You are on page 1of 3

Tips for Reducing

57 Connection Costs
Victor Shneur, P.E.

A little planning goes a long way, especially with respect to steel connections.
These helpful tips should help you keep bolts from driving you nuts, and welds
from torching your temper.

onnections can be expen- tions. Drawings that don’t show actual sive—and sometimes impossi-

C sive, and they can take a lot


of effort to create during
the design and construc-
tion process. How can you
save time and money—and make
everybody’s work easier when work-
ing with connections on fast–track
end reactions can lead to costly and un-
safe connections.

4. Always provide complete load


paths (including transfer forces)
where there are axial forces. Keep load
paths simple.
Favor factored end reactions
ble—copes in the W8.
■ Favor W12 and W14 sections for
typical gravity columns. The dis-
tance between flanges makes web
connections easier.
■ Consider using heavier member sizes
to eliminate stiffeners (see Tip 18).
schedules? Here are some general
guidelines for structural engineers for
5.
(ASD).
(LRFD) over service end reactions ■ Provide adequate flange width at
perimeter members. Provide beams
the design of economical bolted and Provide details that clearly repre- that frame slab openings to support
welded connections for columns,
beams and braces.
6. sent the design intent. They will
eliminate misunderstandings and save
deck and pour stops, and to weld
studs.
Communication is key. Develop a time. Use A36 steel for connection
1. working design-build team for
fast-track projects—with the fabricator 7. Use standard AISC connections
when possible.
12. angles, and plates for typical
connections.
and erector on board. The main bene- Don’t be excessively conser- Specify readily available an-
fits are:
■ Design requirements can be con-
8. vative—connections need to with-
stand only design loads.
13. chor rods. Often, the rods are
delivered in a rush immediately after
veyed accurately. Simplify as much as possible. For the contract has been awarded and be-
■ Everyone’s expertise can be utilized.
■ Detailing can start quickly.
9. example, make column-base de-
tails symmetrical, use the same spacing
fore communication has been estab-
lished between fabricator and engineer.
■ Duplication of work can be avoided. for expansion anchors and minimize When possible, use standard
■ “Revise and Resubmit” on ap-
provals is avoided.
the number of sizes of slab edge clo-
sures/pour-stops. This expedites the
14. tolerances established by
ASTM A6/A6M, the AISC Code of Stan-
■ All parts work together without fabrication and erection process and dard Practice for Steel Buildings and
“surprises.” greatly reduces the number of possible Bridges (www.aisc.org/code), and
■ Paperwork is minimized. mistakes—and repair costs. AWS. Tighter tolerances will increase
■ Your best chance for cost savings. Check structural drawings for costs and construction time substan-
■ Good working environment.
Connection approvals should
10. constructability issues.
Review the member sizes for
tially.
Avoid overly restrictive specifi-
2. occur in a timely manner. Detail-
ers need connections immediately for
11. connection economy:
■ Preferably, a supporting beam should
15. cations.
Don’t “over-specify” details—
fast-track project delivery. Make ap-
proval comments clear. Confusing
have at least the same depth as the
supported beam.
16. you might not be aware of fab-
rication/erection procedures, required
notes cause misinterpretation and ■ Don’t frame W8 beams into the clearances, etc.
more paperwork. webs of heavy W-shapes or plate

3. Engineers should always provide


all end reactions, including shear,
girders. The thick flanges of the
heavier shapes will require exces-
17.

Moment connections:
Eliminate when possible. For exam-
moment, torsion and axial end reac- ple, you can use a cantilever at the

Modern Steel Construction • July 2003


Least Weight Isn’t Heavier Columns Specify ASTM A36
Always Least Cost Minimize Stiffeners Connection Material
roof in lieu of two moment connec- ■ Complete each released area as Never use bolts with the same
tions to the column.
■ Provide actual moments/moment
much as possible.
■ Size members conservatively.
31. diameter but different
strengths on a job—it can lead to mis-
envelopes and vertical end reac- ■ Consider using field-welded con- takes.
tions. nections for openings. Use short-slotted holes in out-
■ Favor extended end-plate moment
connections. Refer to AISC Design
■ Immediately inform fabricator of
the areas of possible substantial re-
32. standing legs of connection an-
gles, end plates and single-plate
Guide 4: Extended End-Plate Moment visions. connections.
Connections for design information. Provide for tolerances—use When loads are large, consider
■ Shop weld short cantilevers.
■ Moment connections to HSS
23. oversized, short-slotted, and
long-slotted holes in bolted connec-
33. larger diameter bolts and/or
ASTM A490 bolts.
columns are usually very expensive. tions, and leave extra space for welded ■ Bolt material cost is roughly propor-
Stiffeners can complicate con- connections. tional to strength.
18. nections for framing beams.
■ Specify only when required. 24. Make embedded plates a min-
imum 6” to 8” larger than re-
■ Higher strength bolts save in con-
nection material, hole making, and
■ Wherever possible, use partial- quired for connections. Field fixes for installation cost.
depth stiffeners. embedded plates that are mislocated Consider excluding bolt
■ AISC’s SteelToolTM Clean Columns
v3.1 can help avoid column stiffen-
are time and money consuming.
Clearly identify all changes
34. threads (X-bolts) for:
■ Heavily loaded connections where
ers. It’s available
www.aisc.org/steeltools.
at 25.
drawings.
and revisions on design typical bolt size doesn’t give enough
capacity.
■ Refer to AISC Design Guide 13: Wide- When shop or field errors re- ■ Shop assembled trusses.
Flange Column Stiffening at Moment
Connections for designing and speci-
26. quire correction:
■ Request an as-built report. It clearly
■ Connections when outer plies are
3
/8” thick or larger.
fying stiffeners. shows the problem and eliminates Use slip-critical connections

19. Favor one-sided shear connec-


tions (single-angle and single-
misunderstanding and misinterpre-
tation.
35. for:
■ Bracing connections with oversized
plate), but avoid expensive through- ■ Discuss possible solutions with fab- or slotted holes.
plate connections at HSS columns. ricator or erector. ■ Field-assembled trusses with over-
Rule of thumb: The more ■ Keep in mind: labor is expensive, sized holes.
20. pieces there are in a connection
detail, the more expensive it is to fabri-
material is relatively inexpensive.
■ As a rule of thumb, fast decisions
■ Members with short/long-slotted
holes when force applies parallel to
cate and erect. and approvals are required to con- the slots.
Give some thought to the de- tinue the work. ■ Built-up compression members.
21. sign of column splices:
■ Do not specify to “develop the full
■ Remember that not every error re-
quires correction.
■ Cyclic loads.
Where fully pretensioned bolts
bending strength of the smaller
shaft.” This is not always necessary. 27. Wherever possible, specify
bearing joints. It makes the
36. are needed, permit the use of
any of the four methods approved by
■ Use field-bolted column splices for most economical use of bolts, elimi- RCSC and AISC:
moderate uplift forces. nates masking or a special paint sys- ■ Turn-of-nut.
■ Minimize the number of splices, es- tem, and reduces installation and ■ Calibrated wrench.
pecially for HSS columns. Some- inspection requirements. ■ Twist-off-type tension-control bolt.
times it is more economical to Use snug-tightened joints as ■ Direct-tension-indicator.
extend the lower shaft for another
level than to add a splice.
28. much as possible.
Favor ¾”-diameter A325 bolts 37. Mechanically galvanized
ASTM A325 bolts provide ex-
■ For W-column splices with PJP or
CJP welds at flanges, favor web
29. for typical structures.
Try to limit bolt diameters to
cellent corrosion resistance and require
a minimum overtapping of nuts and
channel(s) over temporary flange
lugs wherever possible. This will
30. 1” or smaller. Larger diameters
require special equipment, larger spac-
easier pretensioning.
Keep your bolt holes as ra-
make detailing, fabrication and
erection easier.
ing and edge distance, and special 5/16”-
thick washers (ASTM F436) for fully
38. tional as possible:
■ Don’t use different hole sizes in the
Design-build projects require pretensioned ASTM A490 bolts. same member. It leads to mistakes
22. extra attention:

July 2003 • Modern Steel Construction


Keep Bolt Holes Member Reactions Single-Pass Fillets
One Size Per Piece Simplify Detailing Are Cost-Effective

and slows fabrication because shop hydrogen process: “Minimum weld


re-tooling is required for the piece. size is dependent upon the thinner of
■ Don’t specify slots in material the two parts joined.” Favor Fillet Welds
thicker than bolt diameter plus 1/8”.
The AISC Specification doesn’t allow 44. Use intermittent fillet welds
when possible.
Over Groove Welds
punching holes in such material, Use AISC Specification Appen-
and it is difficult to make slots. A
good alternative would be to use
45. dix J2.4 for fillet welds. This al-
lows an increase in strength of the fillet
oversized holes. weld based on direction of the force. Slip-Critical Joints
■ Use the same oversized holes in all Note: Per AISC it is also acceptable for ex-
plies if it is possible. tended end-plate moment connections. Only When Needed
■ Use long-slotted holes in girts and Favor fillet welds over groove
any members that must be field-
aligned to tolerances other than
46. welds. Groove welds are usu-
ally more time consuming.
standard steel framing tolerance (for Favor PJP welds over CJP
example, curtain wall connections).
Correctly apply AISC require-
47. welds.
Allow full-strength connec-
39. ments for fillers:
■ Fillers in slip-critical joints are not
48. tions in lieu of CJP welds in
statically loaded structures. Fillet
required to be developed. welds up to ¾” are more economical.
■ Fillers up to ¼” thick can be used in Specify effective throat size or
bearing joints without reduction in
strength.
49. required strength for welds.
Allow the use of groove-
■ Fillers up to ¾” thick don’t have to be
developed if the design shear strength
50. welded joints with a prepara-
tion that minimizes weld metal
of the bolts is multiplied by the factor volume.
[1 - 0.4(t – 0.25)], where t is the total
thickness of the fillers up to ¾”.
■ Fillers over ¾” must be developed
51. Leave weld access holes open.
Inspect critical CJP welds with
by bolts or welds, in or outside of
the joint.
52. Ultrasonic Testing (UT).
Avoid the “weld-all-around”

40. Leave extra holes open. In al-


most all cases they don’t need
53. symbol. It is expensive, and in
a lot of cases it’s not required—and
to be filled, and filling takes a lot of sometimes it’s even prohibited.
time (think labor costs), especially for Avoid shop welding on galva-
thick members. 54. nized surfaces.
Layout welds to reduce re-
41.

Avoid over-welding.
The weld doesn’t need to be
55. straint, especially for large
welds. This lowers the possibility of
stronger than base metal in any lamellar tearing.
case. Favor horizontal and flat posi-
■ Excessive welding can cause serious
problems (distortion, cracking, etc.).
56. tions. Let gravity work for you.
Try to minimize field-welded
This can lead to expensive repairs or
even rejections.
57. connections and favor field-
bolted connections. ★
■ Weld connection elements for actual
forces. Victor Shneur, P.E. is a chief engineer
Use single-pass fillet welds with LeJeune Steel Company in Minneapo-
42. where possible. A 3/8” fillet
weld requires 44% more material and
lis, MN. He is a member of the AISC Com-
mittee on Manuals and Textbooks. This
100% more labor, but it is only 20% article was adapted from the paper Mr.
stronger than a 5/16” fillet weld. Shneur submitted for the 2003 NASCC,
Use AWS D1.1 rules for mini- “How to reduce the cost of common struc-
43. mum weld size. Per AWS
D1.1/D1.1M:2002, Table 5.8, for low-
tural steel connections.”

Modern Steel Construction • July 2003

You might also like