SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Inspection of Auxiliary Piping Installation SAIC-G-2004 25-May-05 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A. General:

Pump auxiliary piping have been inspected per SAIC-G-2002, (Receiving


A1 SATIP-G-005-01
Inspection of Centrifugal Pumps) at material receiving.
All piping components are re-assembled/installed in their respective
P&ID #
A2 locations as shown in the P&ID. (i.e.: piping, removable pipe spools,
____________
valves, vents, drains, spectacle plates, blinds, flange spacers, etc)

All in-line equipment & Instruments are installed in their respective


P&ID #
A3 locations as shown in the P&ID. (i.e.: Strainer, flow meter, orifice fitting,
____________
Pressure Indicators, Temperature indicators, etc)

For dissimilar metals connections; examples: a stainless steel flange to


carbon steel flange, or a Cu-Ni flange to carbon steel flange, the SAES-L-105
A4
potential for galvanic corrosion shall be determined in consultation with Para 5.7.1
the Materials Engineering Unit of Consulting Services Department
Where potential galvanic corrosion exists, the types of joints are
restricted as follows:
1) For flanged joints of dissimilar metals, insulating gaskets, stud bolt
sleeves and washers such as PIKOTEK, or approved equal.
SAES-L-105
A5 2) For non-flanged mechanical joints of dissimilar metals, a dielectric
Para 5.7.2
union.
3) Welded joints of dissimilar metals are not permitted.
Connection of dissimilar metals is by means of a dielectric or insulating
union.

REMARKS:

REFERENCE DOCUMENTS:
1. Project's P & ID # ________________________
2. SAIC-G-2002, Equipment /Material Receiving Inspection, Rev 0
3. SAES-L-105, Piping Material Specifications, (30 September, 2003)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Page 1 of 1