CODE (PAP) Procurement Program/Activity/Project User


Construction of PYDO Main Building PYD-Office
Construction of Executive Office PYD-Office
Construction of Multi-Purpose Building PYD-Office
Tiling Works of Lobby and Offices PYD-Office
Constrution of Backdoor and Fire Exit PYD-Office
Construction of Canteen PYD-Office
Procurement of Necessary Items for Lighting PYD-Office
Procurement & Installations of Electrical Materials at PYDO PYD-Office
Procurement of Materials for Tiling and Painting Works PYD-Office
Philippine Youth Developmet- Office
ANNUAL PROCUREMENT PLAN FOR 2019
Procurement Timeline (Schedule)

Pre-Proc Ads/Post of Pre-bid Eligibility Sub/Open Bid


Procurement Method Conference IAEB conference Evaluation of BIds Evaluation
Public bidding 4/23/2019 4/24/2019 5/25/2019 5/26/2019 5/27/2019 5/28/2019
Public bidding 4/23/2019 4/24/2019 5/25/2019 5/26/2019 5/27/2019 5/28/2019
Public bidding 4/23/2019 4/24/2019 5/25/2019 5/26/2019 5/27/2019 5/28/2019
Public bidding 4/23/2019 4/24/2019 5/25/2019 5/26/2019 5/27/2019 5/28/2019
Public bidding 4/23/2019 4/24/2019 5/25/2019 5/26/2019 5/27/2019 5/28/2019
Public bidding 4/23/2019 4/24/2019 5/25/2019 5/26/2019 5/27/2019 5/28/2019
NP-Shopping 6/5/2019 N/A N/A N/A N/A N/A
NP-Shopping 6/5/2019 N/A N/A N/A 7/5/2019 N/A
NP-Shopping 2/23/2019 N/A N/A N/A 3/7/2019 N/A
e (Schedule) Estimated B

Acceptan
Notice of Contract notice to Delivery/C ce/Turnov
Post quali Award sIgning Proceed Ompletion er Source of Funds Total Estimated budget
5/29/2019 7/30/2019 7/31/2019 7/1/2019 1/20/2020 2019 GAA P18,000,000
5/29/2019 7/30/2019 7/31/2019 7/1/2019 1/20/2020 2019 GAA P8,000,000
5/29/2019 7/30/2019 7/31/2019 7/1/2019 1/20/2020 2019 GAA P8,500,000
5/29/2019 7/30/2019 7/31/2019 7/1/2019 1/20/2020 2019 GAA P7,000,000
5/29/2019 7/30/2019 7/31/2019 7/1/2019 1/20/2020 2019 GAA P1,500,000
5/29/2019 7/30/2019 7/31/2019 7/1/2019 1/20/2020 2019 GAA P2,000,000
N/A 6/27/2019 6/30/2018 2019 GAA P50,000
N/A 7/30/209 7/30/209 2020 GAA P53,000
N/A 3/30/2019 3/30/2019 2021 GAA P200,000
Estimated Budget

Remarks (brief description of


MOOE Capital outlay Program/Project)
P18,000,000 Infrastraucture Project
P8,000,000 Infrastraucture Project
P8,500,000 Infrastraucture Project
P7,000,000 Infrastraucture Project
P1,500,000 Infrastraucture Project
P2,000,000 Infrastraucture Project
P50,000 Purchase of Materials/ Facilities Improvements
P53,000 Purchase of Materials/ Facilities Improvements
P200,000 Purchase of Materials/ Facilities Improvements