Professional Documents
Culture Documents
CONCRETE
STRUCTURES
Foundations
Instructions for the Members of BIBM, CEMBUREAU, EFCA and ERMCO:
It is the responsibility of the Members (national associations) of BIBM, CEMBUREAU, EFCA and ERMCO
to translate and/or adapt this publication within their national framework, to publish it under their own
name and to disseminate it to their contacts at national level.
Copyright: European Concrete Platform (when legal body is established), March 2007.
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in
any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior written
permission of the European Concrete Platform: BIBM (International Bureau for Precast Concrete);
CEMBUREAU, The European Cement Association; EFCA (European Federation of Concrete Admixtures
Associations); ERMCO (European Ready Mixed Concrete Organisation).
All information in this document is deemed to be accurate by the European Concrete Platform at the time of
going into press. It is given in good faith.
Information on European Concrete Platform document does not create any liability for BIBM, CEMBUREAU,
EFCA and ERMCO. While the goal is to keep this information timely and accurate, the European Concrete
Platform cannot guarantee either. If errors are brought to its attention, they will be corrected.
The opinions reflected in this document are those of the authors and BIBM, CEMBUREAU, EFCA and ERMCO
cannot be held liable for any view expressed therein.
All advice or information from the European Concrete Platform is intended for those who will evaluate the
significance and limitations of its contents and take responsibility for its use and application. No liability (including
for negligence) for any loss resulting from such advice or information is accepted.
Readers should note that all European Concrete Platform publications are subject to revision from time to time
and therefore ensure that they are in possession of the latest version.
How to design concrete structures using Eurocode 2
6. Foundations
Limit states
The following ultimate limit states (ULS) should be satisfied for
geotechnical design; they each have their own combinations of
actions. (For an explanation of Eurocode terminology refer to How
to design concrete structures using Eurocode 2: Introduction to
Eurocodes2).
EQU Loss of equilibrium of the structure.
STR Internal failure or excessive deformation of the structure or
structural member.
GEO Failure due to excessive deformation of the ground.
UPL Loss equilibrium due to uplift by water pressure.
HYD Failure caused by hydraulic gradients.
Geotechnical categories
Eurocode 7 recommends three ‘geotechnical categories’ to assist in
establishing the geotechnical design requirements for a structure
(see Table 1).
Methods of design and combinations values for the partial factors to be applied to the actions
There has not been a consensus amongst for these combinations of partial factors are given in
geotechnical engineers over the application of limit Table 2 and the partial factors for the geotechnical
state principles to geotechnical design. Therefore, to material properties are given in Table 3. Combination 1
allow for these differences of opinion, Eurocode 7 will generally govern the structural resistance, and
provides for three design approaches’ to be used for combination 2 will generally govern the sizing of the
the ULS. The decision on which approach to use for a foundations. The partial factors for soil resistance to
particular country is given in its National Annex. Design sliding and bearing should be taken as 1.0 for both
approach 1(excluding pile and anchorage design) is combinations.
illustrated in this guide. In this approach, there are two
sets of combinations to use for the STR and GEO The partial factors to be applied to the actions at the
ultimate limit states. The EQU limit state are given in Table 4; the geotechnical
material partial factors being the same as for
combination 2 in Table 3.
Pile foundations
For the purpose of this guide it is assumed that the pile
design will be carried out by a specialist piling contractor.
The actions on the piles must be clearly conveyed to the pile
designer, and these should be broken down into the
unfactored (i.e. partial factor = 1.0) values for permanent
action and each of the applicable variable actions (e.g.
imposed and wind actions). The pile designer can then carry
out the structural and geotechnical design of the piles.
where: Note
σgd = the design value of the ground bearing
pressure
fctd = the design concrete tensile strength from
Exp. (3.16)
Deep elements
For deep elements the advice in Eurocode 2 for the side
faces of deep beams may be followed. The distance
between bars should not exceed the lesser of twice the
beam depth or 300 mm. For pile caps the side face may
be unreinforced if there is no risk of tension developing.
References
1 EN 1997: Eurocode 7: Geotechnical design. (2 parts).
2 NARAYANAN, R S & BROOKER, O. How to design concrete structures using Eurocode 2: Introduction to
Eurocodes. The Concrete Centre, 2005.
3 EN 1992–1–1, Eurocode 2: Design of concrete structures. General rules and rules for buildings.
4 MOSS, R M & BROOKER, O. How to design concrete structures using Eurocode 2: Beams.
The Concrete Centre, 2006.
Acknowledgements
This guide was originally published by BCA and The Concrete Centre in the UK. The authors of the original publication
were R Webster CEng, FIStructE and O Brooker BEng, CEng, MICE, MIStructE
2. Text is highlighted in pink indicates that some action is required on the part of the
country adapting the documents for its use