STATUS OF WORKS FOR THE MONTH OF APRIL 2018.UNIT-I
POWER HOUSE
+ All main(21 nos) and auxiliary (25 nos)columns of Power House completed.
> Construction of CW Pit completed.
> Casting of TG deck completed.
> Casting of Generating transformer foundation completed in full shape.
‘Transformer placed in position.
v
Casting of Station Transformer foundation 'completed in full shape.
v
Casting of RCC wall for fire wall is in progress, 2" lift completed.
> RCC for 2nos BFP foundations rafts completed out of 3nos.
v
RCC for Plinth beam 116Rmtr completed out of 155Rmtr.
BOILER
> All columns (34 nos) completed in full shape along with backfilling.
> Left side PA & FD fan Plum concrete completed. Backfilling done to provide
access to crane movement
> RCC for FD & PA fan foundations completed in full shape.
> Bunker Main columns (18 nos) completed. Plum PCC for 6 Mill rafts completed
> All ID duct columns(36 nos) completed in full shape.
ESP
> All columns(100 nos) completed in full shape.
> Casting of 15nos RCC rafts for 1D duct support columns out of 28nos
> Casting of 6nos RCC pedestals bolt lit,12nos 1" lift for ID duct support columns
out of 29,
> Casting of RCC raft completed for ID fan-A & ID fan-B.
> Shuttering for tie beam of ID Fan-A raft is in progress.
> RCC for Gas recirculation foundation is in progress (1* lift completed).v
vvvyvyv
v
UNIT-I
POWER HOUSE
Casting of RCC column pedestals 21 nos completed out of 21nos.
Casting of all Auxiliary column bolt lifts completed full shape.
Casting of TG Deck completed
CW pit completed in full shape. (
Generatin}j transformer foundation completed in full shape. ffrection of generator
is completed.
Casting of RCC walls and stab completed for Oil water pit.
Plum PCC for all 3nos BFP foundations completed.
BOILER
All columns(34 nos) completed in full shape along with backfiling.
Plum concrete (M7.5) completed for all PA and FD fan foundations.
Mill and Bunker raft completed, Casting of RCC columns for bunker completed in
full shape.
Plum PCC for 6 Mill rafts is completed.
AILID duct support columns(36 nos) completed in full shape.
ESP
All columns 100 nos completed in full shape along with backfilling
UNIT-HI
POWER HOUSE
All main(21 nos) and auxiliary (25 nos)columns of Power House completed
CW pit completed in full shape.
Casting of TG Deck completed
Generating transformer foundation completed in full shape along with railing.
Plum PCC for all 3nos BFP foundations completed,
BOILER
All columns (34 nos) completed in full shape along with backfilling
Casting of left side PA&FD fan foundations completed.