Professional Documents
Culture Documents
After careful and considered review of the content of this paper by a duly
constituted expert committee, this paper has been found to be in violation of
IEEE's Publication Principles.
We hereby retract the content of this paper. Reasonable effort should be made to
remove all past references to this paper.
The presenting author of this paper has the option to appeal this decision by
contacting TPII@ieee.org.
Construction Project Schedule Risk Analysis and Assessment Using Monte Carlo
Simulation Method
12 1 2 12
Dezhi Jin , , Zhuofu Wang , Xun Liu \ Jianming Yang , Meigui Han ,
1. Institute of Construction P roject Management, Hohai University,Nanjing, China
2. School of Engineering, Nanjing Agricultural University, Nanjing, China
jindezhi@njau.edu.cn
Abstract-Construction projects are initiated in complex and uncertainty associated with construction development in
dynamic environments resulting in circumstances of high terms of time. When specifically considering the execution
uncertainty and risk, which are compounded by demanding of a construction project, controlling risks resulting from the
time constraints. This paper describes an application of Monte uncertainty is accomplished through the achievement of
Carlo simulation method to consider and quantify uncertainty reliable project schedules. In reality, failure to fulfill the
in construction scheduling. This paper points out the
project objectives within cost and on time is quite common.
importance of the construction project scheduling risk analysis
As a result of techniques, such as probabilistic scheduling,
and assessment from the perspective of contractor and points
and stochastic process (Monte Carlo simulation), being
out the limitations of project management network techniques
systematically employed at the start of a project's
(CPMlPERT). Based on analyzing the principle of construction
development, the uncertainty related to duration is
project scheduling risk analysis and assessment using Mote
Carlo simulation method, the evaluating steps of Mote Carlo
considerable due to the probability of future complicated
simulation method are given. Ultimately, the outcomes of the
conditions and changing environments. One main concern of
paper are illustrated by an instance. a project manager or decision maker is not to exceed the
approved project's cost and schedule. Indeed, a project
Keywords-construction project; scheduling risk; Me; risk control effort is devoted to ensuring that the actual cost does
assessment not deviate from the planned cost and that the project is
completed on schedule.
I. INTRODUCTION
II. LIMITATIONSOF CPM ANDPERT
In today's construction industry, the engineering
construction project, especially the large investment project, A. Limitations o/CPM
often has huge investment, long construction period, The basic assumption of CPM is that each activity'S
technological and economy risk, the great potential impact to duration as well as the logical relationships between
the ecological environment, uncertain factors. So these activities is determined in a network schedule. However,
characteristics incur that the factual project deviate from the there exist a lot of uncertainty factors such as politics,
consequence that people expect by a certain degree. The economy, meteorological and hydrological conditions,
losses result from risks increasing with the size and construction scheme, resource supply, construction
complexity of construction projects, even determine the environment and so on, which may cause that construction
success or failure of the construction projects. The site conditions are difficult to be completely accurately
preparation of the construction project schedule is primarily proven and that project implementation will be influenced by
based on engineering quantity and resources allocation, storm, flood, typhoon, etc. These uncertain factors in the
construction quota and other factors. However, these factors construction project make both the durations of activities and
are uncertainty in actual construction. The objective of the logical relationships between them in highly uncertain
project schedule, as one of the three control objectives, status.
affects the cost targets and quality targets. When the Therefore, it is necessary for us to focus on how to
construction project schedule risk occurs, the contractor in calculate the time parameters and determine whether the
order to rush the progress is bound to increase the human and construction project can be completed on time. When the
material resources, make the cost of the project will increase, construction plan can not be realized, the so-called schedule
and the project quality is also easy to problems. When the risk has been formed. As to this kind of network schedule
progress of the out of control, resulting in significant problem with uncertain activity durations, the basic salvation
schedule delays, so that the project can not be put into methods include PERT and Monte Carlo (MC).
production on schedule to benefit not only to owners to pay
the contractor the tender stated in the annex to the B. Limitations o/PERT
corresponding amount as damages for breach of schedule Based on mathematical statistics theory, PERT is often
delay costs, but also seriously affect the company's used to solve network schedule problems with definite
reputation, the company bid in the future rather than reactive. logical relationships and uncertain activity durations. It is
In today's construction industry, one of the important simple, but still with some obvious deficiencies as follows:
goals is the quantification and minimization of the
597
(i) It requests that activity durations should obey � the probability models of each random variance are
distribution or normal distribution and that the critical path's constructed, which are done sampling and then each
duration should obey normal distribution. When an actual activity's duration will be determined, this process is
project does not meet the conditions, the calculation equivalent to simulation for one time [7]. Every time when
precision will be obviously influenced. The activity durations doing an experiment, we use sampling technique fIrst and get
in PERT are assumed to be random and obey � distribution. the random data of activity durations, then we can calculate
Therefore, the activity durations can be estimated by three the random project duration r; with CPM. After simulating
point method [1]. It is mainly for the calculation convenience for N times, we can get random duration
to assume that the activity durations obey � distribution,
serialization {r; Xi 1,2,.··, N) , and then we make on the
=
big enough, the calculation result has high accuracy. When a u -00 .J27r
n
project has large scale or many activities, the computing
Pr =l-P (2)
quantity is large under a certain requirement of calculation
accuracy. What's more, when the accuracy requirement Where Ts is required duration, Te is the expected
increases one magnitude, the calculation quantity should
increase two magnitudes, which can be realized by computer. duration on the critical path, u is the standard deviation on
n
Clearly, with the development of computer technology, using the critical path, P is completion probability while Pr is
MC method to assess schedule risk of a project has obvious
the schedule risk.
advantage.
B. Basic principle to evaluate schedule risk with MC IV. CASE STUDY
598
Figure 1. A Certain Schedule Project Network Graph
Activity Optimistic duration (a) Most likely duration Pessimistic duration (b)
(i, j) (m)
1,2 8 10 12
1,3 4 5 6
1,4 4 7 9
1,5 4 5 6
2,3 4 5 7
2,6 16 18 20
3,4 2 4 5
3,7 3 6 9
4,7 2 3 5
5,7 7 8 9
5,8 7 9 10
6,7 14 16 18
6,8 2 3 5
6,9 3 4 5
7,8 6 9 11
8,9 9 11 13
8,10 3 5 8
8,11 2 7 12
8,12 3 5 6
9,10 3 5 7
9,13 17 19 21
10,11 2 4 6
10,14 2 4 5
Activity Optimistic duration (a) Most likely duration Pessimistic duration (b)
(i, j) (m)
11,14 2 7 9
599
12,14 7 9 10
12,15 8 9 10
13,14 13 15 17
13,15 2 3 4
13,16 2 4 5
14,15 7 9 11
15,16 8 10 12
15,17 2 5 8
15,18 3 7 12
15,19 4 5 6
16,17 2 5 6
16,20 16 18 20
17,18 3 4 6
17,21 3 6 9
18,21 2 3 5
19,21 7 8 9
19,22 7 9 10
20,21 14 16 18
20,22 2 3 5
21,22 8 10 12
600
Determining the times of simulation schedule risks can be calculated accordingly. For example,
when the regulated duration of schedule is 155 days, the
completion probability is 0.68%, and that is to say, the risk
of project can not be completed on time is 99.32%.
Acquiring the parameters of each activity for the
construction project V. CONCLUSIONS
ACKNOWLEDGMENT
REFERENCES
[I] Li Qinghua, The Collection of Chinese Network Plan. Beijing:
Earthquake Press, 1993, pp.807-8I2.
Calculating the expected value and variance of
total duration for project
[2] T. K. Littlefield, and P. H. Randolph, "An answer to sasieni's
question on PERT times, " Management Science, vol. 33, issue. 10,
October 1987, pp. 1357-1359.
[3] K. R. MacCrimmon, and C. A. Ryavec, "An analytical study of the
Figure 2. Simulation flow chart of the progress of the project
PERT assumptions," Operations Research, vol. 12, issue. I, 1964, pp.
16-37.
The results of simulated 10000 times are shown in Table [4] Li Gansheng, Wang Zhuofu, and Bai Hongkun, "Network planning
2 and Fig. 3. computer simulation and risk analysis, " Journal of Hohai University,
vol. 29, issue. 1, 2001, pp. 65-69.
TABLE II. The DURATION and variance of project SIMULATED 10000
[5] Bajis Dodin, "Determining the k most critical paths in PERT
TIMES
network, " Operations Research, vol. 32, issue. 4, 1984, pp. 859-877.
[6] Bajis Dodin, "Bounding the project completion time distribution in
Simulated times Mean (day) Variance (day)
PERT network," Operations Research, vol 33, issue 4, 1985, pp. 862-
881.
10000 160.8467 2.3670
[7] Jamal F. AI-Babar, Keith C. Crandall, "Systematic risk management
approach for construction project, " Journal of Construction
Engineering and Management, vol. 116, issue 3, 1990, pp. 533-546.
[8] Xu Zhe, and Feng Yuncheng, "Risk analysis of network project, "
Systems Engineering Theory and Practice, 1998, issue. 4, pp. 25-28.
[9] Wang Zhuofu, and Chen Dengxing, "risk analysis of water
conservancy and hydropower construction schedule," Journal of
Hohai University, vol. 27, issue. 4, 1999, pp.83-84.
[l0] Shu Xingming, "Seeking Critical path through the shortest path
method and And its implementation of SAS," Journal of Guangxi
University, vol. 27, issue. 1,2002, pp. 264-269
Figure 3. The line of chart total duration simulated 10000 times
601