Schedule

The roof renovation of College of Architecture and Fine Arts is expected to take
five (5) months from the project approval.
Pre-Construction Phase: January 6,2019 – February 15,2019
1. Procurement
2. Design Phase
3. Bid Solicitation
Demolition: February 18,2019 – March 15,2019
1. Installation of safety Equipment
2. Roof Demolition
*Routine for each day before work:
 Attendance
 Orientation of the Project
 Orientation of Safety Precautions
Installation of Roof: March 18,2019 – May 17,2019
1. Roof Frame Construction
2. Roof Material Installation
3. Final Inspection
*Routine for each day before work:
 Attendance
 Orientation of the Project
 Orientation of Safety Precautions
Post Construction: May 20,2019 – May 31,2019
1. Site Clearing
2. Turnover