurry content,
 Hydrogen flux,
 Vibration limits,
 Corrosivity probes, etc.
Integrity Operating Windows –
Examples
 Chemical
 pH,

 Water content,

 Acid gas loading,

 Sulfur content,

 Salt content in crude,

 NH4HS content,

 NH3 content,
Integrity Operating Windows –
Examples
 Chemical
 TAN,

 Acid strength,

 Amine strength,

 Inhibitor concentration,

 Chloride contamination levels,

 Oxygen content, etc.


IOW Example – Hot Hydrogen
Service
Temperature
Mechanical Design Limits
 Mechanical design window
set by the design code e.g.
EOR Process Temp IOW
ASME
 IOW set by material limit
for high temperature SOR Process Temp

hydrogen attack in API RP


941
 SOR process temperature
definitely within the IOW
 EOR process temperature Pressure

possibly beyond the IOW –


need to know the hydrogen Based on H2 pp Based on
Total Pressure
partial pressure and
duration of EOR conditions
SOR EOR Present
Temperature, C 450 500
Pressure, MPa 3 3.1
Service,
Position Stress, MPa hr
T-piece 59.35 66.24 249660

249660
SOR - Start of Run
Straight 1a 36.70 41.02

36.70 41.02 249660


Field weld
1b2a 35.10 38.98 249660

Straight 2b 47.50 51.28 249660

Bend 1 33.60 36.66 249660

32.90 34.90 249660


Straight 3a
47.40 51.31 249660
Straight 3b
31.20 34.44 249660
Bend 2
38.30 42.16 249660
Straight 4a 249660
53.90 58.41
Straight 4b 37.20 40.38 249660
EOR - End of Run
Bend 3 37.20 249660

249660
Straight 5a 37.20 39.99
Integrity Operating Windows –
Typical Numbers per Operating Unit
(before & after an intensive review)
 Typically start with 5 -10 IOW’s that may
already be in place, along with other
operating quality variable limits
 Typically end up with 30 – 50 IOW’s with
about 5 -10% being critical limits
(requires drastic and/or immediate
action), and the rest being standard limits
(requires attention within a specified
timeframe to get back into control)
Definitions: IOW Critical Limit
A limit at which the operator has one last
opportunity to return the process to a
safe condition and, if exceeded, could
result in one of the following in a fairly
short timeframe:

• A Catastrophic Release of Hydrocarbons or


Hazardous fluids
• Loss of Containment
• Non-orderly Shutdown
• Significant Environmental Impact
• Other Unacceptable Risk
Critical IOW Limit – Examples
 Boiler Feed Water Level
 Loss of boiler feed water level could quickly cause
boiler tube rupture
 Hydroprocess Reactor Temperature
 Metal temperatures below the MDMT could give
rise to brittle fracture

 Heater Tube Skin Temperature


 Tube could rupture quickly if overheated, caused,
for example, by a no flow or hot spot condition.

 Sulfuric Acid Strength in Alkylation


 Too low acid strength could cause runaway
reaction
Definition: Standard Level
A limit that, if exceeded over a defined
period of time, could cause one of the
following to eventually occur:

• A catastrophic release of hydrocarbons or hazardous


fluids
• Loss of containment
• Non-orderly shutdown
• A negative impact to the long term unit performance
and its ability to meet turnaround run length
• Excessive financial impact
Standard Level Examples
 REAC NH4HS Concentration
 Corrosion of the air cooler and downstream
piping
 Heater Tube Skin Temperature
 Metallurgical creep could lead to eventual tube
failure.
 Crude Fractionator Dew Point
Temperature
 Sustained operation below dew point could cause
damage to fractionator internals or potential loss
of containment
Standard Level Examples
 pH of Crude Tower Overhead
 Sustained operation below standard pH level
could lead to corrosion of tubing and piping and
potential loss of containment.
 Desalter Outlet Salt Content
 Sustained operation above standard level could
lead to corrosion and potential loss of
containment
L
Integrity Operating Windows –
Successes
 In the CCD review, one IOW team noticed that a previous
project had installed the wrong construction materials –
immediate inspection revealed significant HTHA damage
 An operator on the team disagreed with the unit process
engineer and said that “we actually operate much hotter
than you think because we use the by-pass” – immediate
inspection revealed significant localized damage
 A corrosion engineer questioned the higher level of NH4HS
in the REAC system of an HCU – immediate inspection
revealed a previously-missed localized spot of significant
corrosion
 An IOW was set on NH4HS concentration at another
refinery, which then began to take routine lab samples –
soon thereafter discovered the concentration was too high
and took steps to increase wash water and adjust
feedstock
Operator Training on CCD’s and
IOW’s
 Level 1
 Awareness and Overview of the PEI Process Safety
Initiative
 SSA Video / CCD / RBI / OEMI / Operator Training
 Level 2
 Introduction to Corrosion Control Documents
 What they contain; where they’re stored; how to use
them
 Level 3
 Details contained within each operator’s unit-specific
CCD
 Specific IOW’s and the reasoning behind them
 What can happen if the IOW is exceeded
Life Cycle estimation
The remaining life of critical
components can be determined
through rigorous analysis of
- Thermal/ mechanical stresses,
- Natural frequencies and mode
shapes,
- Scale formation
- Crack initiation,
- Crack propagation
- Creep.
- Stress testing
- Vibration monitoring
Life Cycle estimation
For life assessment estimation expertise
required in
 Stress Corrosion Cracking
 Solid Particle Erosion
 Crack Propagation
 Low and High Cycle Fatigue
 LifeCycle Fatigue Crack Analysis Services
 Probabilistics
 Nuclear Steam Generator Tube Wear and Life
Assessment Services
 Customized System Health Management
L
l
L
On Stream Inspection
Injection Point (IP)

 Injection points undergo corrosion


 Potential corrosive IP’s to be listed
 Technical Dept./Process Engineers involvement
necessary
 API 570 for guidance
 Shell (1988) and Conoco known cases of
incidents arising out of IP corrosion
 Is effective On-Sream Inspection Program in
place
L
Pipe (Bull) Plug

 An overlooked source of releases and fire


 Vibration and thread connection main
factor for failure
 Major Fire in a Refinery in France arising out
of a sudden ejection of a Bull (Pipe Plug)
from a pump case
 US Midwest Refinery fire due to dislodging
of a Bull Plug when an Inspector stepped on
it
 A Structured inspection schedule exists?
L
Positive Material
Identification

 New construction have 2-4% material


error
 Running plants too can face upto 1-2%
material error
 IPCL (Nagothane. India) ,Baton Rouge
(Louisina, US) incidents
 API 578 to be used effectively for material
verification
L
Small Bore Piping
(SBP) Inspection
 Normally escapes attention
 SBP failure can cause serious
incidents:
 Hydrocracker fire in a California
Refinery (1980)-fracture of a 1” H2 line
 US Midwest refinery fire (2000)-
rupture of a ¾”SS line
 Practice to monitor and inspect high Risk
SBP in place?
L
Stress Corrosion Cracking (SCC)
 (SCC) is the cracking
induced from the
combined influence of
tensile stress and a
corrosive X 500
environment. The
impact of SCC on a
material usually falls
between dry cracking
and the fatigue
threshold of that
material
L
Wire wrapping/Boxing
of Flanged Leaks

 Considered a safe and successful practice for


attending leaks in Equipment and Pipelines
 To be supervised by Specialist/Material
Engineers
 Selant can overload bolted boxes and chemical
in it can cause corrosion at times
 HE head in a California Refinery blew off as
enclosed bolting corroded
 Case of Valve Bonnet blowing off

 Are these points covered-Mtc. Procedure ? L


L
API RP 941 Steels for Hydrogen
Service at Elevated
Temperatures and Pressures in
Petroleum Refineries and
Petrochemical Plants

L
API RP 920 -1990, PREVENTION OF
FRACTURE OF PRESSURE VESSELS
( withdrawn but still followed) L
Managing Effects of Aging

Intelligence •Influence the Future proactive


Risk

Knowledge •Ability to predict


future Condition

•Recognise Parameters
Information that affect
susceptibility to failure

•Recording Last
Data Condition after
reactive
Inspection)
Managing Effects of Aging
20

18

16

14

wallthickness[mm]
12

10

Tools to establish corrosion rates0 0 5 15 20


time [y] 25
Tools to establish technical condition 10

Tools to establish prediction confidence


Tools to establish minimum required wall thickness
Integration of Multiple Work
Processes Leading To
Sustained Asset
Long Term Integrity
Asset Integrity

Focused Asset Integrity Reviews


Design and
Materials Selection
Corrosion Risk-Based
Control & IOW’s Inspection

Asset integrity management is a balancing process


designed to achieve lowest total cost of ownership

59
Achieved Maintenance Cost& Plant Availability

1994 1995 1996 1997 1998 1999


0.0 95.0
% Reduction of Maintenance Cost

2.0
94.0

General Availability (%)


4.0
6.0 % plant 93.0
availability
8.0
92.0
10.0
12.0 91.0
% cost reduction vs.
14.0 Plant availability
90.0
Average of 10
16.0
Sites
89.0
18.0
20.0

…and Incident Free


Mechanical Integrity
 Written procedures to maintain the on-going
mechanical integrity of process equipment
are established and implemented
 Follow recognized and generally accepted
good engineering practices for inspections
and testing procedures
 Document each inspection and test
 Correct equipment deficiencies that were
found outside acceptable limits defined by the
process safety information/data sheet before
further use or in a safe and timely manner
Risk Based Inspection (RBI)
 Identify the probable damage mechanisms
 Review the equipment history and last
known condition
 Review any special inspection programs
underway, e.g. PMI, CUI, HTHA, D/L’s,
etc.
 Establish inspection
techniques/strategies/intervals
 Establish probability of failure before and
after planned inspection and mitigation
activities
 Estimate most likely failure mode, e.g. pin
hole leak, cracking, rupture, etc.
Remaining Lifecycle of Power plant Tubes
subject to overheat Creep damage
Remaining Life Assessment of Power
Plant Re heater Tubes
 Oxide scale technique is used to
determine RCLA of Boiler
RH/SH Tubes
 At high temp. scale forms inside
Tubes
 The scale grows on a
predictable rate depending on
tube wall temperature
 By measuring the thickness of Long-term Creep damage lead
scale, average time at a to costly Tube failure which
temperature can be assessed
can be prevented by RCLA
 The informations can be
entered into a software eg.
EPRI TubelifeIII to predict the
Remaining Time to failure
Example – Remaining Life Assessment
of Primary reformer Tubes
 The primary reformer is the most
critical asset in a Hydrogen
plant
 Reformer tube failure due to
Creep presents a particularly high
risk of unplanned outages
 Remnant life assessment of
reformer tubes minimizes the risk
of unplanned shutdowns due to
tube failures
 Tube harvesting/replacement
strategies can be based on sound
principles rather than arbitrary
criteria
 Reformers to be operated more
aggressively, resulting in
increased production and
profitability
Example – Remaining Life Assessment
of Primary reformer Tubes (Contd…)
 HP Alloys used in reformer tubes are not
amenable to standardized creep
condition assessment procedures such
as those in API 530 and API 579.
 Temperature and stress vary through
the tube wall and along the axis of the
tube e primary reformer is the most
 Due to variability in creep properties
a detailed database of alloy behavior
is required
 Laser-Optic Tube Inspection
System
 Hundreds of thousands of data points
recorded in a typical inspection.
 inspections Analyze 100% of data
following
 4 API RP579 Level III Fitness-for Service
and Remaining Life
Creep Behavior of HP Alloys
Primary Reformer
LCA
Creep Behavior of HP Alloys

Macrocracking
STRAIN 1 2 3

1. Primary Creep Microcracking


2. Secondary Creep
3. Tertiary Creep
Aligned
Cavities
Steady-
State
Creep Rate Isolated
Cavities

TIME

Cavities and Microcracks only display


themselves near end of life of tubes.
They do not allow
remnant life predictability.
Plant Data
LOTIS®
Inspection
Inspection Technology Comparison

Other technologies
are useful only at or
very near Tube Failure.
This is often too late to
predict Remnant Life
or to provide useful
tube replacement
strategy

L
Software
 Operates Nuclear aircraft carriers 365 days
 Landing and launching of Aircraft every
few minutes
 Young crew with average intelligence
 Near 100% availability w/o incident
Whose Job is Asset Integrity
Management
 Management
 Operations Grp
 Engineering/Maintenance Services
 Reliability Engineering
 Process Emgineering
 Project Engineering
 Corrosion Engeneering
 Inspection
Best Practice – Implementation of
Asset Integrity Program
 Corrective Action is the implementation
to eliminate a detected nonconformity.
 Preventive Action, which is the action to
eliminate the cause of a detected
nonconformity or other undesirable
situation.
 Elimination Action, which eliminates the
cause of a potential nonconformity or
other undesirable potential situation.
Key to Success in
Asset Integrity Management
 Effectiveness which is:
 Producing
 Decisive

 Decided

 Desired Results
 Procedures and Training not good enough
 Allocating Time and Money not good enough
 Knowledge transfer and Effective
implementation is the Key
PIEM- Structured vs Informal
 Structured approach is the Key
 Mere informal approach can not ensure
best asset integrity
 Structured approach to be adopted
immediately if not done
 Minimizes incidents (fire, explosion, toxic
release)
PEIM Shop level
Commitment and Approach
 Blocking and tackling
 Back to basics
 Perseverance
 No distraction on a/c of “Fire fighting”
 No distraction due to Production Pressure or
Poor Economic Environment
 Procedure
 Training
 Discipline
Common problem
 When oil prices are high,
production requirements tend to
take precedence, and
 When price is low—maintenance
and rejuvenation is seen as a
costly burden, which can be
deferred
Asset Integrity Management
Indicators
Co. Practice Status
 Leadership  Rate of Maintenance
 Responsibility problem
 Accountability  Ratio of Breakdown to
 Data Management Predictive Maintenance
 Quality for Critical Equipments
 Interpretation  Rate of Plant Changes
 Organization Learning not incorporated into
 Communication documentation before
 Employee involvement next Turnaround

You might also like