Professional Documents
Culture Documents
MULTIPLE CHOICE
Assuming constant annual demand for an item, increasing its order quantity: *
1 point
In the fixed-time period model, the order quantity is determined for which: *
1 point
Transportation cost.
Obsolescence.
Cost of storage space.
Cost of money invested in inventory.
The item is not moved from one place of the storage area to another.
The owner of the inventory does not own the warehouse.
The item is not perishable.
None of the above
The basic EOQ model is based on all the following assumptions except: *
1 point
This study source was downloaded by 100000858625340 from CourseHero.com on 12-07-2022 20:19:12 GMT -06:00
https://www.coursehero.com/file/76722027/POM-Final-examdocx/
Estimates of ordering and carrying costs are accurate.
Order is instantaneously received exactly when previous inventory has just been used up .
The “how much to order” decision always has an influence on the following
costs except: *
1 point
The level of inventory at which a new order needs to be placed to replenish depleted
stock is called the: *
1 point
Service level.
Reorder point.
Minimum inventory level.
Safety stock.
To establish the reorder point in the EOQ model, we must know both: *
1 point
The annual demand and the number of orders placed per year.
The annual demand and the lead time.
The daily demand and the order quantity.
None of the above
In the basic EOQ model, the average inventory level is equal to one-half this value: *
1 point
Can we delay a particular activity and still finish the project on time?
When are we scheduled to start a particular activity?
Which activities should be finished on time?
All of the above.
This study source was downloaded by 100000858625340 from CourseHero.com on 12-07-2022 20:19:12 GMT -06:00
https://www.coursehero.com/file/76722027/POM-Final-examdocx/
Can be completed in no time at all
Means the project is expected to be delayed.
The following descriptions are always true of the critical path in a project EXCEPT: *
1 point
Delaying it beyond its slack will cause the delay of the whole project.
It can be delayed.
Both A and B.
Neither A nor B.
Activities A, B, and C are started at Week 0 and are the immediate predecessors for
Activity J. If the earliest finish times for the three activities are Week 11, Week 15, and
Week 10, respectively, then the earliest start time for J will be *
1 point
Week 10
Week 11
Week 12
Week 15
Given a project with three paths and their corresponding path lengths: A-B-C: 25 days,
A-D-E: 15 days, and B-C-E: 20 days; which of the following statements is TRUE? *
1 point
This study source was downloaded by 100000858625340 from CourseHero.com on 12-07-2022 20:19:12 GMT -06:00
https://www.coursehero.com/file/76722027/POM-Final-examdocx/
Which of the following questions regarding a project CANNOT be answered even if the
critical path of a project is known? *
1 point
How long can each of the activities be delayed without delaying the project?
When is the earliest project completion time?
Which activities should not be delayed?
None of the above
No difference
How activity times are estimated
CPM can be used to monitor project costs, while PERT cannot
PERT can be used for large projects, while CPM is only suitable for simple projects
Critical activities
Noncritical activities
Activities with the most slack
Activities that require the least resources
94 units
95 units
100 units
2,000 units
50 times a year
Every 50 days
Every 9 days
Whenever Item X’s inventory level drops to 50 units
This study source was downloaded by 100000858625340 from CourseHero.com on 12-07-2022 20:19:12 GMT -06:00
https://www.coursehero.com/file/76722027/POM-Final-examdocx/
1 point
21x
50x
40x
None of the above
40 units
48 units (47?)
223 units
None of the above
Php 8,485
Php 16,971
Php 2,000,000
None of the above
Php 8,485
Php 16,971
Php 2,000,000
None of the above
Php 8,485
Php 16,971
Php 2,000,000
None of the above
Zero
Php 8,485
Php 16,971
None of the above
Including its total annual purchasing cost, how much would be Item X's total annual
inventory cost? *
This study source was downloaded by 100000858625340 from CourseHero.com on 12-07-2022 20:19:12 GMT -06:00
https://www.coursehero.com/file/76722027/POM-Final-examdocx/
1 point
Php 2,008,485
Php 2,000,000
Php 2,016,971
None of the above
How many rolls of gauze bandages should be ordered for this period? *
3 points
13 rolls
33 rolls
53 rolls
137 rolls
13 rolls
33 rolls
53 rolls
137 rolls
What's the expected demand during the order interval and lead time? *
2 points
33 rolls
53 rolls
137 rolls
144 rolls
What would have been the desired service level if an order quantity of 142 rolls were
placed when the stock on hand is 30 rolls? (Assume: amount on order and backorder
is zero). *
4 points
95%
96%
97%
99%
This study source was downloaded by 100000858625340 from CourseHero.com on 12-07-2022 20:19:12 GMT -06:00
https://www.coursehero.com/file/76722027/POM-Final-examdocx/
Powered by TCPDF (www.tcpdf.org)
1 point
Php 2,008,485
Php 2,000,000
Php 2,016,971
None of the above
How many rolls of gauze bandages should be ordered for this period? *
3 points
13 rolls
33 rolls
53 rolls
137 rolls
13 rolls
33 rolls
53 rolls
137 rolls
What's the expected demand during the order interval and lead time? *
2 points
33 rolls
53 rolls
137 rolls
144 rolls
What would have been the desired service level if an order quantity of 142 rolls were
placed when the stock on hand is 30 rolls? (Assume: amount on order and backorder
is zero). *
4 points
95%
96%
97%
99%
This study source was downloaded by 100000858625340 from CourseHero.com on 12-07-2022 20:19:12 GMT -06:00
https://www.coursehero.com/file/76722027/POM-Final-examdocx/
Powered by TCPDF (www.tcpdf.org)