1. API 510 says that widely scattered pitting can be ignored provided that the:
a. pit depth is less than ½ the minimum required thickness.
b. pit depth is less than ½ the vessel’s current thickness away from the pit.
c. remaining thickness is not less than ½ the minimum required thickness.
d. remaining thickness is not less than ½ the current thickness away from the pit.
3. When repairs and alterations are being conducted, which individual or organization is
responsible for Quality Control?
a. Authorized Inspection Agency
b. Repair Organization
c. API 510 Inspector
d. On-site Pressure Equipment department
6. The maximum inspection interval for a pressure relief device in normal service is:
a. the lesser of 1/2 remaining life or 10 years.
b. based on acceptable performance of the device.
c. based on acceptable performance of the device with a max. interval of 5 year.
d. based on acceptable performance of the device with a max. interval of 10 year.