PLANNED MAINTENANCE
SYSTEM MANUAL
DOCUMENT STATUS:
CONTROLLED
COPY
COPY NO:
02
© 2017 Regulus Offshore Sdn Bhd (951778-A)
This document is the property of Regulus Offshore Sdn. Bhd. and may contain confidential and proprietary information. It may not be used for any purpose
other than that for which it is supplied. This document may not be wholly or partly disclosed, copied, duplicated or any way made use of without prior
written approval of Regulus Offshore Sdn. Bhd.
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: ‘01
PLANNED MAINTENANCE SYSTEM MANUAL REVISION STATUS
Guidance to Interpretation of
ROSB-PMS-P08 02 1-Nov-17 Technical Manager DPA MD
Vessel Certificates
DP Equipment Maintenance
ROSB-PMS-P09 02 1-Nov-17 Technical Manager DPA MD
Programs
THIS IS A CONTROLLED DOCUMENT. VERIFY THAT THIS IS THE CURRENT VERSION BEFORE USE.
The issue date & revision number of this document is printed at the header box except the cover page. Revisions to this document
shall be issued, as necessary by Regulus Offshore Document Control Department, any corrections or revisions considered
necessary shall be submitted to HQ for authorisation, via the DPA.
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
PLANNED MAINTENANCE SYSTEM MANUAL REVISION HISTORY
Rev. Effective
Document No. Document Title Description of Change
No Date
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
TABLE OF CONTENTS
TABLE OF CONTENTS
SECTION 1 INTRODUCTION TO DECK PMS (ROSB-PMS-P01) ............................................................. 1-1
SECTION 2 DECK DEPARTMENT GUIDELINES (ROSB-PMS-P02) ....................................................... 2-1
SECTION 3 FIRE FIGHTING AND SAFETY (ROSB-PMS-P03) ................................................................ 3-1
SECTION 4 DECK EQUIPMENT (ROSB-PMS-P04) .................................................................................. 4-1
SECTION 5 HULL (ROSB-PMS-P05) ......................................................................................................... 5-1
SECTION 6 NAVIGATION EQUIPMENT (ROSB-PMS-P06) ..................................................................... 6-1
SECTION 7 COMMUNICATION EQUIPMENT (ROSB-PMS-P07)............................................................. 7-1
SECTION 8 GUIDANCE TO INTERPRETATION OF VESSEL’S CERTIFICATES (ROSB-PMS-P08) .... 8-1
SECTION 9 DP EQUIPMENT MAINTENANCE PROGRAM (ROSB-PMS-P09) ....................................... 9-1
SECTION 10 INTRODUCTION TO ENGINE ROOM PMS (ROSB-PMS-P10) ........................................... 10-1
SECTION 11 ENGINE ROOM DEPARTMENT GUIDELINES (ROSB-PMS-P11) ..................................... 11-1
SECTION 12 MAIN PROPULSION (ROSB-PMS-P12) .............................................................................. 12-1
SECTION 13 AUXILIARY DIESEL ENGINE (ROSB-PMS-P13) ................................................................ 13-1
SECTION 14 AUXILIARY MACHINERY (ROSB-PMS-P14) ...................................................................... 14-1
SECTION 15 ELECTRICAL SYSTEM (ROSB-PMS-P15) .......................................................................... 15-1
SECTION 16 FIRE FIGHTING AND SAFETY (ROSB-PMS-P16) .............................................................. 16-1
SECTION 17 DECK MACHINERY (ROSB-PMS-P17)................................................................................ 17-1
SECTION 18 HULL (ROSB-PMS-P18) ....................................................................................................... 18-1
SECTION 19 MISCELLENEOUS (ROSB-PMS-M19) ................................................................................. 19-1
DISCLAIMER
This document has been prepared and authorised for use in Regulus Offshore Sdn. Bhd., where relevant. Regulus Offshore make
no warranties to any other party as to the accuracy, validity, or fitness for use or application of the contents of this document.
Regulus Offshore reserves the right to revise the information in this document at any time without notice.
TABLE OF CONTENTS
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 1: INTRODUCTION (ROSB-PMS-P01)
This served as a controlled reference manual that supplements the Shipboard Operation Manual Document
No. ROSB-SOM-P35: Planned Maintenance System (PMS).
The Deck planned maintenance must be carried out in accordance to the Shipboard Operation Manual
Document No. ROSB-SOM-P34: Planned Maintenance System (PMS) and its attached PMS forms,
especially the Deck Servicing Plan (Form: DSP).
Any equipment and/or instructions written in this manual but NOT shown in the Deck Servicing Plan are NOT
applicable to the PMS.
In instances of any discrepancies between the Deck Servicing Plan and the contents of this manual, the
former shall prevail.
Thus the main function of this manual is only to allow the vessel’s Master or anyone who is carrying out the
Deck planned maintenance, to have easy access to a set of general task instructions.
It must however be stressed that the task instructions contained in this manual serve only as general
guidelines. The person carrying out the planned maintenance MUST refer to the manufacturers’ manuals or
brochures for detailed instructions.
When in doubt, please contact the Technical Manager for assistance.
Section 1-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 2: DECK DEPARTMENT GUIDELINES (ROSB-PMS-P02)
Section 2-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 3: FIRE FIGHTING AND SAFETY (ROSB-PMS-P03)
A. CO2 EXTINGUISHER
(1) Safety pin check in place with attached chain/lanyard.
(2) Check that weight is correct.
(3) To lubricate trigger hinge.
Section 3-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 3: FIRE FIGHTING AND SAFETY (ROSB-PMS-P03)
C. FOAM EXTINGUISHER
(1) To check cap in place with attached lanyard
(2) Open cover and check that inner cylinder seal is not broken, change if need to.
(3) Test mixture of the two liquids that foam can be formed with a few drop of each.
(4) Change mixture if necessary.
B. SAFETY LAMP
(1) Check lamp battery to ensure no leakages.
(2) Ensure battery are fully charge.
(3) Test lamp and observe luminous intensity.
C. B.A. SET
(1) Check face mask, air hose, air regulator for deterioration, leaks and damage.
(2) Test how air pressure alarm and ensure they are working.
(3) Check air bottles for corrosion and damage.
(4) Ensure air bottles are fully charged and all valves are free to operate. Emptied bottle to be marked and
re-charge at the earliest opportunity.
NOTES:-
All vessels above 500 GRT are to have minimum TWO complete sets of fireman’s outfit and
breathing apparatus.
Section 3-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 3: FIRE FIGHTING AND SAFETY (ROSB-PMS-P03)
EQUIPMENT NO.: 5515 - FIRE LINE, HOSES, NOZZLES, HYDRANTS AND INTERNATIONAL SHORE
CONNECTION
A. FIRE LINE
(1) Check all fire line for corrosion and leaks.
(2) Ensure all fire line are painted RED.
B. FIRE HOSE
(1) Check all hoses for deterioration.
(2) Ensure all couplings are not damage and rubber seals are in good condition.
(3) Check and ensure all fire boxes to have hose.
NOTES:-
All fire hoses to be flushed clean with fresh water and dry after each fire drill before storing.
C. NOZZLE
(1) Check all nozzles and ensure they are dual-purpose type (i.e. not jet and spray) incorporating a shut-
off.
(2) Ensure all nozzles are free to operate from jet to spray.
D. FIRE HYDRANTS
(1) Check all hydrants valves and ensure they are free to operate.
(2) Check and ensure all rubber seals and locking mechanism are in operational condition.
NOTES:-
All vessels above 500 GRT are to have minimum ONE International Shore Connection.
Section 3-3
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 3: FIRE FIGHTING AND SAFETY (ROSB-PMS-P03)
NOTES:-
Wire to turn end to end at an interval of not more than 30 months and to renew when necessary at
an interval of not more than 5 years.
Section 3-4
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 3: FIRE FIGHTING AND SAFETY (ROSB-PMS-P03)
v) Check wire for any damages and lubricate where necessary. Ensure end termination and lifting
hook in satisfactory condition
vi) Winch is free to move in both directions.
vii) Ensure no obstructions in way of launching area.
Section 3-5
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 3: FIRE FIGHTING AND SAFETY (ROSB-PMS-P03)
Section 3-6
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 4: DECK EQUIPMENT (ROSB-PMS-P04)
B. WIRE
(1) As far as practicable, the wire to be examined for surface wear, broken strands, corrosion, kinks
and bird caging.
(2) Examine all sockets, socket fastener for cracks, deformation and mechanical damage.
(3) Lubricate wire if necessary.
C. CHAIN
(1) As far as practicable, the chain to be examined for wear, missing or loose studs and
deformation.
(2) Examine connecting link for slack or corroded taper locking pins.
(3) To check and ensure swivels are free.
Section 4-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 4: DECK EQUIPMENT (ROSB-PMS-P04)
NOTES:-
It is recommended that the chain and connecting link be inspected for wear every time the
anchor is weighed.
NOTES:-
No welding is allowed to be carried out by unauthorised personnel on crane structure.
Section 4-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 4: DECK EQUIPMENT (ROSB-PMS-P04)
C. WATERTIGHT DOOR
(1) Grease all dogs and hinges and ensure they are free.
(2) Check and ensure rubber lining are not damaged and painted.
(3) Close door to carry out chalk test.
NOTES:-
All watertight doors opening to decks shall have instruction printed on it 'CLOSE AT SEA'
D. HATCH COVER
(1) Grease all toggle bolts. Ensure hinges and wing nuts are free. No painting on toggle bolts is
allowed.
(2) Check all rubber lining, ensure they are not damaged and painted.
(3) Check edges of coaming for corrosion.
E. PORTHOLE
(1) Check dead light to ensure they are free.
(2) Check glass for crack and damage.
(3) Check rubber lining/"O"-ring for deterioration.
(4) Check toggle bolts and nut to ensure they are free. Carry out light greasing if necessary.
NOTES:-
No aerial for portable radio is allowed to pass through porthole.
F. SKYLIGHT
(1) Check dead light to ensure they are free.
(2) Check glass for crack and damage.
(3) Check all hinges, toggle bolts to ensure they are free. Carry out light greasing if necessary.
(4) Close and carry out chalk test.
G. CHAIN LOCKER
(1) Check pump or eductor are operational.
(2) Ensure that it is dry and clean, if possible.
Section 4-3
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 4: DECK EQUIPMENT (ROSB-PMS-P04)
NOTES:-
(a) No direct painting or marking to be done on the rope themselves. All marking to be on a
tag attached to the eye of the rope.
(b) Ropes must be stored on pallets and coil properly when not in use and put under cover
or in stores if not in use for a period of time.
DELTA PLATE
(1) Examine plate for crack and deformation.
(2) Check pinhole for wear.
(3) Oil/grease surface for prevention of corrosion.
Section 4-4
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 4: DECK EQUIPMENT (ROSB-PMS-P04)
Section 4-5
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 5: HULL (ROSB-PMS-P05)
The Master or Officer assigned to carry out the Hull examination should use the rescue boat/work
boat working down along the shipside or from the jetty if the vessel is alongside. During
examination, it is recommended to keep the vessel as light as possible.
(1) To check if any sharp indentation of side shell plating. If found, to be further examined for cracks
and puncture.
(3) To check all overboard discharge pipes, their shell reinforcement ring and external shell plating
beneath the outlets for corrosion.
(4) To check stern plating or the stern bar especially the wind and water area for damage.
EQUIPMENT NO.: 7510 - SUPERSTRUCTURE DECK HOUSE, DECK PLATING AND DECK SHEATING
(1) Examine all plating and sheating for cracks and damage.
(4) If the deck sheating damaged or uneven surface, crew will apply cement on the damaged part to
avoid any crew members trip or fall during operation.
Section 5-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 5: HULL (ROSB-PMS-P05)
The crew members assigned by the Master to inspect Tanks and Void Spaces shall check for the
following condition and clean the tanks where necessary:-
1) Tank Structure :-
a. any cracks at tank corners, edges and at termination of frames, beams, stiffeners, etc
b. bends or buckling of bulkheads, frames, beam knees, brackets or other members
2) Dents:-
a. dents in bulkheads or plates, note the area and depth involved especially for dents which are
deep but cover a small area and likely to cause cracks or leaks
3) Leaks:-
a. heavy corrosion or pitted rust and cracks that can cause leaks.
b. Streaks of stain on the plates indicate the existence of leaks
4) Pipes condition, if any pipes pass through tank or void space:-
a. general condition of the pipe, rust, leaks and bends especially where the pipe passes through
bulkheads or other members.
5) Tank Coating and Rust condition:-
a. condition of tank coating, including coating thickness and areas where coating is still intact.
b. condition of steel due to rust and scales
6) General Cleanliness:-
a. accumulation of dirt, mud, rust scales, etc.
b. clean up where necessary
Section 5-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 6: NAVIGATION EQUIPMENT (ROSB-PMS-P06)
Section 6-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 6: NAVIGATION EQUIPMENT (ROSB-PMS-P06)
Section 6-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 7: COMMUNICATION EQUIPMENT (ROSB-PMS-P07)
Section 7-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 7: COMMUNICATION EQUIPMENT (ROSB-PMS-P07)
(3) Check if there is any damage on flexible antenna and VHF casing.
(4) Transmission test and observe signal strength.
Section 7-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 8: GUIDANCE TO INTERPRETATION OF VESSEL’S CERTIFICATES (ROSB-PMS-P08)
(BB) Certificates that are issued by the approved Classification Society as follows:-
1. International Load line Certificate (1966)
2. Cargo Ship Safety Construction Certificate
3. Cargo Ship Safety Equipment Certificate
4. Cargo Ship Safety Radio Certificate
5. International Oil Pollution Prevention (IOPP) Certificate
6. International Tonnage Certificate (1969)
SECTION (AA)
1. Ship's Registry
This document is issued by flag administration and indicate the particulars of Owners, vessel and
vessel's identification.
It does not have expiry date but it will cease to be valid once there is a change of ownership.
3. Exemption Certificate
As to case to case basis, flag administration may consider issuing Exemption Certificate for the
vessel. Exemption like;
1. Exempted from carrying immersion suit and TPA
2. Exempted from carrying a Class 5 Officer
3. Exempted from one trip voyage for reduced manning
Section 8-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 8: GUIDANCE TO INTERPRETATION OF VESSEL’S CERTIFICATES (ROSB-PMS-P08)
SECTION (BB)
1. International Load line Certificate (1966)
This certificate checks on the water tightness of all openings, the load and draft markings of the
vessel.
Validity is for 5 years from the date of initial survey and may extended up to 5 months after the
expiring date only for the purpose of allowing the vessel to complete its voyage.
Mandatory periodic survey is to be carried out annually and shall be held not before 3 months prior
to, nor later than 3 months after the annual date of the certificate.
Section 8-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 8: GUIDANCE TO INTERPRETATION OF VESSEL’S CERTIFICATES (ROSB-PMS-P08)
SECTION (CC)
1. Deratting Certificate or Deratting Exemption Certificate
This certificate is issued by the Ministry of Environment to check that the vessel is free from
infectious disease.
Deratting Exemption Certificate is issued when after inspection by Port Health Officer without
fumigation, a Deratting Certificate is issued instead.
This certificate is valid for a period of (6) six months from date of issue.
Section 8-3
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 9: DP EQUIPMENT MAINTENANCE PROGRAM (ROSB-PMS-P09)
Equipment No.: 9210 – Position reference system (Cy scan, DGPS, Taut Wire, HPR)
1. To check all mounting bolts/ nuts are properly connected.
2. To check and ensure all cable, connectors are properly connected.
3. To check and ensure signal strength are normal.
4. To check beacon battery validity, if applicable.
5. To check sign of overheating and any abnormal noise of rotating/ moving part.
Equipment No.: 9220 – Position reference sensor (Wind sensor, VRU, Gyros)
1. To check all mounting bolts/ nuts are properly connected.
2. To check and ensure all cable, connectors are properly connected.
3. To check and ensure signal is available and signal strength is normal.
Section 9-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 10: INTRODUCTION TO ENGINE ROOM PMS (ROSB-PMS-P10)
This served as a controlled reference manual that supplement the Shipboard Operation Manual Document
No. ROSB-SOM-P35: Planned Maintenance System (PMS).
The Engine Room planned maintenance must be carried out in accordance to the Shipboard Operation
Manual Document No. ROSB-SOM-P35: Planned Maintenance System (PMS) and its attached PMS forms,
especially the Engine Room Servicing Plan (Form: ESP).
Any equipment and/or instructions written in this manual but NOT shown in the Engine Room Servicing Plan
are NOT applicable to the PMS.
In instances of any discrepancies between the Engine Room Servicing Plan and the contents of this manual,
the former shall prevail.
Thus the main function of this manual is only to allow the vessel’s Chief Engineer or anyone who is carrying
out the Engine Room planned maintenance, to have easy access to a set of general task instructions.
It must however be stressed that the task instructions contained in this manual serve only as general
guidelines. Whenever necessary for the benefits of better maintenance the person carrying out the task
MUST refer to the manufacturers’ manuals for detailed instructions.
When in doubt, please contact the Technical Superintendent (TS) for assistance.
Section 10-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 11: ENGINE ROOM DEPARTMENT GUIDELINES (ROSB-PMS-P11)
The description in the “Period” serves only as a guideline for the maintenance interval. The user MUST carry
out the planned maintenance according to the interval specified in the Engine Room Servicing Plan.
Section 11-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
Section 12-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
Section 12-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
Section 12-3
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
Section 12-4
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
Section 12-5
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
Section 12-6
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
Section 12-7
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
MOTOR
(5) Check wire terminal and gland tightness.
(6) Clean fan impeller and protective guard.
(7) Clean motor casing cooling fins.
(8) Check starter panel wire terminal for tightness. Vacuum clean starter panel.
WARNING
Main breaker to the assigned equipment to be in "OFF" position. Tape breaker, and display sign board.
MOTOR
(4) Check wire terminal and gland tightness.
(5) Clean fan impeller and protective guard ventilation passage.
(6) Clean motor casing cooling fins.
(7) Check starter wire terminal for tightness. Vacuum clean starter panel.
WARNING
Main breaker to the assigned equipment to be in "OFF" position. Tape breaker, and display sign board.
Section 12-8
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 12: MAIN PROPULSION (ROSB-PMS-P12)
MOTOR
(1) Check wire gland tightness.
(2) Check damage of motor and protective guard.
Section 12-9
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 13: AUXILIARY DIESEL ENGINE(ROSB-PMS-P13)
Section 13-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 13: AUXILIARY DIESEL ENGINE(ROSB-PMS-P13)
Section 13-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 13: AUXILIARY DIESEL ENGINE(ROSB-PMS-P13)
Section 13-3
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 13: AUXILIARY DIESEL ENGINE(ROSB-PMS-P13)
Section 13-4
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 13: AUXILIARY DIESEL ENGINE(ROSB-PMS-P13)
(2) Check starting valves air pipes for sign of overheating. This indicate valves are leaking.
(3) Lubricate air distributor.
EQUIPMENT NO.: 2081/2281/2482 - BATTERY STARTING SYSTEM
(1) Check battery electrolyte specific gravity.
(2) Top up with distilled water if necessary.
(3) Check tightness of battery terminal.
(4) Ensure battery cleanliness.
(5) Check condition and tension of charging alternator fan belts; DO NOT do not over-tighten fan belt.
(6) Check wire connection to starter.
MOTOR
(5) Check wire terminal and gland tightness.
(6) Clean fan impeller and protective guard ventilation passage.
(7) Clean motor casing cooling fins.
(8) Check starter wire terminal for tightness and contactor for arcing. Vacuum clean starter panel.
WARNING
Section 13-5
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 13: AUXILIARY DIESEL ENGINE(ROSB-PMS-P13)
Main breaker to the assigned equipment to be in “OFF” position. Tape breaker and display sign board.
Section 13-6
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 14: AUXILIARY MACHINERY (ROSB-PMS-P14)
Section 14-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 14: AUXILIARY MACHINERY (ROSB-PMS-P14)
MOTOR
(1) Check wire terminal and gland tightness.
(2) Clean fan impeller and protective guard ventilation passage.
(3) Check starter wire terminal for tightness and contractor for arcing. Vacuum clean starter panel.
WARNING:-
Main breaker to the assigned equipment to be in "OFF" position. Tape breaker and display
sign board.
MOTOR
(5) Check wire terminal and gland tightness.
(6) Clean fan impeller and protective guard ventilation passage.
(7) Check starter panel wire terminal for tightness and contractors for arcing. Vacuum clean starter
panel.
WARNING
Main breaker to the assigned equipment to be in "OFF" position. Tape breaker and display
sign board.
Section 14-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 14: AUXILIARY MACHINERY (ROSB-PMS-P14)
MOTOR
(1) Check wire terminal and gland tightness.
(2) Clean fan impeller and protective guard ventilation passage.
(3) Clean motor cooling fins
(4) Check starter panel wire terminal for tightness and contractors for arcing. Vacuum clean starter
panel.
(5) Test no voltage alarm.
WARNING:-
Main breaker to the assigned equipment to be in "OFF" position. Tape breaker, and display
sign board.
Section 14-3
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 14: AUXILIARY MACHINERY (ROSB-PMS-P14)
(2) Ensure no internal leakage of non-return valve. This will affect constant cutting in and out of
pressure set.
(3) Check pumps for noise and vibration during operation.
(4) Check all sealing arrangement.
MOTOR
(1) Check wire terminal and gland tightness.
(2) Clean fan impeller and ventilation passage.
(3) Clean motor casing cooling fins.
(4) Check starter wiring and terminal for sign of overheating. Tightness all loose terminals.
WARNING:-
Main breaker for assigned equipment to be in "OFF" position. Tape breaker and display.
MOTOR
(1) Check wire terminal and gland tightness.
(2) Clean fan impeller and ventilation passage.
(3) Clean motor casing cooling fins.
(4) Check starter wiring and terminal for sign of overheating. Tightness all loose terminals. Vacuum
clean starter box.
WARNING
Main breaker for assigned equipment to be in “off’ position. Tape breaker and display sign
board.
Section 14-4
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 14: AUXILIARY MACHINERY (ROSB-PMS-P14)
B. C.P.P. THRUSTER
(1) Check header tank and hydraulic oil level.
(2) Check oil condition.
(3) Check all hydraulic pipes and hose connection.
(4) Check hydraulic pump coupling, noise, vibration during operation.
(5) Check local and remote pitch indicator, ensure they are coincide.
C. PRIME MOVER (MOTOR DRIVEN)
(1) Check all wire terminal and ensure tightness.
(2) Check contactors and terminals for de coloration and oxidation in the vicinity of the joint indicating
overheating.
(3) Clean all ventilation passage.
(4) Test run and record current loading from ampere meter.
Section 14-5
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 14: AUXILIARY MACHINERY (ROSB-PMS-P14)
MOTOR
(1) Check all wire terminal and ensure tightness.
(2) Check conductor and termination for de coloration and oxidation.
(3) Clean all ventilation passage.
(4) Vacuum clean starter panel.
(5) Test run and record current loading.
WARNING:-
Main breaker to the assigned equipment to be in off position. Tape breaker and display sign
board.
Section 14-6
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 14: AUXILIARY MACHINERY (ROSB-PMS-P14)
Section 14-7
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 15: ELECTRICAL SYSTEM (ROSB-PMS-P15)
Section 15-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 15: ELECTRICAL SYSTEM (ROSB-PMS-P15)
Section 15-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 16: FIRE FIGHTING AND SAFETY (ROSB-PMS-P16)
MOTOR
(1) Check wire connection and gland tightness.
(2) Check motor overheating and abnormal noise.
(3) Ensure all covers and cable entries are water-tight.
Section 16-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 16: FIRE FIGHTING AND SAFETY (ROSB-PMS-P16)
EQUIPMENT NO.: 5030 - FIRE MONITOR PUMP CLUTCH AND GEAR BOX
A. CLUTCH
(1) Check free engagement of clutch on remote and local control.
(2) Check clutch control air system to ensure no leaks.
(3) Check all regulating valves and adjust pressure accordingly.
B. GEAR BOX
(1) Open inspection cover.
(2) Check gear tooth for pitting, breakage.
(3) Check bearing slackness and creeping in bearing housing.
(4) Check oil spray and ensure they are not choked.
Section 16-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 16: FIRE FIGHTING AND SAFETY (ROSB-PMS-P16)
WARNING
Advance warning to be given to the crew on board before commence testing.
Section 16-3
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 16: FIRE FIGHTING AND SAFETY (ROSB-PMS-P16)
B. AIR OPERATED
(1) Check air reservoir pressure, drain dry all water.
(2) Check all piping connection.
(3) Function test of all valves.
(4) Re-charge air reservoir.
C. HYDRAULIC OPERATED
(1) Check all hydraulic piping.
(2) Check oil level of tank.
(3) Lubricate all control valves.
(4) Function test of all valves.
Section 16-4
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 17: DECK MACHINERY (ROSB-PMS-P17)
MOTOR
(1) Check wire terminals and glands tightness.
(2) Clean fan impeller and protective guard ventilation passage.
(3) Clean motor casing cooling fans.
(4) Check starter panel wiring terminals for tightness. Observe any sign of overheating or discoloration.
WARNING:-
Main breaker to the assigned equipment to be in "OFF" position. Tape breaker and display
signboard.
Section 17-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 17: DECK MACHINERY (ROSB-PMS-P17)
Note:-
To freshwater wash and grease after every anchor handling job.
Section 17-2
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 18: HULL (ROSB-PMS-P18)
Section 18-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 19: MISCELLENEOUS (ROSB-PMS-P19)
NOTE:-
Ensure that during hosing down or cleaning operation, no water is allowed to settle on
electrical machinery. The compartment should look clean and tidy after this operation.
This is one of the criteria that indicate the performance of the Chief Engineer and his
subordinates.
Section 19-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 20: APPENDICES (ROSB-PMS-P20)
VESSEL :
PORT :
DATE :
2 STARBOARD 6-MONTHLY
Section 20-1
CONTROLLED COPY 02
INTEGRATED MANAGEMENT SYSTEM (IMS)
Document Title: Planned Maintenance System Manual (PMS) Document No: ROSB-PMS
Issue Date: 1 NOV 2017 Revision No.: 02
Section 20: APPENDICES (ROSB-PMS-P20)
VESSEL :
PORT :
DATE :
EQUIPMENT EQUIPMENT
LUB OIL TYPE OF DATE OF DATE OF SAMPLE ANALYSIS
S/No. NAME OF EQUIPMENT MAKE & RUNNING REMARKS
RUNNING HRS L.O SAMPLE TAKEN SEND ASHORE INTERVALS
MODEL HRS
1 MAIN ENGINE (P) 6 MONTHLY
2 MAIN ENGINE (S) 6 MONTHLY
3 NO. 1 AUX ENGINE 6 MONTHLY
4 NO. 2 AUX ENGINE 6 MONTHLY
5 NO. 3 AUX ENGINE 6 MONTHLY
6 NO. 4 AUX ENGINE 6 MONTHLY
7 EMERGENCY GENERATOR 12 MONTHLY
8 STEERING (P) 6 MONTHLY
9 STEERING (S) 6 MONTHLY
10 STERNTUBE (P) 6 MONTHLY
11 STERNTUBE (S) 6 MONTHLY
12 CPP (P) 6 MONTHLY
13 CPP (S) 6 MONTHLY
14 FiFi GEARBOX (P) 12 MONTHLY
15 FiFi GEARBOX (S) 12 MONTHLY
16 NO.1 BOW THRUSTER 12 MONTHLY
17 NO.2 BOW THRUSTER 12 MONTHLY
18 STERN THRUSTER 12 MONTHLY
19 AZIMUTH THRUSTER 12 MONTHLY
20 DECK MACHINERY 12 MONTHLY
CHIEF ENGINEER NAME & INITIAL: _________________________
Section 20-2
CONTROLLED COPY 02