You are on page 1of 4

C A S E S T U D I E S O N A P P LY I N G B E S T P R AC T I C E TO I N - S I T U CO N C R E TE F R A M E B U I L D I N G S

St George Wharf Case Study Slab deflections

Deflections (mm), dead load case 1

6=
5=
4=
Introduction 3=
2=
The European Concrete Building Project
at Cardington was a joint initiative aimed 1=
at improving the performance of the 0=
concrete frame industry. It led to the
preparation of a series of Best Practice
Guides, giving recommendations for
Figure 1: Lusas deflection prediction output for a prow end of St George Wharf
improving the process of constructing in-
situ concrete frame buildings.

In most cases adequate control of deflections may be achieved by


complying with specified span/depth ratios. However there are
some situations where they should be calculated in order to comply
with tolerances concerning cladding and partitions.

Key Points
As part of a programme to disseminate This Case Study discusses experiences of predicting and measuring
and apply what has been learnt from
Cardington, BRE has subsequently actual deflections in reinforced concrete flat slabs.
worked directly with those involved in • Prediction of deflections in two-way spanning systems is not straightforward
St George Wharf, a high-profile, 100,000 m2
mixed-use phased development on the
and deflections may not be easy to calculate without computer aided analysis.
River Thames. • Deflections and the times at which they occur should be considered in
BRE worked jointly with the developers, conjunction with the limits associated with them. In general, deflections need
St George (South London), their to be considered both before and after installation of cladding and partitions.
engineers, White Young Green,
and specialist concrete contractors, • Early age construction loading can have a significant impact on deflections as
Stephenson, to develop and implement a result of induced cracking. Appropriate modelling of cracking behaviour is
process improvements tailored to the therefore essential if realistic deflections are to be predicted.
St George Wharf site.
• The sensitivity of the predicted deflections to the assumptions made,
This work has led to a series of
particularly the tensile strength of the concrete, should be assessed and the
innovations being trialled, the results of
which are summarised in this series of likely error bounds determined. Past experience suggests typical error
Best Practice Case Studies. bounds for deflection calculated to be +0/–30% arising from conservative
assumptions about material properties.

www.cementindustry.co.uk www.stephenson-ssc.co.uk www.wyg.com www.bre.com www.dti.gov.uk www.construct.org.uk www.stgeorgeplc.com www.concretecentre.com

1
10
Introduction c 1st slab above cast
 9
d 2nd slab above cast
Adequate control of deflections can
usually be achieved for in-situ reinforced
8 e
concrete beams and slabs by compliance

Theoretical load (kN/M2)


with specified span/depth ratios.  7
However, as flat slab structures become a
b f
more slender, serviceability is increasingly  6
governing their design. This publication is  5
concerned with situations where
Slab struck 3rd slab above cast
prediction of deflections is considered  4
desirable or is a specific requirement.
 3
As for many similar developments, the
specific issues in relation to deflections  2
for the St George Wharf development
 1
were:
 0
• The influence of deflections on internal 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150
partitions and the required allowance
for these. Time from casting (days)

• The tolerances on the precast cladding Figure 2: Typical load history for slabs at St George Wharf
fixed around the perimeter of the
structure.
A further issue, which is becoming 25 KEY
increasingly important, is the influence of
early age loading, as there is a desire to Floor 3
speed up the floor cycle. In-situ reinforced 20 (measured)
concrete structures can be subject to
significant loads during construction. Floor 4
(measured)
This results from the need to support 15
Deflection (mm)

freshly cast slabs above those already


Predicted
constructed, and for the construction to (fct=3 N/mm2
support its self-weight when struck. In
many cases, construction loads from 10
Predicted
casting the slab above will be greater (uncracked)
than service loads and will govern long-
term slab deflections.  5

Since precast cladding is normally


manufactured to fixed dimensions, it
is generally the deflection of the slab  0
relative to the supports around the   0 50 100 150
perimeter, both before and after Time (days)
installation, that is of particular interest.
Figure 3: Maximum deflections at St George Wharf
In contrast, with internal partitions, it is
generally the deflections subsequent to
their installation which are of most
interest because the internal partitions
can be adjusted to fit the dimensions at strength at the time of loading. Ideally, Construction loading
the time of installation. Since partitions designers need to consider both the Figure 2 shows a typical load history for
can in theory be installed in any location influence of the likely tensile strength of the slabs at St George Wharf. Here the
at any stage after construction it is the concrete at key stages in the forces in the two levels of backprops used
prudent to calculate deflections for this construction process and the influence of were measured. It can be seen that the
purpose at the positions where maximum the load history on creep. slab carried its self-weight when struck
deflections are likely to occur (i.e. at the and the peak load occurred when the slab
Curvature in reinforced concrete flat slabs
centre of a bay). A worst-case load above was cast. For load histories similar
in flexure lies between that of an
history should be assumed, which could
uncracked and a fully cracked section. In to that in Figure 2, the theoretical peak
involve less early age loading so that
practice some cracking will be anticipated construction load is given by:
greater deflection occurs at a later stage.
in flat slabs and this will vary, depending wpeak = wself + wform + c(wself +wcon) . . . . 1
The load history of the slab cannot be on the location and load history. For this
predicted precisely but, in practice, reason the most thorough approaches Where
reasonable assumptions may be made, involve integrating curvatures at different wpeak = peak construction load
based on likely construction sequence positions in different directions across
and accepted values for additional wself = self weight of slab e.g. 6 kN/m2
the slab, based on predicted levels of
construction loads. The magnitude of for a 250 mm thick slab
cracking. In practice an iterative process
deflections depends on both the level may be required to arrive at the extent of wform = weight of formwork (a value of
and duration of loading and concrete cracking at a particular location. 0.5 kN/m2 is normally taken).
2
c is a carry through factor of at least shrinkage. The effect of creep can be Where wself is the self-weight of the slab
1/(number of supporting floors) taken into account in deflection only. More accurate estimates of
calculations using deflection can be obtained using cracked
wcon is a construction load comprising
a method known as the effective modulus section analysis, which can be carried out
formwork etc. (a value between 0.75 and
method: an effective concrete elastic on a number of commercially available
1.5 kN/m2 is reasonable)
modulus Ecomposite can be used to finite element packages.
This applies to situations where: account for the different ages at which
• The most recently cast slab carries its loads are applied and their duration. Prediction of deflections at
self-weight after striking; Ecomposite =wi/wi/Eceffi) . . . . . . . . . 2 St George Wharf
• Flying form systems are used so that Where Deflections were predicted initially at
the formwork load is applied before any St George Wharf using various methods
backpropping is installed; but, Eceffi = Ec/(1+i)
based on finite element analysis [4].
• Backpropping is installed prior to any i denotes the load increment. The designer, White Young Green, used
other significant construction loads. For flat slabs subjected to a construction Lusas Finite Element software to carry
load history similar to that in Figure 2, out an elastic analysis to estimate slab
Based on measurements in prop forces at
Cardington and assuming little significant Vollum [4] has shown that the combined deflections (an example is illustrated in
pre-load, Beeby [1] showed that the peak effect of cracking and shrinkage Figure 1). The elastic modulus was reduced
construction load occurred in the top slab increases deflections in flat slabs to account for creep but no reduction was
of the supporting assembly when the by a factor of around 2. made for cracking. Consequently, the
slab above was cast. Beeby’s work shows The superposition of creep coefficients to predicted deflections were significantly
that it is conservative to take c as 0.7 obtain overall creep effects can become less than those measured in the structure.
provided there is at least one level of quite complicated. For load histories Deflections were also predicted at stages
backpropping. The value of c will be similar to those shown in Figure 2, a a to f in Figure 2 using a non-linear finite
lower if the backprops are preloaded but conservative approach is to use a element programme developed at
it is difficult to be sure of the amount of reduced elastic modulus to account for Imperial College. This is shown in Figure 3.
preload achieved in practice. the effects of creep, shrinkage and The effect of construction loading was
There are some other interesting points cracking combined. The corresponding included in the analysis.
to note in Figure 2. The first is the reduced elastic moduli are virtually
duration for which the peak loads have independent of slab thickness. For a Measurements of construction
been sustained. The second is the effect typical 250 mm slab the reduced elastic loading and deflection
of preload in the backprops. Preloading moduli are:
An extensive programme of deflection
has reduced the initial peak construction 4.1 kN/mm2 for a concrete cylinder/cube measurements was undertaken. The
load when constructing the slab directly strength of C30/37
above, and because two levels of deflections were measured using simple
backpropping were used, the theoretical 5.1 kN/mm2 for a strength of C40/50 levelling equipment, which worked well
peak load when constructing the third within the limits of accuracy obtainable
6.0 kN/mm2 for a strength of C50/60
slab above was actually higher than when using such techniques (typically +/–1 mm).
These values should be used in conjunction Deflections were typically measured
constructing the second.
with a maximum loading of wperm as before and after striking and before and
defined below to arrive at total deflections. after application of peak construction
Methods of deflection
There are various components of load loads. Tests were carried out to establish
prediction the creep and shrinkage characteristics of
that generate long-term deflection.
Current advice for predicting deflections The influence of short-term construction the concrete.
is given in References 2 and 3.
load on long-term deflection may be
Deflections can be estimated in flat slabs assumed to be adequately covered using Findings
by the judicious adding of deflections in the methods above. In practice most A set of measurements taken at the prow
beam strips spanning in orthogonal structures only ever experience a end of the St George Wharf development
directions. proportion of the imposed load. For this has provided the following insights.
The main limitations of this approach are: reason the total deflection in the context
1. The predicted deflections from the
• The method may be applicable only to of, for example, assessing precast
Imperial College non-linear finite
structures with rectangular grids. cladding fit is probably best estimated as
element analysis compared well with
aperm. This is the deflection calculated
• Deflections are sensitive to column the measured deflections as shown in
under the influence of the total dead load
moments that are not accurately Figure 3 and were significantly greater
predicted by equivalent frame analysis. plus a proportion of the imposed load
than those originally predicted, which
(typically 30%). This combined load can
• It is not possible to model the effect of neglected cracking. Figure 3 also
be defined as wperm.
variation in moment across the width of shows that predictions based on an
beam strips. For the purposes of assessing deflections uncracked section can significantly
of partitions, which can be cut to fit on underestimate self-weight deflections.
For this reason the best method for installation, it is the subsequent
predicting slab deflections in two way 2. Care should be taken to ensure that
deflections that are of primary interest.
spanning systems may be finite element boundary constraints are accurately
Based on research at Cardington, Vollum
analysis. The simplest approach is to modelled in deflection calculations.
recommends that this deflection a can
carry out an elastic analysis in which the Columns are best modelled with three-
be estimated from:
elastic modulus is reduced to account for dimensional ‘brick’ elements in finite
the effects of cracking, creep and a = aperm(1 - 0.55wself/wperm) . . . . . . . . .3 element analyses.
3
C A S E S T U D I E S O N A P P LY I N G B E S T P R AC T I C E TO I N - S I T U CO N C R E TE F R A M E D B U I L D I N G S

3. Cracking was observed at soffit 3. The effect of peak construction loads Acknowledgements
locations and in the tops of the slabs should ideally be considered at the
over columns. design stage when considering both The support of the DTI for this project
the serviceability and ultimate limit under the Partners in Innovation scheme
4. The cracking observed appears to be is gratefully acknowledged.
states. This is because slabs are
more extensive than at Cardington.
subject to peak construction loads,
This may be due to the actual concrete
which tend to govern long-term
strengths achieved on this project
deflections and can theoretically be
being closer to the nominal design The Best Practice Guide, Flat slabs for
close to the design ultimate load of
strength, resulting in the cracking efficient concrete construction,
slabs designed for domestic loading.
moment being exceeded by a greater summarises work carried out on these
margin and at more locations. The 4. Where deflections are likely to be an topics during the construction of the
cracks may also be more visible due to issue and reliance on span/depth in-situ concrete building at Cardington.
the reduced floor to ceiling heights. ratios is not deemed sufficient, the This can be downloaded free from
modelling employed should ideally be the Downloads section of The
5. Despite deflections having been larger
sophisticated enough to allow the Concrete Centre’s website at
than originally predicted, this is not
sensitivity of predicted deflections to www.concretecentre.com and at
believed to have caused problems.
the age, magnitude and duration of the http://projects.bre.co.uk/ConDiv/
6. Based on the information collected the construction loads to be assessed. concrete%20frame/default.htm
developer intends to review the need
The work undertaken and the conclusions
for complicated deflection head details
reached in relation to the innovations
on future phases of the project.
described above should be viewed in the
context of the particular project on which
Conclusions the innovations have been trialled.
1. Serviceability issues, particularly
deflections and vibrations, are This Case Study is underpinned by a full
becoming increasingly important with report [4] giving the background and
the move towards longer span, more further information on the work
slender, reinforced concrete flat slab undertaken.
structures.
References Case Studies in this series of applying
2. Reliance on span/depth ratios may be best practice:
1. Early striking of formwork and forces in
insufficient, particularly if deflection
backprops by A. W. Beeby, BRE Report • St George Wharf project overview
limits are specified for particular items
394. Published by Construction • Early age concrete strength
such as cladding and partitions.
Research Communications, London, assessment
Furthermore, better knowledge of
2000. • Early age construction loading
deflections on site has the potential
to provide economy in specifying items 2. Deflections in concrete slabs and • Reinforcement rationalisation and
such as deflection head details and the beams. The Concrete Society. A joint supply
movements that they must accommodate. report from BCA, The Concrete Society • Slab deflections
and RCC, 2003. • Special concretes
3. Prediction of deflections in two-way
spanning systems is not straightforward 3. Approaches to the design of reinforced
and may require finite element analysis. concrete flat slabs by R. Moss. BRE
Report 422. Published by Construction Ref TCC/03/06
4. The limitations of standard finite
Research Communications, London, First published 2004
element software based on linear
2001. Price group A
elastic analysis for predicting
ISBN 1-904818-06-4
deflections should be recognised, 4. Backprop forces and deflections in flat
particularly its sensitivity to the slabs: construction at St George Wharf © The Concrete Centre 2004
assumed material properties and the by R. Vollum. BRE Report BR463, 2004. Published by The Concrete Centre on
difficulty in accurately representing the behalf of the project partners.
effects of cracking. www.concretecentre.com.

Recommendations For further copies of these Best Practice


Case Studies contact
1. In general span/depth ratios may www.concretebookshop.com
continue to be used as a satisfactory
method of controlling deflections. All advice or information from The Concrete
Centre is intended for those who will
2. If deflections are to be predicted then, evaluate the significance and limitations of
as found at Cardington, the designer its contents and take responsibility for its
should be aware that slab deflections use and application. No liability (including
can be increased significantly by that for negligence) for any loss resulting
from such advice or information is accepted.
cracking induced by construction
Readers should note that all Centre
loading. If the deflections are not to be publications are subject to revision from time
underestimated, such cracking must be to time and should therefore ensure that
allowed for when predicting they are in possession of the latest version.
deflections.
4

You might also like