Professional Documents
Culture Documents
Electric Distribution Load Characteristics PDF
Electric Distribution Load Characteristics PDF
Author:
H. L. Willis
A T&D system exists to deliver power to electric 2. Power Systems Exist to Satisfy Customers, Not Loads
consumers in response to their demand for electric energy.
The traditional manner of representing customer
This demand for electricity, in the form of appliances, lighting
requirements for power system engineering has been as
devices, and equipment that use electric power, creates electric
aggregate electric loads assigned to nodes for electrical design.
load, the electrical burden that the T&D system must satisfy.
For example, customer needs in an area of a city may be
In a de-regulated power industry, quality of service - basically
estimated as having a maximum of 45 MW. That value is
quality in meeting the customers’ needs - is paramount.
then assigned to a particular bus in engineering studies aimed
Quality begins with a detailed understanding of the customer’s
at assuring that the required level of power delivery can be
demand requirements, and includes the design of a system to
provided by the system.
meet those needs. This chapter discusses electric load and
Traditionally, the engineering methods used in those design
presents several important elements of its behavior that bear on
studies have been system-based: performance and criteria are
T&D system engineering aimed at satisfying those
evaluated against the power system itself, not against the
requirements as economically as possible.
customers’ needs. Equipment loading limits, single-
contingency backup criteria, and voltage drop/power factor
I. ELECTRICAL LOADS
guidelines defined on the distribution system and even at the
1. Consumers Purchase Electricity for End Use Application customer meter point, all view electrical performance from the
system perspective, and do not directly address customer
Electricity is always purchased by the consumer as an
needs.
intermediate step towards some final, non-electrical product.
Such engineering methods, while necessary to tailor many
No one wants electric energy itself, they want the products it
aspects of T&D design, are not sufficient to completely
can provide: a cool home in summer, a warm one in winter, hot
address the maximization of customer value. Power systems
water on demand, cold beverages in the refrigerator, and 48
exist to satisfy customers, not loads. Understanding the
inches of dazzling color with stereo commentary during
specific needs of the customers — how much quality they
Monday-night football. Different types of consumers purchase
require in power delivery as well as the quantity of power they
electricity for different reasons, and have different
need — can improve the value provided by the power system.
requirements for the amount and quality of the power they buy,
The “two Qs” — quantity and quality — both need to be
but all purchase electricity as a way to provide the end-
considered in designing and operating a power system to
products they want. These various products are called end-
provide maximum customer value.
uses, and they span a wide range, as shown in Table 1.
business, or factory, the various individual end-use loads understanding of how customer loads interact with the power
operate simultaneously, forming the composite load, as system. Most critical, however, is simply the act of keeping in
depicted in Fig. IB. The T&D system sees this composite load mind that the “electric loads” used in T&D engineering studies
through the meter as a single load. In aggregate, the loads of represent the energy needs of people using electricity. The
all customers produce the system load (Fig. 1A), with each best power system is one that satisfies their needs as
type or class of customer contributing a portion to the overall economically as possible.
system demand.
The amount of electric load created on a power system
II. CUSTOMER ELECTRIC LOAD BEHAVIOR
within any end-use category, for example residential lighting,
depends on a number of factors, beginning with the basic need 3. Connected Load
for lighting. People or businesses who need more lighting will
The connected load is the sum of the full load (nameplate)
tend to buy more electricity for that purpose. Also important
continuous ratings of all electrical devices in the composite
are the types of appliances used to convert electricity to the
load system. A typical household in a developed country
end-use. Consumers using incandescent lighting rather than
might have a 4,000-watt water heater, a l,OOO-watt water-well
fluorescent lighting will use appreciably more electric power
motor, a 5,000-watt central air conditioner, a 6,500-watt space
for otherwise similar end-uses.
heater, thirty lighting fixtures or lamps with an average load of
The schedule of demand for most end-uses varies as a
100 watts each, a 4,000 watt cooking range, a 3,500 watt
function of time. In most households, demand for lighting is
clothes washer/dryer, a 500 watt refrigerator, and 2,500 watts
lowest during mid-day and highest in mid-evening, after dusk
of miscellaneous home entertainment, personal grooming, and
but before most of the residents have gone to bed. The daily
other small appliances, for a total of 30,000 connected watts of
schedule of lighting demand usually varies slightly throughout
load. Whether all or any of these are operating at any one time
the year, too, due to seasonal changes in the daily cycle of
depends on a number of factors, including the demand for their
sunrise and sunset. Some end-uses are only seasonal. Demand
various end-use products. It is rare that all the connected load
for space heating occurs only during cold weather. Peak
in a system or at any one customer’s location would be
demand for heating occurs during particularly cold periods,
operational at one time (for example, air conditioning and
usually in early morning, or early evening, when household
heating would not be running simultaneously).
activity is at its peak.
The quality of the electric power supplied is more critical to
4. Electric Load Curves
some end-uses than to others. A power system that can
provide the quantity of power required may still not satisfy the Use of the products created by electric power - light, heat,
consumers, either because it does not provide sufficient hot water, images on the TV, and so forth, varies as a function
availability of power (reliability), or because it does not
of time of day, day of week, and season of year. As a result,
provide sufficient voltage regulation or transient voltage
the electric load varies. A load curve plots electric
performance (surges, sags). Reliability and voltage regulation
consumption as a function of time. Fig. 2 shows seasonal peak
needs vary from one end-use to another, as will be discussed
day load curves for residential loads from two electric systems
later in this chapter, and depends mostly on the value of the
in the United States. In one system, demand is highest in
end-use to the customer.
summer, during early evening, when a combination of air
The value that consumers place on any particular end-use is
conditioning demand and residential activity is at a peak. In
a function of its importance to their quality of life, or to the
the other, peak demand occurs on winter mornings, when a
productivity of their factory or commercial business. An
electric heating demand is highest.
important (but for many power engineers, counter-intuitive)
concept is that end-use value is not of a function of the cost of
the electric power. For example, most personal computers and
workstations use only 2-3# worth of power per hour, yet users
typically report that an hour’s interruption due to lack of power
has a cost of a dollar or more.
Cost is a major factor in T&D design. In fact, cost is often a
consumer’s primary concern, for which they are willing to
accept major compromises in quality, and quantity, or service.
The challenge facing T&D engineers is to meet consumer
needs for both “Qs” - quantity and quality - at the lowest
possible cost. Building a system that delivers higher reliability Fig. 2—Typical summer (solid line) and winter (shaded line) peak
levels than customers need is exactly the same as building one day load curves for a metropolitan power system in the southern
that can deliver much more power than they need. US (left) and a rural system in New England (right).
Knowledge of the customer needs for quantity and schedule
of power delivery, and of the value they place on reliability, Load curve shape - when peak load occurs and how load
voltage regulation, surge and sag protection, and other factors, varies as a function of time - depends both on the connected
are important factors in modern power factor design, as is an load (appliances) and the activitv and lifestvles of the
786 Characteristics of Distribution Loads Chapter 24
consumers in an area. Differences between the electric “non-productive work” required for their function, such as
demand patterns of otherwise similar types of customer (as in produce the magnetic field inside a transformer or motor,
Fig. 2) occur because of differences in climate, demographics, without which they can not function.
appliance preferences, and local economy. VAR flow on a power system consumes capacity in
conductors, transformers, and other equipment, but provides no
5. Demand useful “real” work. It is mitigated by the use of capacitors and
other devices, or by changes in the end-use device so that it
Demand is the average value of load over a period of time
consumes fewer VARS (see Chapter 8).
known as the demand interval. Often, demand is measured on
an hourly or quarter-hour basis, but it can be measured on any
interval - seven seconds, one minute, 30 minutes, daily,
monthly, annually. The average value of power, p(t) during
the demand interval is found by dividing the kilowatt-hours
accumulated during the interval by the number of hours in the
interval.
Demand is the average of the load during the interval. The
peak and minimum usage rates during the interval may have
been quite different from this average (Fig. 3). Demand
intervals vary among applications, but commonly used interval
lengths are 5, 15, 30, and 60 minutes.
Peak demand, the value often called “peak load,” in design Fig. 3—Demand on an hourly basis (blocks) over a 24 hour period.
studies, is the maximum demand measured over a billing or Continuous line indicates demand measured on a one-minute
measurement period. For example, a period of 365 days interval basis. Maximum one-minute demand (at 552 PM) is
contains 35,040 fifteen-minute demand intervals. The about 4% higher than maximum one-hour demand (S-6 PM).
maximum among these 35,040 readings is the peak fifteen-
minute demand. This value is often used as the basis for an
9. Voltage Sensitivity of Loads
annual demand charge if the readings measure a single
customer’s usage, and as a capacity target in engineering The various electrical appliances connected to the power
studies: the maximum amount the system must deliver. system exhibit a range of different load vs. voltage
sensitivities. Important characteristics include their response
6. Demand Factor to transient voltage changes and their steady state load vs.
voltage behavior.
The demandfactor of a system is expressed as the ratio of
Transient voltage response is difficult to characterize and if
maximum demand to the connected load. Normally the
important, should be modeled with detailed, and specific, study
demand factor is considerably less than 1.O.
of the transient response of the particular loads involved.
Classification of transient load response into categories is
7. Load Factor
useful in some cases, but no simple generalization works in all
Load factor is the ratio of the average demand to the peak cases.
demand during a particular period. Load factor is usually For “steady state” representation, individual electric loads
determined by dividing the total energy (kilowatt hours) are generally designated as falling into one of three categories
accumulated during the period by the peak demand and the depending on how they vary as a function of voltage
number of demand intervals in the period, as
Constant impedance loads, for example an incandescent
LF = Total usage during period (1) light or the heating element in an electric water heater,
(Peak Demand) x m are a constant impedance, whose resulting load varies
as the square of the voltage.
where m = number of demand intervals in period
Constant current loads, including some types of power
LF = Average Demand (2) supplies, many electroplating systems, and other
Peak Demand industrial processes, are basically constant current
loads. Energy drawn from the system is proportional to
Load factor gives an indication of the degree to which peak
voltage.
demand levels were maintained during the period under study.
Load factor is typically calculated on a daily, monthly, Constant power loads, such as some types of electronic
seasonal, or an annual basis. power supplies, and to an approximate degree,
induction motors, vary their load only slightly in
8. Power Factor response to changes in voltage.
All loads require real power - kilowatts - to perform useful In each category, reference to a load as “ 1 kW” refers to its
work such as mechanical rotation or illumination. Reactive value at 1.O PU voltage. Table 2 shows the value of a 1 kW
loads also require reactive volt-amperes (VAR) to do a type of load in each category, as a function of voltage.
Chapter 24 Characteristics of Distribution Loads 787
TABLE2 — ACTUALLOAD OFA “1 KW LOAD” OFVARIOUSCATECKRIES converge, changing input data to represent all loads as constant
AS A FUNCTIONOFTHEPERUNIT SUPPLYVOLTAGE - WATTS power will promote convergence to an approximate solution.
Analytical studies and digital programs can be simplified
by deleting the constant current category and using only
constant power and constant impedance type loads. Constant
current load behavior (the rarest of the three types) can be
represented over the range .88 to 1.12 PU voltage, with less
than .75% error, if modeled as a mixture of 49.64% constant
power, and 50.35% constant impedance load. The column
labeled “Ratio” in Table 2 shows this mix of load types, with
the right-most column giving the percentage error in
representation of an actual constant current load.
Chapter 24
- 1
As an increasingly large number of water heaters is While no single customer within the group depicted in Fig. 12
considered as a group, the erratic, back-and-forth behavior of would have an individual load curve that looked anything like
the individual water heater load curve gradually disappears. Fig. 12B (every customer’s load curve looks something like
The load curve representing a group’s load becomes smoother Fig. 12A), the smooth coincident load curve for the group has
as the size of the group is increased, the peak load per water two legitimate interpretations.
heater drops, and the duration at lengthens. By the time 1,000
I. The curve is an individual customer’s contribution to
water heaters are reached (Fig. 1 IG) the curve shape is quite
system load. On the average, each customer of this
smooth, and peak load is at its coincident value of 1,100
class adds this load to the system. Add ten thousand
watts/unit.
new customers of this type, and the system load curve
Thus, Fig. 10 (same as Fig. 1 lG), while unlike any
will increase by ten thousand times this curve.
individual water heater’s actual load curve, is an accurate
representation of water heater behavior from either of two 2. The curve is the expectation of an individual
perspectives. First, it is a diagram of average contribution to customer's load. Every customer has a load that looks
system load, or coincident load, on a per water heater basis — something like the on-off behavior shown in Fig. 12A,
l/l 00,000 of the load of the 100,000 water heaters in the but each has slightly different on-off times that vary in
system. Second, it is the expectation of a water heater’s load an unpredictable manner from day to day. Fig. 12B
as a function of time. To a certain extent, the exact timing of gives the expectation, the probability-weighed value of
the “on” load blocks in Fig. 7- 9, and Fig. 11 is random from daily load that one could expect from a customer of
day to day. Fig. 10 is a representation of the expected load of this class, selected at random. The fact that the
one water heater, as a function of time; the best estimate, a day expectation is smooth, while actual behavior is erratic,
ahead, of load as a function of time. is a result of the unpredictability of timing in when
Note that energy per water heater (area under the load appliances switch on and off.
curve) is not a function of group size. The energy used per
Commercial and industrial customers exhibit intra-class
water heater is constant in any of the load curves in Fig. 11.
coincident behavior qualitatively similar to that discussed here,
but the shape of their coincidence curves may be (usually is)
15. Coincident Load Behavior in General different than for residential. By contrast, inter-class
Most of the major loads in any home or business behave in coincidence is the difference in timing of peak periods among
a manner similar to the on-off, coincident behavior shown in classes (Fig. 4).
Fig. 7 - 9 and Fig. 11. Refrigerators and freezers, air
conditioners, space heaters, water heaters, and electric ovens in
homes; and pressurizers, water heaters, process and other
finish heaters, and other equipment in industry; all turn on and
off in a performance-regulated duty cycle manner. As a result,
individual household load curves, and many commercial and
industrial site load curves, display the blocky, on-off load
behavior shown in Fig. 12A. As with the water heaters, when
a group of similar loads (homes in this case) is considered as a
single load, the load curve becomes smoother, the peak load
drops, and the minimum load rises. Note that the vertical scale
of all six load profiles shown in Fig. 12 is in “load per
customer” for each group.
The 22 kW non-coincident needle peak demand shown in
Fig. 12A for a single household is high, but not extraordinary
for homes in the southern United States. Load curve A
represents a 2100 square foot residence with 36 kW connected
load (sum of all possible heat pump, water heater, garage door
opener, washer-dryer, other appliance and lighting loads).
While customer characteristics vary from one system to
another, the qualitative curve shape behavior shown in Fig. 12,
as well as the tendancy of load curves to become smoother,
and peak loads lower, as group size is increased, apply to all
power systems.
16. Coincident Curve: Expectation of Non-Coincident Load Fig. 12—Non-coincident (A) and coincident (B) winter peak day
load curves for home in a suburban area of Florida. Curves B
The interpretation of coincident load behavior as the through F show the gradual transformation from non-coincident
expectation of non-coincident load behavior, as explained in to coincident behavior as group size increases. Feeders see load
sub-section 14 (water heater example) is generally applicable. curves similar to B. Every service drop sees a load curve like A.
792 Characteristics of Distribution Loads Chapter 24
17. Importance of Coincidence Assessment in T&D Design 18. Coincidence Factors and Curves
Coincidence behavior of load, as depicted in Fig. 12, is Usually, coincident load behavior is summarized for
important to T&D planning and engineering. Equipment such application to power distribution system engineering by the
as service drops, service lines (LV), and service transformers, coincidence factor, and the coincidence curve. Coincidence
which serve small numbers of customers, must be designed to factor is a measure of how peak load varies as a function of
handle load behavior, including customer needle peaks, of the group size for customers
type depicted in Fig. 12A. Normal service does not require
this equipment to handle these load levels for more than a few C = observed peak for the group
(3)
minutes at a time, a factor that can be considered in I( individual peaks)
determining the load rating of this equipment. By contrast,
Fig. 12 illustrates well that as the number of customers in the
equipment serving large groups of customers sees fully
group increases, the peak load/customer usually drops by a
coincident load curve behavior (Fig. 12B). Peak load per
considerable amount. Coincidence factor, C, can be
customer is lower, but peak duration is much longer.
represented of as a function of the number of customers, n, in a
Usually, in spite of the high needle peak values, the thermal
group
capacity of service drops, service (LV) circuits, and service
transformers can be determined based on coincident peak load C(n) = peak load of a group of n customers (4)
values. The thermal time constants for most conductor, cable, n x (average individual peak load)
and transformers are much longer than the duration of any where n is the number of customers in the group,
needle peak. As a result, thermal loading calculated on the and 1 < n < N = number of customers in the
basis of coincident curve shape is usually representative of the utility system
thermal loads that will result from the actual non-coincident
load curves. Diversity factor, D(n), is the inverse of coincidence factor.
Voltage drop and losses are another matter, however. Fig. It measures how much higher the customer’s individual peak is
13 compares the losses that result in a set of triplex service than its contribution to group peak.
drops, for the two load curves Fig. 12A and Fig. 12B. The
result shown is typical. Use of coincident rather than non- D = Diversity factor = l/ Coincidence factor (5)
coincident load curve typically results in errors of up to 50% in
estimating low voltage system losses, and up to 16% in The coincidence factor, C(n), has a value between 0 and 1,
estimating the total voltage drop to the customer’s meter. and varies with the number of customers in a fashion identical
to the way the peak load varies. Fig. 14 shows a coincidence
curve, a plot of how C(n) varies with n. Typically, for
residential and small commercial load classes, C(n) tends
toward an asymptotic value of between .33 and SO for large
values of n. The value for larger commercial and industrial
customers is usually higher, - .75 to .85 is typical, Table 5
gives representative asymptotic coincidence values for typical
customer classes. Coincidence behavior varies greatly from
one utility to another, and among customer classes. The curves
and tables shown here are representative of the type of
behavior seen in all power systems, but can not be
quantitatively generalized to all power systems.
Fig. 15—Coincidence curve for winter peak conditions, and for off- Fig. 17—Annual load duration curve for a power system serving a
peak conditions (late fall).
I I
metropolitan area in the southeastern United States.
794 Characteristics of Distribution Loads Chapter 24
Fig. 18—Examples of coincidence curve modification due to various types of demand-side management (DSM) programs. Thin solid
line indicates base coincidence behavior. Heavier lines indicate the coincidence behavior of the load after DSM modification.
21. Coincidence Curve and DSM Interaction switches off, the water heater will activate. Over any lengthy
period of time (an hour or more) both appliances usually
Many integrated resource methods, such as appliance receive all the energy they need. Thus, over any large group of
interlocking and load control, and other demand-side customers, coincidence of energy usage within any demand
management (DSM) measures, change the coincidence period will not be affected. The asymptote is unchanged.
behavior of customer loads, not the loads themselves. For An opposite type of effect is shown by the broad line in Fig.
example, adding insulation and weather-sealing to a building 18B. Appliance load control is basically a method to limit
does nothing to change the load of its air conditioning and duty cycle, and thus coincidence of load. Typically, load
heating system. These energy conservation measures slow controllers are set to limit the operation of any appliance to no
heat transfer into and out of the building, lengthening the the more than a certain number of minutes per demand period. For
“off’ portions of every on-off cycle. The same needle peaks example, a controller might be set to limit its air conditioner to
occur, but spaced farther apart in time. Basically, this DSM no more than 12 minutes operation out of any 15 minute
measure cuts the percent of time the AC/heater is on, and period, a duty cycle of 80%. During peak conditions, the
hence the coincidence of these appliances. average thermostat may want to operate its air conditioner 90%
Fig. 18A illustrates the change in coincident load behavior of the time. Thus, this load control effects an 11% reduction in
made by universal use of appliance interlocking among all air conditioner energy usage. As a result, the asymptotic value
residential customers in a large group. Interlocking involves of the coincidence curve, for large groups of customers with
jointly wiring the thermostats for the electric water heater, and load control, is reduced.
the air-conditioner/heater, so that the water heater cannot Such a load control measure makes no impact on the
operate if the air-conditioner/heater is operating. It is a simple maximum height of the needle peaks produced by any
form of the appliance schedule optimization that can be household. The AC unit is still the same connected load, and
affected with home automation systems. still likely to overlap with other appliances to create high
The broad line in Fig. 18A shows the resulting coincidence needle peaks. As a result, load control has no impact on the
curve. The 22 kW peak values, which occasionally resulted value of the coincidence curve for individual customers. In
from the random overlapping of appliances activating cases where control is poorly coordinated, or the load control is
simultaneously, are now completely avoided. As a result, the aggressively used to maximize the reduction of coincident
22 kW peak values, and the value of the coincidence curve at peak load, it can produce a “rebound effect,” increasing peak
the Y-axis, are both reduced by the magnitude of the water loads on some levels of the system, as shown by the dotted line
heater’s connected load (4 kW in this example). in Fig. 18B. Fig. 18C through Fig. 18F represent the actions of
However, the water heater is not denied energy. Its use is other often-used DSM approaches.
merely deferred until periods when the air conditioner or heater Fig. 18 illustrates two very important points about DSM
is switched off. As soon as the master (AC-heater) appliance programs. First, DSM programs do not necessarily produce
Chapter 24 795
similar amounts of load reduction on all levels of the power to zero. Demand recorders as used in revenue metering and
system. Second, by use of coincidence curve analysis of the most (but not all) electronic meters use this type of load
type shown in Fig. 18, it is possible to target a DSM program’s recording.
load reductions at particular levels of the power system. DSM Essentially, instantaneous sampling records the actual load
measures that affect the peak loads of large groups of value at specific instants spaced an interval apart. Period
customers, or small groups, can be selected as needed to target integration averages its load measurement over the entire
feeder or service (LV) levels. sample interval between two of those instances. There can be,
and usually is, a considerable difference in the recorded data,
IV. MEASURING LOAD CURVE DATA depending on which of these two different sampling techniques
is used.
Regardless of the actual behavior of the electric load, it is
measured and sampled through the “eyes” of equipment and
procedures which may introduce errors by not capturing
completely all of the load’s characteristics. Many types of load
recording perform a type of filtering that makes load behavior
look more coincident (smoother, lower peak) than it actually
was. Other types mis-recording of load cycles in a way that
renders the load curve data virtually useless. In both cases, the
data looks like load curves, but is inaccurate. Regardless,
power engineers must be aware of the source of all load data,
the method used in its recording, and any limitations it creates
on the accuracy or use of the resulting data.
The problem with instantaneous sampling applied in this 24. Signal Engineering Perspective on Load Sampling
case is that its rate is much to slow to “see” the load behavior.
Load as a function of time is a signal, a value measured as a
But unlike period integration, which smooths the load curve
function of a continuously varying indexing parameter. A
when applied at a slow rate, instantaneous discrete sampling
fundamental concept of signal engineering is that any signal
distorts it, badly, as shown. The load being recorded in this
can be represented as the sum of a set of sine waves of
case (Fig. 12A), has very erratic on-off load behavior common
different frequencies and magnitudes. Low frequencies are
to non-coincident loads. It is simply random chance whether a
slowly undulating sine waves, high frequencies represent rapid
particularly hourly recording instant, falls upon a needle peak,
shifts in value. Any behavior that is characterized by rapid
or a “needle valley.” For a load that has needle peaks, as does
shifts in value is high frequency behavior. A load curve with a
any individual household load, instantaneous sampling at a low
great deal of on-off “choppiness,” as for example Fig. 12A, has
sampling rate gives very poor, even completely unusable
a large amount of relatively high frequency behavior. On the
results.
other hand, a smooth coincident load curve (Fig. 12B) has no
high frequencies.
A fundamental theorem of sampled signal theory is that for
instantaneously discrete sampled data to be valid, the sampling
must be done at twice the rate of the highest frequency in the
signal. Thus, to capture completely behavior of a load curve
that has rapid shifts in load (and thus avoid errors as depicted
in Fig. 23), it is necessary to sample it twice as often as its
appliance loads cycle on and off. Since many appliances turn
on and off within a fifteen or even ten-minute period, a
minimum rate of five-minute sampling is necessary to see peak
load, coincidence, and load curve behavior of such rapid
Fig. 23—Single household load curve (top of Fig. 20) sampled with cycling on an individual household basis. Better yet, one-
hourly discrete sampling. Left: load curve sampled discretely minute samples can be used when trying to identify appliance
every hour at the beginning of the hour. Right; sampled every or individual household load behavior in detail.
hour 15 minutes after the hour. As mentioned in sub-section 23, instantaneous discrete
sampling and period integration sampling differ dramatically in
While the two load curves in Fig. 23 look quite different, what they do if sampling rate falls short of these requirements.
and bear no resemblance to the actual load curve shape, they Essentially, period integration samples a load curve but filters
share one characteristic: Both seem to oscillate back and forth it simultaneously. The averaging over each demand interval,
every three to five hours. This is called aliasing, or “frequency as discussed above, smoothes out choppiness (removes high
folding” in signal theory, and is essentially a “beat frequency” frequencies). To a very good approximation, this type of
generated by interference between the sampling rate, and the sampling can be thought of as responding only to frequencies
duty cycle rate of the appliances in Fig. 12A. Something in the signal that are in the band of frequencies below one-half
similar to this occurs any time the measured quantity being its sampling rate. The period integration responds to
sampled cycles back and forth at a faster rate than the frequencies in the band it can “see” (those below its sampling
sampling. In this example, appliances are cycling on and off rate limit) and ignores those above that limit.
at a rate much too fast for the hourly sampling rate to track. Thus, sampling a load at half-hour intervals with period
The beat frequency, or “aliasing profile” shown here, is a integration will obtain valid information on all frequencies in
characteristic of under-sampled curves, something to watch for the load up to one cycle/hour, but will smooth out, or filter,
in load data. This type of distortion is common. It is fairly fluctuations that are due to more rapid load behavior. (This
easy to detect by manual inspection (at least if given some perspective is slightly simplistic - i.e., only approximate on
training and understanding of what causes it), and its presence several minor technical points - but sufficient for this
means that the load curve data is probably completely invalid. discussion). Instantaneous sampling, on the other hand, does
In the presence of a great deal of erratic on-off load shifts, not filtering, and tries to respond to everything it sees.
as occurs in most non-coincident loads, neither period However, it can only validly see frequencies below twice its
integration (demand sampling) or instantaneous discrete sampling rate. It responds to frequencies above that limit by
sampling gives a completely accurate measurement of the load aliasing them, interpreting high frequency changes as low
curve behavior. The integration method averages behavior frequency. The result is a recorded load curve that may be
over each period. The instantaneous method may chance upon invalid for most engineering and analysis purposes, as are
any value. If the load being measured is fairly smooth, for those in Fig. 23.
example the load of an entire power system, then the level of
error in either case is minute and the issue unimportance. On 25. Determination of the Sampling Method and Type
the other hand, if there is a good deal of non-coincident load
behavior, as usually with loads measured on the distribution Both period integration and instantaneous sampling record
system, then the sampling rate phenomena discussed here are only “approximate data” when applied at too low a sampling
of concern in the load analysis and subsequent engineering. rate to track non-coincident behavior in the load. Instantaneous
798 Characteristics of Distribution Loads Chapter 24
sampling aliases high-frequency load behavior, producing load dividing by 1,000 may seem to be a proper way to produce a
curve data that is useless for engineering and load analysis representative single-household non-coincident load curve, it
purposes. On the other hand, period integration filters out the gives a smooth coincident curve instead.
high-frequency behavior in the load, producing curves that Addition is a signal filtering process. The “average” curve
appear “more coincident” than the actual load. While this obtained by addition/division of a number of customer sample
introduces an inaccuracy in subsequent load analysis and load curves is filtered, in a way that removed high frequency
engineering, the curves are at least correct within the context of load fluctuations. This is the major reason why many T&D
coincident load analysis. engineering studies and load analysis procedures consistently
In all cases, the preferred approach is to use period underestimate non-coincident load behavior and often
integration applied at a high enough rate to sample all the underestimate the amount of coincidence (value of C(n) for n
behavior pertinent to the engineering. However, choice of very large). Most of the load curve data available to engineers
sampling rate and method is often a compromise between cost has been obtained and processed by averaging a group of
and accuracy. There will always be some load behavior sampled customer load curves. This averaging produces only
occurring at a rate faster than can be sampled. Most loads coincident load curve data. Most load curve data in use at
contain motor starting transients and switching fluctuations electric utilities has been produced by averaging, over large
that can only be captured by very high (10 Mhz) sampling enough - customer samples, that it is effectively representation
rates. of completely coincident behavior.
The engineers and load analysts performing load research It makes no difference, in the example cited above, whether
must either select a load recording method that suits their the load curves added together were samples for 1,000
needs, or make only valid use of the data that has been given to households on the same day, as described above, or perhaps
them. Recommended practice is to research fully where the 1000 days worth of one minute readings for one house. In
load curve data came from and how it was recorded, and if it either case, the result of adding together the sampled curves
has gone through any type of aggregation, filtering, or other and averaging them to create an average with create a smooth,
process that might have altered coincident demand behavior. coincident load curve.
Although a majority of recorded load research data comes from The usual reason that a set of load curves is averaged is to
demand interval recorders (period integration), a surprising produce a single curve that is most representative of the set’s
number of sources produce discrete sampling. This includes behavior. Simply put, algebraic methods (averaging) cannot
data taken from SCADA systems, certain types of signal be used to produce average non-coincident curves: there is no
recorders, as well as most portable devices made for logging work-around within normal algebraic approaches. Instead,
loads on feeder and service level circuits. In addition, many some form of pattern recognition or clustering analysis must be
people forget that data “read by hand” from strip and circular applied to find the “load curve most like all the others.” For
charts is essentially discretely sampled data. example, the k-.means method of cluster analysis can be used to
The fact that instantaneous sampling can, and often does, identify one or more curves which have, individually, the most
severely alias non-coincident load behavior does not mean it is “average” peak load, variation rates, energy usage, and daily
necessarily a bad recording method, but it must be used with curve shape.
caution. Similarly, while period integration (demand
recorders, etc.) always records accurately within its sampling 27. Sampling Rate Influences Load Duration Curve Shape
rate limitations, it can be applied at too slow a rate to see
Load duration curves will appear different depending on the
needle peaks and non-coincident load behavior that are present.
sampling rate of the load data, too, as shown in Fig. 24. Since
High sample rate does not guarantee high frequencies.
data sampled at faster rates “sees” non-coincident needle
Sampling a signal at a fast rate does not guarantee that there
peaks, it yields load duration curves that reflect that load
will be high frequencies in the data. It could very well be that
the load being sampled is smooth and has no high frequencies. behavior. Fig. 24 shows annual load duration curves for Fig.
Often, the sensors in recording machinery have a poor 12A, based on 5- and 60-minute demand period sampled data.
response to high-rate fluctuations. For example, strip chart
recorders with a very tight dampers cannot respond to fast load
shifts. Essentially, such mechanical stabilizers remove high
frequencies from the load curve signal.
28. Relationship Between Losses and Demand shows the losses vs. demand data for this feeder, on an hourly
demand period basis. The relationship appears much closer to
Usually, electrical losses are modeled as a function of
squared than when the individual customer data was examined
demand with an equation fitted to measurements taken during
on the same hourly basis (Fig. 26A). Error in estimating losses
selected periods (e.g., the data in Fig. 26). Most often, the
as a function of demand occurs with a = .07, b = .93, and e =
function used estimates hourly losses as a function of hourly
1.91. (A larger value of b, and a value of e closer to 2,
demand, using the maximum recorded hourly demand, and
indicates a more “squared’ relationship). Generally, losses vs.
maximum recorded hourly losses as factors in the computation.
demand behavior for equipment serving large groups of
Either of two functional representations are often used. As
customers appears less linear and more quadratic (squared)
applied to hourly data, they would be:
than for smaller groups.
Losses(h) = L,,, x (a x D (h)/D,,, + b x (D(h)/Dma.J2) (6) In Fig. 26C, the feeder’s losses and energy (essentially the
same as demand, demand = energy/173.33 hr./mth.) are
Losses(h) = L,,, x (D(h)/ D,,,) ’ compared on a monthly basis, instead of the hourly basis used
in Fig. 26B. The observed relationship between losses and
Where h indicates the hour, demand is much more linear than when hourly intervals were
D(h) is the demand observed in hour h, used to analyze the same load: error is minimized with a = .4 1,
D max = maximum recorded hourly demand b = .59, and e = 1.52. The monthly demand period is much
Lmax = losses during maximum demand hour longer than the major cycle periods of the feeder’s load (daily
a+b=l and weekly variations). Generally, losses vs. demand behavior
e is a value between 1.O and 2.0 appears more linear if longer demand intervals are used in the
analysis.
The values a and b in equation 6 are essentially the same as
the “a and b factors” used in traditional computations of losses 29. Mean Error in Estimating Loads
factor from load factor.2 They represent the extent to which
losses behave in a linear, or squared, manner, respectively. Representation of losses as a squared function of demand in
Where losses are a linear function of load, a = 1 and b = 0, and equations like 6 and 7 usually results in underestimation of the
the value e in equation 7 would be 1.O. Where losses have a average level of losses. Note the plotted lines, representing
squared relationship to demand, a = 0, b = 1, and e = 2.0. linear and squared losses behavior in Fig. 26. The curve
Significant “non-squared” losses behavior on distribution representing losses as a function of demand squared is lower in
systems usually occurs in the equipment that serves individual all cases than the measured losses. The line representing
customers with small loads. The most extreme “non-squared” losses as a linear function of demand is uniformly higher than
losses vs. demand behavior that is routinely encountered is a any of the losses’ measurements. This is always the case when
single household load, as shown in Fig. 26A (data is taken using losses estimation equations such as 6 or 7, calibrated
from the same load as in Fig. 12A. This is the losses vs. load against peak period demand and the values D,,, and L,,,.
situation for the service drops leading to this single house. Generally, if the long-term performance of a load analysis
As the measured hourly demand in Fig. 12A varies, both its and prediction equation is to overestimate losses, then it is too
peak load and load factor vary roughly in proportion to one linear in the calibration of its a and b, or e terms, regardless of
another. As a result, hourly losses vs. demand behavior is a the level of its average absolute hourly error. Similarly, if it
mixture of the two extremes discussed above. Modeling of consistently shows a bias toward underestimating the amount
hourly losses as a squared function of hourly demand (a = 0 of losses over many demand periods, then it has been
and b = 1 in equation 6, or e= 2.0 in equation 7) gives 35% calibrated as too quadratic, even if it is giving satisfactory
average absolute error. Error is 13.5% when using 15 minute average error on a demand-period basis.
intervals. Modeling of the losses as a linear function of
demand gives roughly twice these levels of error (almost all
TABLE 6—COEFFICIENTS
FOR LOSSES vs. DEMAND ON AN HOURLY
distribution losses behavior is closer to squared than to linear).
DEMANDPERIODBASISAS A FUNCTION
OF SYSTEMLEVEL
Usually, proper selection of a, b, and e coefficients can cut
error by about 3/4. Use of a = .33 and b = .66 in equation 6
minimizes average absolute error, reducing it from 35% to
8.9%. Use of e = 1.51 in equation 7 similarly minimizes error,
at 9.1%. The two equations provide different estimates on an
hourly basis (with an average absolute difference of 4%) but
are roughly equal in overall modeling accuracy. When using
quarter-hour demand periods in this example, a = .24, b = .76,
and e = 1.6 minimizes average absolute error, at less than 5%.
The load curve shown in Fig. 12A is one of 282 residential
loads in a neighborhood served by a 12.47 kV feeder. Fig. 26B
VI. T&D SYSTEMS ARE BUILT TO SATISFY A personal computer exhibits demand characteristics
CUSTOMERS, NOT LOADS exactly the opposite of the water heater’s. A typical PC has a
connected load of about 180 watts, and a contribution to
32. Quantity, Quality, and Value
coincident peak of the same magnitude. But while its
The diverse types of consumers purchasing electric power connected load is one twentieth, and its peak demand only one
from the distribution system have different uses for the power sixth of the water heater’s, its demand for quality is much
they buy, different needs for quantity (amount of power higher. Measured as the time it can go without power while
purchased), and needs for quality (continuous availability, tight continuing to perform its end-use function, a PC is about
voltage regulation), and different dispositions to pay a 15,000 times more sensitive to power continuity problems than
premium price to get exactly what they need. The value a a water heater. It is also vastly more sensitive to voltage sags
particularly consumer places on electric power is a function of and surges, and long-term changes in voltage.
his or her needs for electricity, primarily as defined by the Largely because of the different needs of their appliances
economic or personal value of the end-use (i.e., watching and equipment, and the difference values of the net end-use
television and keeping food cool, stamping sheet metal into products, electric customers vary greatly in their demand for
equipment cases, operating a cash register/inventory system), electric power quality. Fig. 29 gives five examples of “cost of
and as fashioned by the demands of the appliances used to interruption” value of electric customers. The cost vs. time
convert electricity into the end-use. functions shown are not typical, because there is no typical
The major element of customer quality is availability of need for power quality, just as there is no typical quantity of
sufficient quantities of power. Quality can be as or even more power requirement that suits all customers. In general,
important than quantity in determining the customer value, but commercial and industrial consumers have a higher demand
the important point is that both quantity and quality are major for both quantity and quality of power than residential
factors to be considered in determining how to maximize consumers.
customer value. Two common residential appliances that In a competitive electric power industry, and a world where
illustrate the opposite extremes in these two “Q dimensions” attention to quality is taken for granted in many other
that can exist among customers. These are an electric water industries, power system engineers should anticipate increasing
heater and a personal computer. levels of attention on quality of power delivered. This does not
A typical 50-gallon storage water heater has a connected necessarily mean that quality must be or will be improved.
load of 4,000 watts, and a coincident contribution to system Cost is an important element of value, and a large portion of
peak of about 1,100 watts. This is a relatively high demand for consumers in most power systems would prefer to pay a lower
quantity of power as compared to most household appliances price for power, even if that means they must sacrifice some
(typically only central air conditioners or heaters use more amount of power quality in return. The important point is that
power). Power to a water heater can be interrupted routinely like quantity of power, quality is an important attribute. As it
for several hours at a time (and often is under peak-shaving is with quantity, it is possible to overbuild or underbuild a
load control programs). Such interruptions make little impact power system with respect to the amount of quality that needs
on its value to the customer, because it can supply reasonable to be delivered. The challenge facing power engineers is to
quantities of hot water from its storage tank during power design the lowest cost system that can deliver the required
interruptions. In addition, its end-use performance is virtually levels of both, and no more.
immune to voltage sags, surges, and even significant long term
variations in supply voltage. Thus, while a water heater has a
high demand for quantity, it has a low demand for power VI. GROWTH OF ELECTRIC LOAD AND T&D
quality. CAPACITY REQUIREMENTS
Fig. 30—Spatial distribution of electric load for a city of about 1 million population in the eastern United States. Shading indicates
load density. Lines indicate major roads. At the left, 1998 winter peak load. At the right, a forecast of peak load for year 2010,
based on projected trends in load density, customer count, area development, peripheral expansion, and end-use loads. The city is
projected to grow both up and out during the 12-year period. Some interior areas are projected to increase in load density, but others
are not, and load density decreases in a few areas. Load develops in previously vacant areas, particularly along the south periphery.
The load maps in Fig. 30 outline the mission of the T&D 35. Growth Drives System Expansion
system for the region shown. In the year 1998 it must deliver
Fig. 30B shows the projected load 12 years later than Fig.
2,3 10 MVA of electric power in the geographic pattern shown.
30A, based on a detailed evaluation of economic growth of the
Its ability to do so reliably and economically is the major
region, land availability, demographic and zoning factors, and
measure of its performance as a power delivery system.
expected changes in per capita and end-use loads. After this
34. Load Density Varies With Location 12-year period of growth, the T&D system will be expected to
deliver 3,144 MW in the pattern shown. During the intervening
Fig. 30 illustrates how load density varies as a function of 12 years, additions and changes to the system must be made so
location within a power system. Analysis of load in terms of that it can grow along with the load. This load growth is the
kW/acre or MW/square mile is a convenient way of relating it motivation for the equipment additions, and the expansion
to local T&D capacity needs and is often used in power budget will be well spent only if the equipment is located, and
delivery planning. Load density is an important aspect of locally sized properly, to match the evolving load pattern in
T&D planning, since the capacity and location requirements of Fig. 30B.
T&D equipment depend on local load characteristics, not Comparison of Fig. 30A and Fig. 30B reveals several
system averages. Typical ranges of values for urban, suburban, characteristics of load growth as it affects T&D systems:
and developed rural areas are given in Table 7. The values
shown are typical, but values specific to each particular system Previously vacant areas develop load, e.g., the swath of
should be obtained by measurement. load growth across the entire southern frontier of this city
between 1998 and 2010. Entirely new parts of the system
must be built into these areas.
TABLE7—TYPICAL
LOAD DENSITIES
FORVARIOUS TYPES
OFAREAS
The difference between Fig. 30A and Fig. 30B represents By contrast, growth in any relatively small geographic area
the challenge facing this system’s T&D planners. They must is not a smooth continuous trend from year to year. Instead, it
make additions whose equipment types, capacities, locations, follows the Gompertz curve, commonly referred to as an 5”
and interconnections to the existing system result in a “12- curve, shown in Fig. 31. The “S” curve is the basic behavior
years hence” system that can reliably and economically serve of load growth as it affects T&D equipment, such as in feeder
the pattern shown. and substation areas. Nearly every small area within a large
power system has a load growth history similar to that shown
36. Two Causes of Load Growth in Fig. 3 1, for a very simple reason: landfills up.
The S curve has three distinct phases, periods during the
Two simultaneous processes create electric load growth or
local area’s history when fundamentally different growth
change, both at the system and at the distribution level.
dynamics are at work:
Increases in the number of customers in the utility service
area, and increases in the usage per customer cause electric Dormant. The time ‘before growth”, when no load
load to grow. No other process causes load growth: If the growth is occurring. The small area has no load and
electric demand on a power system increases from one year to experiences no growth: growth “hasn’t arrived yet.”
the next, it can be due only to one or a combination of both of
these processes: Growth ramp. During this period growth occurs at
a relatively rapid rate, usually due to new
I) New customers are added to a system due to migration construction.
into an area (population growth) or electrification of
previously non-electric households. Customer growth Saturation. The small area is “filled up” - fully
causes the spread of electric load into areas that were developed. Growth may continue, but at a very low
“vacant” from the power system’s standpoint. level compared to that during the growth ramp.
2) Changes in per capita usage occur simultaneously and What varies most among the thousands of small areas in a
largely independently of any change in the number of large utility service territory is the timing of their growth
customers. In developing economies this is driven by ramps. Seen in aggregate over several thousand small areas,
the acquisition of new appliances and equipment in and the overall system load curve looks smooth and continuous
homes and businesses. In developing nations, per because there are always roughly the same number of small
capita load growth often decreases, due to improving areas in their rapid period of growth. The continuous year-to-
appliance efficiency. year trend for the whole system is due to diversity in the timing
of when areas grow: any one area grows for only a short time,
In cases where per capita consumption is increasing, it is
but new areas of growth are constantly being added to a
usually due to major shifts in appliance market penetration. For
growing city, so as a whole, it grows continuously.
example, the percentage of homes and businesses using electric
Evidence of historical “S” curve load growth exists in every
power to heat the interior of buildings may increase from 20%
city. Most people can identify areas of their home town or city
to 26% over a decade. In such a case, even if appliance that developed in the 196Os, the 1970s the 1980s or the 1990s.
efficiency is increased slightly, electric load will grow.
The buildings in these areas are of a common age, because all
were built during a “burst” of development in that area, at that
37. Spatial Load Growth and the “S” Curve Characteristic
time.
When viewed from a total system basis, a growing power
system generally exhibits a smooth, continuous trend of annual 38. Relation of Load Growth Causes to “S” Curve Shape
peak load growth. Given a healthy economy, and corrected for
These two causes of load growth are tied to different parts
variations due to weather, the load in the region will simply
of the “S” curve characteristics, as shown in Fig. 31. The
continue to grow at a continuous rate.
growth ramp occurring over a short period of time is due to
new customers in the area. The slow, steady growth thereafter
is due to increasing per-capita usage by the customers in the
area. In some cases, the slow, steady trend is a reduction over
time, due to improving appliance efficiency.
operation of their system. Facilities are utilized more steady annual load growth over a long period of time, as
efficiently if they are sited correctly. The need for locational shown. Except for weather and economy, many cities have in
detail in planning and engineering is called spatial resolution. fact grown steadily in this manner: Denver, Phoenix,
Spatial resolution requirements vary depending on Indianapolis, Bangkok Caracas, and Rabat, to name just a few.
application: feeder planning requires more detail on and is Imagine dividing the metropolitan area illustrated in Fig. 32
more sensitive to changes in the location of loads, than into quadrants. Each quadrant would still be very large (in a
transmission planning. Table 8 gives typical range of spatial city like Atlanta or Houston, nearly a thousand square miles).
resolutions (knowledge of load as a function of location) that If the exact load history of each quadrant could be plotted, all
work well in T&D planning. The table indicates that would be slightly different in amount of load and rate of
knowledge of how load density, and load growth are usually growth, but all would still have a fairly smooth, continuous
needed to match equipment locations so that economy and trend. This is shown in Fig. 33.
reliability are maximized to the load. Resolution as used in
the table refers to the width of a square area used for load
studies, and within which reliable information on load
locations is not available.
sake, imagine that a house is built in this very small area), and spatial resolution, growth is usually a short, intense period of
a significant load established. For many years thereafter, this development. It usually happens in areas where there was no
annual load peak of the small area varies only slightly - the previous load, and it does not always occur - many areas stay
house is there and no further construction occurs. vacant.
The quantitative behavior of the “S curve” growth The three changes in growth character discussed above
characteristics will depend somewhat on the spatial resolution occur on(v because spatial resolution of data collection and
(small area size used). There are three important interactions analysis changes. The character of the load growth itself does
with between growth characteristics and spatial resolution. not change, only the way it appears to the planner. By asking
for more spatial information (the “where” of the T&D planning
I. The YY curve behavior becomes sharper as the service
need) the very appearance of load growth itself, changes.
territory is subdivided into smaller and smaller areas.
The smaller the small areas being studied (the higher the
spatial resolution) the more definite and sharp the “S”
curve behavior exhibited, as shown in Fig. 35.
Quantitative behavior of this phenomena depends on
growth rate, demographics, and other factors unique to a
region, and varies from one utility to another.
Qualitatively, all utility systems exhibit this behavior:
“S” curve load trend becomes sharper as area size is
reduced.
1996). However, the exact timing of growth appears to be early, in order to reach these disparate locations. An economic
, somewhat random, at least as viewed from apriori information dilemma develops because the utility will eventually need a
likely to be available to the planner. Implications for T&D good deal of capacity in these routes when the load fills in the
expansion are clear. The system cannot be extended area, but planners do not want to incur the cost of building now
incrementally outward from the southeast as load grows. for load levels not expected for 1O-12 years. The challenge is
Instead, substation siting and feeder expansion must deal with to find a way to expand the system without building a majority
delivering “full load density” to an increasing number of of the routes early, or having to build many long routes with
neighborhoods scattered over the entire region, that develop higher capacity than will be needed for years.
geographically into a higher overall density. This means that
full feeder capability (maximum designed load and maximum 41. “Putting Out Fires” Is the Norm in T&D Expansion
designed distance) may be needed far sooner than predicted by T&D planners often speak about “putting out fires” -
the “gradually increasing density” concept. having to develop plans and install equipment and facilities on
a tight time schedule, starting at the last moment, without
proper time to develop comprehensive plans or coordinate area
development overall. A point illustrated here is that the load
growth aspect of this situation is the norm: rapid growth that
starts with little warning, fills in an area relatively quickly, and
then moves elsewhere, not only happens on a regular basis, but
is the normal mechanism of growth. The “S Curve” growth
characteristic, its tendency to be sharper in smaller areas, and
the semi-random, discontinuous pattern of load development
described above, are very general characteristics that affect all
power systems. Load development in a small area almost
always begins with little long-term warning, grows at a rapid
rate to saturation, and then moves to other areas, usually near
by, but often not immediately adjacent.
This growth characteristic is the basic process that drives
T&D expansion, equipment additions, and the planning and
engineering process. T&D engineers will never change the
nature of load growth and development. The recommended
approach is to develop planning, engineering, and equipment
procurement procedures that are compatible with this process.
These include:
a) Master plan development based on projected area
development. As noted above, the eventual load density
for any small area, and the overall pattern of development
for a region, can be predicted with reasonable accuracy
fairly far in advance. Thus, long range plans optimized to
the expected pattern of development can be developed.
b) Use of modular system layouts for transmission,
substations, feeders and service (LV) parts of the system,
that permit modular expansion on an incremental parcel
basis. Some types of layout are more expandable on a
“fill in the parts” basis that others. In particular, the
growing use of multi-branched rather than large-trunk
feeder layouts is one reaction to this situation. Such
Fig. 36—Load grows as developing parcels of land. As a region
feeders can be expanded on a short range basis, to cover a
fills in with load, individual parcels develop very quickly, but
growing area as needed, yet still fit into an optimized
often leave vacant areas between them. The utility may have to
build a majority of the primary feeder lines that kill de needed
long-range plan.
eventually, long before a majority of the growth has developed. c), Organization of the planning, engineering, and
construction process with short lead times for
Such expansion is difficult to accomplish economically: implementation. Given that a long-range master plan
feeders must be extended over much of this area early in the exists for an area, the key to success is a short start-up and
12-year period, so the utility can serve the widely scattered lead time for engineering of the details and project
pockets of high load density. Great capacity is not needed at implementation, once development begins.
that time, because the overall load is not high. However, a
good portion of all the routes eventually needed is required
808 Characteristics of Distribution Loads Chapter 24
REFERENCES
1. Power Distribution Engineering- Fundamentals and Applications, by J. 15. Spatial Electric Load Forecasting, by H. L. Willis, Marcel Dekker, New
J. Burke, Marcel Dekker, New York, 1994. York, 1996.
2. Trends in Distribution Reliability, by J. J Burke, ABB Electric systems 16. Power Distribution Planning Reference Book, by H. L. Willis, Marcel
Technology Institute, Raleigh, NC 1997. Dekker, New York, 1997.
3. Urban Distribution Load Forecasting, final report on project 079D 186, 17. Some Unique Signal Processing Applications in Power Systems
Canadian Electric Association, 1982. Analysis, by H. L. Willis and J. Aanstoos, IEEE Transactions on
4. Research into Load Forecasting and Distribution Planning, report EL- Acoustics, Speech, and Signal Processing December 1979, p. 685.
1198, Electric Power Research Institute, Palo Alto, CA, 1979. 18. Spatial Load Forecasting - A Tutorial Review, by H. L. Willis and J. E.
5. DSM: Transmission and Distribution Impacts, Volumes 1 and 2, Report D. Northcote-Green Proceedings of the IEEE, February 1983, p. 232.
CU-6924, Electric Power Research Institute, Palo Alto, Aug. 1990. 19. Comparison of Fourteen Distribution Load Forecasting Methods, by H.
6. Tutorial on Distribution Planning, by M. V. Engel et al., editors, Institute L. Willis and J. E. D. Northcote-Green, IEEE Transactions on Power
of Electrical and Electronics Engineers, New York, 1992. Apparatus and Systems, June 1984, p. 1190.
7. Edge City, by J. L. Garreau, Doubleday, New York, 199 1. 20. Introduction to Integrated Resource T&D Planning, by H. L. Willis and
8. Computer Speeds Accurate Load Forecast at APS, by A. Lazzari, G. B. Rackliffe, ABB Guidebooks, ABB Power T&D Company, Raleigh,
Electric Light and Power, Feb. 1965, pp. 3 l-40. 1994.
9. Model of Metropolis, by I. S. Lowry, Rand Corp., Santa Monica, 1964. 21. Some Aspects of Sampling Load Curves on Distribution Systems, by H.
10. Sensitivity Analysis of Small Area Load Forecasting Models, by J. R. L. Willis, T. D. Vismor, and R. W. Powell, IEEE Transactions on Power
Meinke, in Proceedings of the 10th Annual Pittsburgh Modeling and Apparatus and Systems, November 1985, p. 3221.
Simulation Conference, University of Pittsburgh, April 1979. 22. A Cluster-based V.A.I. Method for Distribution Load Forecasting, by H.
11. Electrical Loads Can Be Forecasted for Distribution Planning,” by E. E. L. Willis and H. N. Tram, IEEE Transactions on Power Apparatus and
Menge et al., in Proceedings of the American Power Conference, Systems, September 1983, p. 8 18.
Chicago, University of Illinois, 1977 23. Spatial Electric Load Forecasting by H. L. Willis, M. V. Engel, and M. J.
12. Computer Model Offers More Improved Load Forecasting, by W. G. Buri, IEEE Computer Applications in Power, April 1995.
Scott, Energy International, September 1974, p. 18. 24. Forecasting Electric Demands of Distribution System Planning in Rural
13. Load Forecasting Data and Database Development for Distribution and Sparsely Populated Regions, by H. L. Willis, G. B. Rackliffe, and H.
Planning, by H. N. Tram et al., IEEE Trans. on Power Apparatus and N. Tram, IEEE Transactions on Power Systems, November 1995.
Systems, November 1983, p. 3660. 25. Short Range Load Forecasting for Distribution System Planning - An
14. Load Forecasting for Distribution Planning - Error and Impact on Improved Method for Extrapolating Feeder Load Growth, by H. L.
Design, by H. L. Willis, IEEE Transactions on Power Apparatus and Willis, G. B. Rackliffe, and H. N. Tram, IEEE Transactions on Power
Systems, March 1983, p. 675. Delivery, August 1992.