VI.

TIMETABLE/GANTT CHART

The researcher followed the listed activities below in conducting the research.

ACTIVITIES UNDERTAKEN USING GANTT CHART


FROM JULY 2, 2016 UP TO DECEMBER 2, 2016

Activity Duration July Aug. Sept. Oct. Nov. Dec.


1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1. Preparation
of Permit and 15 days
Proposal
2. Submission
of Permit and 15 days
Proposal in
the Division
Office
3. Revision of
the paper 10 days
4.Implementati
on of the paper 60 days
5. Preparation
of the final 10 days
paper
6. Securing for
the Certificate 10 days
of Completion

VII. COST ESTIMATES

In the implementation of the research, the researcher allocated the following expense

items as specified on the table below:

PARTICULARS COST

1. photocopy of interview materials P 50.00


2. coupon bond for output printing P 120.00
3. instructional materials P 1 000.00