Technical Proposal of

Cleaning cooling tower Project


Work period: 5 day operations

Client:
Perrier Vittel (Thailand) LTD

PREPARED BY:
Industrial Cleaning Services Public Company Limited

Office address:
88/8 Warisara 3 Moo 3 Pala , Ban Chang, Rayong 21130, Thailand
Work shop address:
99 Moo 3, Pala District, Ban chang, Rayong 21130, Thailand
Phone: 038 601029 Fax. 038 601030
Phone: 038 601029 Fax. 038 601030
Ref. No. : QO-2015

TECHNICAL PROPOSAL Issued Date: 06_04_2015

Industrial Cleaning Services Co., Ltd. Rev. 0 Page: 2

SECTION 1. Project Information


1.Equipment : Cooling tower
2.Type : Crossflow
3.Product : Cooling water
4.Size : L x W x H = 16 x 5 x 5. Chamber = 4
5.Scope of work : Cleaning of: fan & surrounding, hot water basin & distributor, filler,
cold water basin, sump pit

SECTION 2. Sequence of work

No. Activity Equipment Target


Hiab truck and
1 Mobilization, Lay down and Set up Machine Ready start
Pick up car
2 Ventilation Air ejector Oxygen > 20.9%,

3 Install scaffolding Scaffolding Complete

Visually clean
4 Cleaning of outside filler from top to bottom HP pump 250 bar

Visually clean
5 Cleaning of inside filler from top to bottom HP pump 250 bar

Visually clean
6 Cleaning fan area HP pump 250 bar

Visually clean
7 Cleaning of hot water basin & distributor HP pump 250 bar

Visually clean
8 Cleaning of cold water basin HP pump 250 bar

Visually clean
9 Cleaning of sump pit HP pump 250 bar

Hiab truck and


10 Housekeeping, De-Mobilization Area clear
Pick up car

SECTION 3. Detail Procedure &Drawing Cooling tower


Ref. No. : QO-2015

TECHNICAL PROPOSAL Issued Date: 06_04_2015

Industrial Cleaning Services Co., Ltd. Rev. 0 Page: 3

1. Mobilization, Lay down and Set up


1.1Safety training of all worker
1.2Make sure the cooling tower has been shut down, cut and isolate electricity of the fan
1.3Empty the water inside cooling tower by plant
1.4Mobilization equipment and lay down
1.5Set up equipment follow as drawing above

2. Ventilation
2.1Prepare and install air ejector at the manway
2.2Blow air to start ventilation
2.3Check gas quality inside the cooling tower regularly
Ref. No. : QO-2015

TECHNICAL PROPOSAL Issued Date: 06_04_2015

Industrial Cleaning Services Co., Ltd. Rev. 0 Page: 4

2.4Progress to the next step if Oxygen = 20.9%


3. Install scaffolding
3.1Install Scaffolding inside and outside tower
3.2Inspect the scaffolding before Cleaning.

4. Cleaning of outside filler


4.1Clean outer filler from top to bottom by water jet with spray nozzle

5. Cleaning of inside filler


5.1Clean outer filler from top to bottom by water jet with spray nozzle

6. Cleaning of fan and surrounding

6.1Preparation HPWJ Pump 250 Bar and insert spray nozzles with flexible hose to clean

6.2Clean the fan

6.3Clean structure surround the fan

7. Cleaning of hot water basin and distributor

7.1 Clean the hot water basin and distributor by water jet

8. Cleaning of cold water basin

8.1Remove scaffolding inside the cooling tower

8.2Drain all the waste water in the cold water basin from cleaning activity before toward
sump pit

8.3Clean the cold water basin by high pressure water jet

8.4Drain again the waste water to sump pit

9. Cleaning of sump pit

9.1Drain the waste water to sewer

9.2Final clean the sump pit by high pressure water jet

10. Housekeeping, De-Mobilization equipment


SECTION 4. Equipment and Tool List
- Diaphragm Pump = 1 unit
- Air Compressor (175 CFM) = 1 unit
- High Pressure Pump (250 bar) = 1 unit
- Hose High Pressure ( 1 ½ “ ) = 60 m
- Air Hose ( ¾”) = 30 m
Ref. No. : QO-2015

TECHNICAL PROPOSAL Issued Date: 06_04_2015

Industrial Cleaning Services Co., Ltd. Rev. 0 Page: 5

- Hose ( 3” ) = 30 m
- Scaffolding = 1 set.
- Gas Detector = 1 unit.
- Key & tools Box = 1 lot
- Garbage Bag = 1 lot
- Heap truck ( 5 ton ) = 1 unit
- Air Ejector = 4 ea
- Protection suit, chemical Gloves = 1 lot

SECTION 5. Schedule

SECTION 6. Manpower Loading

Project Manager : 1 person


Supervisor : 1 Person
Worker (confined space) : 8 person
Safety : 1 person

SECTION 7. Organization
Ref. No. : QO-2015

TECHNICAL PROPOSAL Issued Date: 06_04_2015

Industrial Cleaning Services Co., Ltd. Rev. 0 Page: 6

Project Manager
Pitak Phumoolna
Tel : 0827169354

Project Supervisor Safety


Sirichai Faiklang Mr. Komsan Wongngern
Tel : 086-1371776 Tol : 0895448976

Operation Confine
1. Mr. Nuttapong Rongsri
2. Mr. Sompop Yordniltrakarn
3. Mr. Chamrong Saenbut
4. Mr. Jakkrit Nakun
5. Mr. Narong Tongdean
6. Mr. Somwang Seehawong

You might also like