You are on page 1of 28

The World's Leader in Two-Piece Capsules™

Your Natural Partner ™

The design
and operation
of a facility
for filling hard shell
gelatin capsules

Graham C. COLE
Summary percent up to 15 percent of the total installed capi-
tal cost of the plant and equipment. The Food &
Hard Shell Gelatin Capsules are a very popular Drug Administration (FDA) (USA) takes the view that
and convenient method of administrating drugs to if it hasn't been written down then it hasn't been
patients for conventional dosages and more sophis- done !
ticated regimes such as sustained release. The
Whether the project is a new grassroot facility or
shells can be filled at high speed, they provide ready
refurbishment of an old building or area, then valida-
identification, are easy and pleasant to take by mas-
tion considerations must be taken on board by the
king bitter tasting drugs and are robust.
design team from day one.
There are also advantages in developing a cap-
In each section only the production methods, the
sule product as opposed to a tablet, for the formu-
facility and the equipment required for powder filling
lator and the company filling the shells. (1) Many
operations will be evaluated.
combinations of products can be filled (Figure 1).
Some processes used to prepare the product can
be complex, for example extrusion and spheronisa-
tion and it is necessary to consider this multiciplicity About the author
in the design and operation of the manufacturing
Graham Cole is a chemical engineer with over 35
operation.
years experience in the Pharmaceutical Industry. He
Current Good Manufacturing Practice (cGMP) has a degree in technology with the Open Univer-
and the demands of the regulatory authorities sity, is a Fellow of the Institution of Chemical Engi-
world-wide requires greater care in the design of neers of Great Britain and is a Chartered Engineer.
manufacturing facilities, the selection of materials
He entered Glaxo Laboratories as a Laboratory
used in their construction, their layout, the equip-
Technician in 1955 leaving in 1961 to join Aspro-
ment used in the preparation of the materials to be
Nicholas Process Development group where he
filled and the filling operation itself. This paper will
became Manufacturing Manager. He joined Merck
present some ideas and suggestions based on
Sharp and Dohme in 1966 where he was respon-
cGMP in three areas:
sible for process development, process automation,
• the design and layout of the building, equipment evaluation and facility design. In particu-
• the evaluation and selection of equipment, lar, he introduced many of Merck's capsule filling
• validation. processes into facilities in Europe. Latterly he was
with Davy McKee (now part of Kvaerner Process), a
The higher standards that are demanded can re-
pharmaceutical engineering contractor and now has
sult in higher costs, however by careful design
his own consultancy which started in 1991. He has
these costs can be reduced and in many cases eli-
published many articles and papers on solid dosage
minated completely.
form development and published a book on Phar-
Validation is an extra cost which must be incor- maceutical Production Facilities (now in its second
porated into the overheads and whether an outside edition). He has also contributed to books on Hard
consultant is used or internal resources are used, it Capsules (their development and technology) and
still has to be met. Estimates of cost range from 2-3 Pharmaceutical Coating Technology.
ÀÀÀ
,,,
@@@
€€€ÀÀÀ
,,,
@@@
€€€
,,,,
,,,
@@@
€€€
ÀÀÀ ,,,, ,,,, ,,
@@
€€
ÀÀ
,,,
@@@
€€€
ÀÀÀ
,,
@@
€€
ÀÀ ,,,
@@@
€€€
ÀÀÀ
,,,
@@@
€€€
ÀÀÀ ,,
@@
€€
ÀÀ
,,,
@@@
€€€
ÀÀÀ
,,
@@
€€
ÀÀ ,,
@@
€€
ÀÀ
,,,
@@@
€€€
ÀÀÀ
,,
@@
€€
ÀÀ
,,,
@@@
€€€
ÀÀÀ
,,,
@@@
€€€
ÀÀÀ
,,,, ,,,, ,,,,,,,
,,,,
,,,
@@@
€€€
ÀÀÀ,,,
@@@
€€€
ÀÀÀ ,,,
@@@
€€€
ÀÀÀ,,,
@@@
€€€
ÀÀÀ
,,,,,,,

ÀÀÀ
,,,
@@@
€€€
,,,, ,,,,
,,,
@@@
€€€
ÀÀÀ ,,
@@
€€
ÀÀ ,,
@@
€€
ÀÀ ,,
@@
€€
ÀÀ
,,,,,,,
,,,,
,,,
@@@
€€€
ÀÀÀ
,,,
@@@
€€€
ÀÀÀ
,,,, ,,,, ,,,,,,,
,,,,
,,,
@@@
€€€
ÀÀÀ,,,
@@@
€€€
ÀÀÀ ,,,
@@@
€€€
ÀÀÀ,,,
@@@
€€€
ÀÀÀ
,,,,,,,
,,,, ,,,,
,,,
@@@
€€€
ÀÀÀ
,,,,,,,
,,,
@@@
€€€
ÀÀÀ
ÀÀÀ
,,,
@@@
€€€ ,,,,
,,
@@
€€
ÀÀ ,,,
@@@
€€€
ÀÀÀ ,,
@@
€€
ÀÀ ,,
@@
€€
ÀÀ
,,,,,,,
,,,, ,,,,
,,,
@@@
€€€
ÀÀÀ ,,,
@@@
€€€
ÀÀÀ,,,
@@@
€€€
ÀÀÀ
,,,
@@@
€€€
ÀÀÀ
,,,
@@@
€€€
ÀÀÀ
ÀÀ
,,
@@
€€ ,,,,,,,
,,,, ,,,,,,,

,,,
@@@
€€€
ÀÀÀ
,,,, ,,,,
,,
@@
€€
ÀÀ ,,
@@
€€
ÀÀ ,,
@@
€€
ÀÀ
,
@
€
À
À@,À€ €@,À€@,À€@, À€@,À€@,À€@,À€@,À€@,

,,,,,,,
,,,,
,,,
@@@
€€€
ÀÀÀ
,,,
@@@
€€€
ÀÀÀ
,,,,
,,,
@@@
€€€
ÀÀÀ,,,
@@@
€€€
ÀÀÀ ,,,
@@@
€€€
ÀÀÀ,,,
@@@
€€€
ÀÀÀ ,,
@@
€€
ÀÀ ,,,,,,,
,,,, ,,,,,,,

,,,
@@@
€€€
ÀÀÀ
,,,,
,, ÀÀÀ
@@
€€
ÀÀ ,, ÀÀÀ
@@
€€
ÀÀ ,,
@@
€€
ÀÀ
,,,,,,,

,,, ,,,, ÀÀÀ


@@@
€€€
ÀÀÀ
,,,
@@@
€€€
ÀÀÀ ,,,,
,,,
@@@
€€€,,,ÀÀÀ
,,,
@@@
€€€,,,
@@@
€€€
,,,,,,,
,,,,
@@@
€€€
,,,, ,,
@@
€€
ÀÀ ,,,,,,,
,
@
€
À

,,,,,,,
,,,, ,,,,,,,
,,,,,,,

ÀÀÀ
€€€
@@@
,,,
À
,
@
€

,,,
@@@
€€€
ÀÀÀ ,,,
@@@
€€€
ÀÀÀ
1 2 3 4 5 6 7 8 9 10

,,,,
@@@@
€€€€
ÀÀÀÀ
,
@
€
À

ÀÀÀ
€€€
@@@
,,,
,,,
@@@
€€€
ÀÀÀ
,,,,,
,,,
@@@
€€€
ÀÀÀ ,,,
@@@
€€€
ÀÀÀ
pellet mixture powder granulate solid form drug preparations 1st pellet type 2nd pellet type capsules paste

,,,,
@@@@
€€€€
ÀÀÀÀ
,,,,,,,,,
,,,,,
,,,
@@@
€€€
ÀÀÀ ,,,,,,,,,
€À€@, @,À,À€@

,,,,, ,,,,,,,,,
,,,,,,,,,
@,

Figure 1. Various combinations of different drug formulations in capsules.

2
The design and operation of a facility
for filling hard shell gelatin capsules

Graham C. COLE

Chapel Hall,
Middle Green, Higham,
Bury St Edmunds, Suffolk IP28 6NY,
United Kingdom

Table of contents 1.0. Facility design and


equipment requirements
1.0. Facility design and There are many different products that can be
equipment requirements filled into hard shell capsules, ranging from a single
powder substance, through mixtures of powders to
1.1. Process concept
pellets and tablets and combinations of any of
1.2. Warehousing
these. Powder filling only will be considered here
1.3. Dispensary
and it is assumed that capsules will be available
1.4. Process
ready printed.
1.5. Layout and design of facility
In the development and implimentation of any
project there are a number of objectives that must
2.0. Evaluation of hard shell gelatin
be addressed.
capsule filling equipment
a. What type of products are to be handled?
2.1. Pharmaceutical evaluation Are they highly potent? Can they cause allergic
2.2. Mechanical evaluation reactions in the operators? Are they mutagenic?
2.3. cGMP and Validation – to name but a few.
2.4. Summary
Current Good Manufacturing practice suggests
there are two overriding considerations that take
3.0. Validation of hard gelatin capsule filling precedence.
equipment and ancillary services
These are:
3.1. Scope of documentation
3.2. Validation protocol for a MG2 G37 N • total containment of the product within a clo-
capsule filler sed system,
3.3. Summary • providing a barrier between the product and
the operator i.e. total protection.

4.0. Conclusion b. Are these products beta-lactams eg peni-


cillin?
If this is the case then a separate manufacturing
5.0. References facility must be designed.

3
c. What quantities and mix of products are re-
quired? Preparation of the formulation
for filling requires the following steps:
There may be relatively small quantities of a num-
ber of products required rather than large quantities
of individual products. In one case, flexibility of the
operation is the main objective requiring a multi- From Warehouse
plexity of services whereas a single dedicated pro-
duction line can save on materials handling, person-
nel, and special conditions (protection from light Dispense Ingredients
Production Area Transfer to
and oxygen). Dispensary Production Area

Some products require complex processing ope-


rations to modify the availability of the drug in the Mill/Sieve Operation
Mill Transfer to Blending
patient. For example pellets provide a mechanism not always necessary Equipment
to sustain the release of the drug over long periods.
To produce and fill both the active and placebo pel-
Blend
lets into capsules requires both good formulation Blender Transfer to Filling
and efficient unit operations. The filling of thixotropic Equipment

substances may also be an option.


Filling Machine Fill
The design and operation of a facility which in-
cludes these manufacturing operations is not cove-
red in detail in this paper, but many of the principles
are, and it is important to be aware that in the de- Storage
Quarantine
Quality Control
sign of any operation changes may occur in the fu- Prior to Release for
ture which should be considered at the conceptual Packaging
stage.
Packaging Pack
A five year forecast of what requirements will be
needed as there may be new capsule products co-
ming through from Research and Development and Dispatch
some older products may be declining in volume.
These factors should be assessed in the design of a
new facility, the refurbishment of an existing opera- Figure 2. Flow diagram for capsule filling.
tion or in selection of new equipment for develop-
ment and production purposes.
The building may be an adjunct to an existing
operation and the site will provide ancillary person-
1.1. Process concept nel services, the necessary process services (elec-
tricity, heating, HVAC etc) and control laboratories.
To design the facility requires an understanding Where this is not the case (eg green field sites) then
of the overall capsule filling process. The building an allowance must be made for these requirements.
and building services provide the envelope around
the process and the process operation must be A simple flow diagram is shown in Figure 2. All or
performed in areas designed to conform to current some of these operations take place whether in a
Good Manufacturing Practices (cGMP). It will also laboratory or on a production scale.
need a Validation Programme.
For efficient and accurate operations the follo-
For any capsule filling operation there are four wing stages must be assessed.
essential requirements:
• a supply of empty shells, • storage of empty and filled capsules - ware-
housing,
• a supply of powder,
• the process equipment, • raw material dispensing,
• a building to house the equipment, raw mate- • process operations, milling, mixing and filling,
rials and finished product. • packaging.

4
1.2. Warehousing Capsules are sensitive to extremes of tempera-
ture and humidity which depend on the local envi-
In all companies the size of the inventory is criti- ronmental conditions. Storage areas should be de-
cal to the efficient operation of any plant. More and signed to be environmentally controlled to between
more companies are employing Just-in-Time (JIT) 10° C and 30° C and 30 per cent and 70 per cent
relative humidity. Providing the capsules are in sea-
concepts to minimise stock levels and ensure that
led containers, then damage can only occur if the
First in First Out (FIFO) principles apply. A typical warehouse has windows which permit sun to shine
flow diagram is shown in Figure 3. on the containers, producing localised overheating.
Similarly if containers are placed close to a heating
Supplier source within the plant, then distortion of the shell
body and cap will occur. If a machine is operating at
90,000 filled capsules per hour (cph) then one da-
Delivery maged capsule in 10,000 causes a problem on the
Bulk filling machine or the presorter every six to seven
Sacks minutes.
Bottles
Drums Capsules are supplied in containers ranging from
Packaging Components 50,000 for size 000 to 500,00 for size 5. The ware-
Hold/Quarantine
Identify
house will need to allocate sufficient storage loca-
Label tions with adequate capacity for the number of pro-
Sample ducts produced per month and reserve storage
Test depending on what JIT rules exist. (Each storage lo-
Fix Accept/Reject Label
Stack cation generally will hold four containers and depen-
Accept/Reject ding on the size of capsule, this represents 20,000
Return to Supplier (size 000) to 2,000,000 for size five.
Order Transport
Restack In addition storage space must be available for
Reload raw materials and finished stock.
Collation
Unstack The simplest way of handling all these require-
Repack
ments is by installing a computer controlled Mate-
Transfer rials Management System. This records incoming
Compagny Pallet goods, allocates location, and notifies internal de-
Secure/Skin partments of the arrival of these goods. The status
Computer Operation
Scans Storage for an Empty
Location

Transfer to Storage Area


Update Computer Inventory

L.F.B.
Production Demand L.I.W.
Feeders

I.B.C.
Computer Operation
Scans Storage Locations for
Required Materials
Load Check
Transfer cell weight
One lance
Dispensary/Production Silo
per hopper

Dispense L.I.W. Loss in weight


Print label L.F.B. Laminar flow booth
Up-date Inventory-Recorder I.B.C. Intermediate bulk container
Initiate Recorder Procedure Air flow

Figure 3. Flow diagram for storage of materials. Figure 4. Schematic of a pharmaceutical dispensary.

5
Vacuum unit

Discharge station Receiving station

BIN BIN

First floor

Process
machine
Process ground floor

Figure 5. Automated materials handling.

of the material can be controlled using the compu- Balance 1 0 - 1.0 kg (sensitivity 0.01 mg)
ter and with limited personnel access the Quality Balance 2 0-10 kg (sensitivity 500 mg)
Control Department can provide means of quaranti- Balance 3 0-50 kg (sensitivity 1.0 g)
ning the materials until they are passed for produc- In some cases a floor balance may be installed
tion use or sale. Bar codes are now widely used to for larger quantities up to 200 kg. It should be re-
identify products. membered that the cost of balances increases with
their sensitivity. These balances will need to be loca-
ted in cubicles in the dispensary, so that there is no
danger of cross-contamination and different pro-
1.3. Dispensary ducts can be weighed out simultaneously. An area
A schematic example is shown in Figure 4. should be provided for the short term storage requi-
rements of materials used in large quantities and an
The size and equipment required will depend on adjacent area should be provided for materials used
the scale of the operation and the nature of the ma- in small quantities ie colours and surfactants.
terials being dispensed.
Each cubicle should be equipped with laminar air
All balances will be selected on the basis of flow to ensure maximum protection for the operator,
their sensitivity and range of weights required. For minimise dust contamination of the surrounding
example: area and cross contamination.

6
IBC IBC IBC
To Air
suction unit

Powder Empty Filled


shells capsules
Power also
required for
control panel
on outside of
cubicle

C/A 6
Capsule filler
3 phase 1 2 3
4
5
Elect.

Single phase Single phase elect.


House elect. from
vacuum 5 Linked to
capsule filler PMCS system

1) Capsule deduster and sorter C/A : Compressed air


2) Metal detector Elect. : Electricity
3) Interceptor PMCS : Process monitoring and
4) Checkweigher & bench control system
5) Label printer IBC : Intermediate bulk contrainer
6) Scales bench mounted

Figure 6. Capsule filling cubicle.

Each dispensary should be equipped with sui- selection of the milling and sieving equipment will
table dust masks, air supplied suits, safety showers depend on the required physical specifications of
and eye wash stations, to ensure the maximum safe the material. Some material is supplied in specific
handling of the materials. A carefully designed size fractions that only necessitates breaking down
Heating, Ventilating and Air Conditioning (HVAC) the agglomerates. On the other hand, some mate-
and dust extraction system is a major requirement. rial such as the active, may need to be milled to
produce material in a specific size range say, 0-5
1.4. Process µm for optimum therapeutic activity. Here a fluid
energy mill will be required.
The next stage in the material handling pro-
cedure is to transfer the batch of raw materials to The layout of the process area will depend on the
the production area for preparation of the powder material handling concept. For simple manual trans-
mix ready for capsule filling. Two unit operations fer (using Bins and Scoops) each piece of equip-
may be necessary here. The objective is to produce ment is operated on a stand alone basis. If pneu-
a homogeneous free flowing powder mix. This may matic transfer is used for an automatic transfer
require pretreatment of one or all of the ingredients operation, then the mill can be linked to the blender
and it may be necessary to mill or sieve these and the blender to the capsule filler or an interme-
materials to produce a uniform particle size. The diate bulk container (IBC) (see Figure 5).

7
sieve
Mill/

Mix
Raw materials warehouse
Fill
Dispense

Air lock
Wash

Plant Production
Capacity 432 pallets
Collate
process
In

M F Packing
Finished goods warehouse
Stones

Change
Engineering
Quarantine

Male Female Labels Test Office Goods Goods


lockers lockers in out

Admin Lab
Lobby
Canteen

M : Male
F : Female
Admin : Administration

Figure 7. Capsule filling facility layout.

Figure 6 shows a section through an automated capsules are then gravity fed into the blister packer
feed and receiving system for a capsule filler. This or securitainer filling unit.
unit is linked to a Process Monitoring and Control
The objective in all these operations should be to
System (PMCS). Powder and empty capsules are
minimise manual transfer and reduce exposure and
fed under gravity from an IBC and the filled cap-
contact of the product to the operator and the
sules are transferred back to a third IBC. The inter-
environment.
ceptor in this concept is designed to remove excess
dust from the capsule filling operation and capsule At this stage it is useful to produce an equipment
sorting and dedusting operation. For an automated list and equipment data sheets. In the conceptual
system, filled capsules can be stored in an IBC until stage the designer is mainly concerned with the
released to packaging and the IBC can be posi- dimensions, weight, service requirements, links to
tioned above the packaging unit and the filled adjacent equipment and control services. It is also

8
necessary to have an idea of the amount of manual process area into a lower grade technical area. This
intervention that will be required. While labour may means that process utilities can be serviced without
be very cheap in some parts of the world, automa- interfering with manufacturing operations Each
ted handling and control is more reliable. access door from the maintenance corridor and
entrance door to each cubicle from the central
production area is fitted with an interlock so that
1.5. Layout and design of facility both doors cannot be opened simultaniously. This
concept is illustrated in Figure 8. A comparison with
A typical layout is shown in Figure 7. Figure 9 shows how the expensive process space
Process areas require high quality finishes to has been reduced. Figure 10 shows a section
maintain cGMP standards. Traditionally pharma- through this type of facility. Figures 11 and 12 show
ceutical secondary manufacturing facilities have the layout of a traditionnal solid dose manufacturing
been designed on the basis of single rooms or facility and all of these drawings have been shaded
cubicles for each stage of the manufacturing to show the grading of each area e.g. light grey,
process. Transfer of materials has been accom- dark grey and black. These gradings refer to the
plished using a large drum or mobile trolley. Today quality of the air required in each area and the
the industry is investing in more automatic transfer quality of the finishes required, Black will require
systems for material handling in an attempt to minimum standards and light grey the maximum.
reduce costs and improve yields. This results in a Figures 13, 14 and 15 illustrate the concept re-
more integrated manufacturing unit. Computer Inte- quired for an automated facility. It is important to
grated Manufacturing (CIM) is becoming more note here in comparison with Figures 11 and 12,
widely used in the Pharmaceutical Industry to the considerable savings that can be achieved in
reduce labour costs, improve efficiency and in- building costs by reducing the size of the buildings
crease yields. It also reduces the size of the building footprint and of the process area. The traffic floor
and the high cost areas within that building for each (Figure 15) illustrates the pathway for the move-
manufacturing operation. The objective is to remove ment of IBC's for feeding and receiving product
as many of the service functions outside of the from the process equipment on the floor below.

9
Detailed sections

Light grey
Black
HVAC and automated
handling Bin stations HVAC : Heating
ventilating
and air
Air handling unit conditioning

Technical
area
Process
Utilities booth
corridor
access
Personnel

Process
equipment

Figure 8. Detailed section through an automated manufacturing facility.

Light grey
Black
HVAC and Flow and return Bin on Parking
automated handling bin stations AGV bin stations HVAC : Heating
ventilating
and air
Air handling unit conditioning
AGV : Automated
guided
Technical Process vehicule
area booth

Process
corridor
access
Personnel

Utilities
equipment

Figure 9. Detailed section (contained equipment) through an automated manufacturing facility.

10
Light grey
Storage HVAC plant room Dark grey
Black
Packaging Process Process HVAC : Heating
ventilating
and air
conditioning

Figure 10. Section through a traditional manufacturing facility.

Goods in/out Light grey


Packing hall Dark grey
Restaurant
Black
Storage

Engineering Process
change

Process booths

Personnel in/out

Utilities
plant

Process booths

Figure 11. Ground floor layout – Traditional.

Black
Space savings
HVAC : Heating
Storage ventilating
and air
conditioning

Engineering
Admin,
restaurant

HVAC plant room

Figure 12. First floor layout - Traditional.

11
Light grey
Dispensary
Dark grey
HVAC plant room and automated handling Black
BS
Space savings
Storage
BS Bin stations
Packaging Process Technical Process
Product movement
HVAC : Heating ventilating
and air conditioning

Figure 13. Section through automated and non-automated manufacturing facility showing flow of material.

Goods in/out Light grey


Packing hall Dark grey
Restaurant Black
Storage
Space savings
Packaging
change

Engineering
Engineering
change

Process Process booths


Personnel in/out
booths Process
Technical area change
Flameproof technical area
Process Utilities
booths plant

Figure 14. Ground floor layout for an automated facility.

Light grey
Dark grey
Storage Admin,
restaurant Black
Space savings
F Flow stations
Packing lines below R Return stations
F F F F F
Parking stations
F F F F F
Traffic flow
F F F F F
Process booths below
F R R F R F F R F R F R F F Admin : Admistration
HVAC : Heating
Flameproof technical Technical area below ventilating
area below and air
HVAC plant room conditioning
Process booths below Process booths below
F F R F F R F R F R F R R F F F R R F F R

Figure 15. First floor layout for an automated facility.

12
Table 1. Automatic hard gelatin capsule filling machine (updated October 1999).

Continuous Motion Machines


Machine Type Capsule Sizes Theoretical Dosing Principle Pellet Filling Tablet Filling Liquid and Paste Comments
Output Per Hour (powders) Filing
(powder filling)
MG 2
MG COMPACT 000-5 6-48000 Yes Yes Yes Unit for
MG FUTURA 000-5 6-48000 Yes Yes Yes extrusion
G 38/N 00-5 60000 Yes - - of
G 60 00-5 60000 Yes Yes - high solids
G 60/NETT 00-5 60000 Dosator Yes Yes - content
G 37/N 00-5 100000 and piston Yes Yes - pastes is
G 100 00-5 100000 Yes Yes - available
G 120/N 00-5 120000 Yes Yes - for G 36, MG
G 120 00-5 120000 Yes Yes - Compact and
G 120/NETT 00-5 120000 Yes Yes - MG Futura.
IMA
ZANASI DIVISION
MATIC 60 E/F 000-5 60000 Dosator Yes - - -
MATIC 90 E/F 000-5 90000 and piston Yes - - -
MATIC 120 000-5 120000 Yes - - -

Intermittent Motion Machines


Machine Type Capsule Sizes No. of Capsules Theoretical Dosing Pellet Filling Tablet Filling Liquid and Paste
Per Segment Output Per Hour Principle Filling
powder filling) (powders)

ROBERT BOSCH
GMBH
GKF 130 00-5 1 7800 Yes Yes Yes
GKF 400 S 00-5 3 24000 Tamping and Yes Yes Yes
GKF 700 S 000-5 5 42000 disc dosing Yes Yes Yes
GKF 2000 S 00-5 18 150000 Yes Yes Yes

HARRO
HOEFLINGER
KFM III-I 00-5 1 4800 Tamping and Yes Yes Yes
KFM III 00-5 3 15000 disc dosing Yes Yes Yes

ROMACO MACOFAR
CD-5 00-5 1 6000 Yes Yes -
CD-20 00-5 3 20000 Dosator and Yes Yes -
CD-40 00-5 6 40000 piston Yes Yes -
CD-60 00-5 10 66500 Yes Yes -

IMA
ZANASI DIVISION
ZANASI 6 E/F 000-5 1 6000 Yes Yes Yes
ZANASI 12 E/F 000-5 2 12000 Yes Yes Yes
ZANASI 25 E/F 000-5 4 25000 Yes Yes Yes
ZANASI 40 E/F 000-5 6 40000 Yes Yes Yes
ZANASI PLUS 8 E/F 000-5 1 8000 Dosator and Yes Yes Yes
ZANASI PLUS 16 E/F 000-5 2 16000 piston Yes Yes Yes
ZANASI PLUS 30 E/F 000-5 4 30000 Yes Yes Yes
ZANASI PLUS 48 E/F(*) 000-5 6 48000 Yes Yes Yes
ZANASI PLUS 70 E/F 000-5 9 70000 Yes Yes Yes
ZANASI PLUS 85 E/F 000-5 11 85000 Yes Yes Yes

BONAPACE
Dosator and
RC 530 000-5 6 34000 piston Yes Yes Yes

If a customer buys a PLUS 85 and then needs to work 00 or 000, he can buy the size parts and work with 9 elements (ZANASI PLUS in the 70 configuration)
TM
With the necessary size change parts CONI-SNAP SUPRO sizes A - E can be filled an all types of filling machine.
(*) ZANASI PLUS 48 E/F can be later upgraded to ZANASI PLUS 85.

13
2.0. Evaluation of hard shell gelatin 2.1. Pharmaceutical evaluation
capsule filling equipment A typical formulation will contain all or some of
Although improvements in the encapsulation the following:
operation have taken longer to achieve than is the • active,
case for the tablet making process, the capsule • diluent/disintegrant,
filling machine manufacturers today offer an impres- • surfactant,
sive range of machines with varying degrees of so- • flow aid,
phistication and automation. See Table 1. Even • lubricant.
hand filling and semi-automatic machines which rely The preparation of the powder formulation is cru-
heavily on the dexterity of the operator, have been cial to the performance of the filling equipment, but
improved to comply with current Good Manufactu- before the product is tested on the equipment, cer-
ring Practices, and should be evaluated from this tain basic information can be derived by using a
viewpoint. placebo formulation. No placebo formulation can
It is important firstly to recognise that different exhibit the exact characteristics of the formulation
containing the active, but by careful formulation de-
filling techniques are employed by the various ma-
sign and optimisation many physical parameters of
chines on offer. These include:
the product can be reproduced. Some examples
• the volume fill (Figure 16), are given here.
• the auger feed system (Figure 17), At least three different powder mixtures are nee-
• the tamping method (Figure 18), ded for a satisfactory evaluation. Suitable formula-
• compression filling - intermittant (Figure 19), tions are as follows.
• compression filling - continuous (Figure 20),
• the vacuum filling method (Figure 21), Coarse powder (fill-weight 250.0 mg): lactose
coarse grade 246.0 mg + colloidal silicon dioxide,
• liquid fill/ thixotropic mixtures (Figure 22).
1.5 mg + magnesium stearate, 2.5 mg.
It should also be understood that the physical Fine powder I (fill-weight 250.0 mg): lactose fine
treatment of the powder and its storage prior to use grade, 246.0 mg + collidal silicon dioxide, 1.5 mg +
can effect the overall performance of the capsule magnesium stearate, 2.5 mg.
filling operation.
Fine powder II (fill-weight 200.0 mg): lactose fine
Essentially the programme will be divided into grade, 160.0 mg + maize starch, 38.0 mg + ma-
two parts; pharmaceutical appraisal and mechanical gnesium stearate, 2.0 mg.
appraisal. This programme will identify the objec- A Coarse Powder is defined as having a particle
tives and answer such questions as: size fraction of between 5 µm and 250 µm with 75
• what capacity (output) is required, % by weight of over 100 µm and fine powder bet-
ween 5 µm and 100 µm with 75 % by weight below
• is the equipment required for laboratory, pro- 50 µm.
cess development or production purposes,
• is it proposed to establish a standard range of The examples given of fill weight will depend on
units from laboratory through process deve- the capsule size required, the total quantity of pow-
lopment to production (if this approach is der required, the type and output of the equipment
adopted then alternative equipment should be under test. The method of preparation, storage ma-
evaluated to ensure a back-up position when terial handling and conditions under which the tests
or if problems develop with the preferred sup- take place must be standardised as much as pos-
plier), sible. Powder such as lactose and magnesium
• does the equipment comply with current Good stearate should be taken from the same original
Manufacturing Practice (cGMP), batch to minimise batch to batch variation. The im-
portant physical parameters that need to be stan-
• what validation problems exist,
dardised are:
• what is the effect of using different types and
suppliers of capsules, • Flow,
• safety aspects. • Bulk density (both apparent and tapped),
• Powder cohesion.

14
Stroking-in and
tamping device Dosage
hopper
Agitator
Auger feed
Mechanism

Capsule Dosing Powder or Pick-up ring for


body disc granulate capsule bodies

Figure 16. The volume fill. Figure 17. The auger fill feed system.

Transfer station Tamping stations

6th step 5th 4th 3rd 2nd 1st step


punch
Tamping

Dosage
block
Deflector

Dosage
tube
granulate
Powder of

Dosage
punch
Dosage
Transferred

hopper
plug

Capsule body
Capsule body Base plate Dosage disc bushing

Figure 18. The tamping method. Figure 19. Compression filling - intermittent.

1 2

Dosage tube
Dosage punch
Dosage Vacuum Flow of air
trough

Dosage Dosage
trough tube
Dosage Plastic piston
punch with filter
3 4 Dosage
tube Capsule body
Dosage bushing
trough
Formation of the plug
Capsule body
Capsule body bushing
bushing
Transfer slug to the
capsule body

Figure 20. Compression filling - continuous. Figure 21. The vacuum filling method.

15
The dosage piston moves to allow a certain amount
1 of the liquid fill to enter the dosage chamber.
The stirrer revolves, aiding the transfer
2 of the fluid fill into the dosage chamber

Jacketted Product 3
Container
The filling needle descends,
cutting out the flow of liquid
Liquid Fill and revealing the entrance of
2 the control valve,
Stirrer prior to product delivery.

Control
Dosing piston Valve

Outlet
Valve 4
Filling Needle
The dosage piston moves to
Capsule Body Capsule deliver the measured dose of
Body liquid fill, via the control valve,
Bushing to the waiting capsule body.

Top View The filling needle returns to


5
its original position.

Figure 22. Liquid / Semi-Solid Dosage Method

Their relative importance will depend on the Once it is decided to perform a full scale trial,
equipment under test, for example flow and bulk then these trials should be divided into a number of
density will be critical on machines such as the phases which subject the machine to both ideal and
Parke Davis Model 8 which depend on volume fill non-ideal operating conditions. A log should be
and all three on high speed equipment such as the maintained to record faults that develop and the
MG2 G37 N. time taken to clear. From this time event log (an
It is not proposed to detail test methods here, example is shown in Table 2) a general indication of
but measurements of flow using the angle of re- the machines performance can be derived, for
pose, flow out of hoppers, measurement of cohe- example operating output against theoretical out-
sion using shear cells and bulk density are descri- put, the number of faults that occur and the time ta-
bed in Chapter 8 of Hard Capsules (2). ken to clear them. Comparison can also be made
The number of empty shells required (again they for change over times from one size to another and
should be all from the same batch) will depend on cleaning requirements.
the filling rate of the equipment under test and the
length of time it is proposed to operate. For produc-
tion trials it is proposed that the number of shells re- Test procedure
quired will be in the order of 500,000 Coni-Snap
capsules, 500,000 of an alternative capsule and say To carry out the test, set up the machine with
200 kg of the selected placebo formulation. each type of powder in turn and run under ideal
conditions, applying the following criteria for the ap-
The initial tests should be conducted to derive praisal of the machine.
basic pharmaceutical and mechanical data such as
optimium filling speeds and change over times from 1. Uniformity of weight between individual
one size to another eg size 1 to size 3. capsules.

16
2. Uniformity of weight between groups of
Placebo Material - Formula 1
capsules.
Start Action Remarks Sample
3. Uniformity of closure of capsules.
time Number
4. General appearance of capsules and
11.10 Start Relative Humidity 45-50
need for cleaning.
cer cent, at 21 C.
5. Need for polishing capsules. 11.13 Tachometer reading 158,000 c.p.h. 1
6. Proportion of rejects. 11.14 Stop Unopened reject capsules
7. Time spent clearing operating faults. three per minute

8. Output of capsules. 11.15 Start Unopened reject capsules


five per minute
9. In-process control of fill-weights.
11.19 Stop Blocked empty capsule feed tube
10. Maintain a time event log.
11.19 Start
The machine should then be run under non-ideal 11.20 2
conditions. 11.28 Stop Blocked empty capsule feed tube

1. Hopper: allow the powder to fall to a low level 11.19 Start

in the hopper, and check the weight variation 11.30 3

of the filled capsules. 11.33 Stop Broken capsule in upper bush

2. Examine the effects of changing the tempera- 11.34 Start Powder flowing from hopper due to

ture and, if possible, the humidity. and an electrical fault


Stop Low capsule fill weight
3. Vary the speed of the machine over as wide a
11.36 Start Correct capsule fill weight
range as is possible.
11.40 4
4. Estimate the amount of dust produced, the
11.50 5
smooth running or vibration of the machine,
11.59 Stop Blocked empty capsule feed tube
and examine for overheating.
12.02 Start
5. List any modifications that are required.
6. Consider the noise level near the machine, the Table 2. Example of an event-time Log.
extent to which moving parts are protected
and how easy it is to load the machine with
empty capsules and material for filling. etc. This results in some variation in powder flow
and bulk density and may adversely affect the filling
If the equipment is fitted with an automatic
characteristics of that batch of product. The follo-
weight control system, then Phase I should be re-
wing experimental plan is designed to evaluate a
peated to check the performance of this system.
high speed filler operating at 90,000 capsules
Only checks on the weight of capsules are required,
per hour with a fill weight (excluding capsule) of
but a time event log should be kept.
250 mg.
The most fundamental of all these tests is chec-
a. Define location and environment controls
king the weight of the filled capsule. For manually
available eg temperature and relative humidity.
operated hand fillers this is relatively simple and
checks can be in line with an appropriate mono- b. Define quantity of capsules to be filled.
graph in the USP, BP or EP pharmacopoeias (or c. Select formulation and define manufacturing
other pharmacopoeia depending on the country of process. (This process must be performed
origin) or the company's own corporate specifica- under controlled conditions of temperature
tions. Determination of elementary statistics such as and humidity.)
mean weight, standard deviation and coefficient of
d. Measure physical parameters such as bulk
variation can be used to evaluate the samples.
density, flow, particle size, moisture content
Where the equipment under evaluation has a high
and chemical tests on product containing ac-
output then the experimental plan is more complex
tives.
and there are other variables which will apply. Raw
materials will vary within their defined specifications e. Select type of capsules to be used.
particularly regarding their physical characteristics f. Define the sampling plan. The machine will
such as particle size, surface area, particle shape operate theoretically for 5 hours where the

17
powder has a batch size of 125 kg. The sim- f. Maintenance required.
plest method is to collect say 50 filled cap- g. Instrumentation systems (automatic weight
sules every 15 minutes and check weigh 20 and pressure control).
as required by most pharmacopoeias. (Better
h. Equipment specifications.
to collect too many at this stage than find a
shortage during testing. This permits other i. Ease of cleaning.
tests to be performed eg assay, dissolution, j. Safety. (How well is the operator protected
content uniformity where active product is from moving parts and what interlocks are
being filled). provided.)
Where two machines from different manufactu- k. Services required.
rers are being compared then the above plan can l. Cost of basic unit, spares, change parts and
be followed but with a change in the batch size of their availability.
product. The batch size should be doubled to say
m. Dimensions (footprint and height clearance
250 kg and after manufacture it can be divided in
required) and weight.
two parts and 125 kg used on each machine. This
will then eliminate any batch to batch variation in All of these items need to be evaluated in the
raw materials and in the manufacturing process. overall appraisal.
Samples collected during manufacture can be com-
pared to each other and against a known standard.
2.3. cGMP and validation
2.2. Mechanical evaluation No equipment evaluation is complete without an
assessment of GMP and Validation requirements.
Simple machines are generally the best to ope-
rate and maintain. Capsule filling requires an opera- Validation is expensive and the documentation
tion that will separate a container, fill it with powder supplied for the equipment should be examined for
or an alternative, close it and eject it from the ma- details on:
chine without damage resulting in a pharmaceuti- • materials of construction of product
cally elegant product. All automatic equipment ma- contact parts,
nufactured by the leading companies (see Table I)
can achieve this result, however, certain products
• maintenance schedules,
perform better on some types of machines than • operating manual,
others. It is not always possible to define the scien- • diagnostic fault analysis,
tific basis for this and it is best to test the product • calibration of instruments.
on a number of different types to determine the best
performance. Mechanically continuous operating 316L (low carbon content) stainless steel is the
equipment is simpler to maintain than intermittent most commonly used material where products are
but many companies favour intermittent equipment in contact and is readily acceptable to regulatory
from a pharmaceutical viewpoint. agencies as the material of choice. Painted surfaces
are now being replaced universally by stainless steel
One of the main areas of mechanical concern for cladding and this improves both the appearance
a capsule filling operation is how quickly and easily and the cleaning operation.
a size change may be completed and the machine
cleaned ready for the manufacture of a different pro- All automatic equipment requires the use of va-
duct. In addition the main emphasis during evalua- cuum to separate the shells into body and cap and
tion must be on the following areas: the effectiveness of this system should be tested to
ensure consistent performance. Dust extraction is
a. Lubrication systems.
required also and an assessment of the way in
b. Access for maintenance. which the filters are installed, how easily they can be
c. Noise level. changed and their cost should be determined as
d. Mechanical and electrical documentation. part of the engineering/GMP evaluation.
e. Materials of construction and in particular the Companies that supply excellent equipment are
standards of finish for the product contact not always so efficient in providing simple but detai-
surfaces. led operating instructions for the machine. It must

18
be borne in mind that a standard operating proce- 1. Define objectives:
dure (S.O.P.) will be required and assimulating badly
a. Comparison of new equipment against
written or poorly translated documentation can be
existing (same supplier).
lengthy, and expensive.
b. Higher output required.
Calibration of instruments must be addressed to
c. Comparison of various equipment available.
ensure that they are easily maintained in their ope-
rating range and it is important to differentiate bet- d. New product requires capsule filling.
ween critical and convenience instruments. Critical
2. Define formulations to be used:
instruments must be calibrated in their operating
range against known traceable standards for vali- a. Placebo - what physical characteristics
dation. Examples would be the vacuum gauge for required.
measuring the vacuum required to separate the b. Product containing actives.
capsules into their component parts and the gauge c. Capsule type(s).
for measuring the pressure required for producing a
plug on compression filling equipment. Critical ins- 3. Define tests:
truments are defined as those likely to effect the a. On powder.
quality of the finished product for example the
b. On filled capsules.
hardness of the plug may adversely effect drug dis-
solution. Convenience instruments are those requi- 4. Define location:
red to provide data for production operations and
a. In-house.
management purposes e.g. a capsule counter fit-
ted to a capsule filler. (if the capsule counter is fitted b. At equipment suppliers.
to a package unit for counting capsules into bottles c. Other.
or sercuritainers then it becomes a critical instru-
ment). 5. Define personnel expertise
requirements for tests:
a. Formulation pharmacist.
2.4. Summary b. Quality control.
In capsule filling equipment evaluation one of the c. Engineering support.
most important aspects is to define the experimen- d. Others.
tal plan. It may be that some preliminary test work is
required to determine what are the most critical 6. Validation/cGMP input requirements
operations on a particular machine. This can be
7. Cost:
achieved using placebo material before proceeding
to the plan proper. It should be remembered that a. Manhours.
faults do not always show up on high speed equip- b. Materials:
ment until it has been operating for several hours • placebo
and reaches steady state operating temperature. • product
Placebo formulations do not necessarily behave • capsules
as products containing active formulations and a fi- c. Other:
nal trial will be necessary using the actual product. • transport
The size of this trial will depend on cost and whe- • total cost of test programme.
ther the material used can be sold. In this case the
trials are best conducted in registered premises to
ensure all cGMP requirements are met. 3.0. Validation of hard gelatin
It is also worth discussing with other users their
capsule filling equipment
particular preferences and experiences. (Many ma- and ancillary services
nufacturing companies will discuss their use and its
Validation is a Quality Assurance procedure and
performance of various types of equipment).
this concept has been developed by the Pharma-
The following check list may be useful in develo- ceutical Industry to ensure that the manufacture of
ping an experimental plan. medical products and devices are produced using

19
Environment

Facility

Utilities Document Software Quality ?


systems control hardware control Change
HVAC control

Automatic Analytical Packaging


systems
Calibration Labelling
Recall
Storage
Equipment
S.O.P's Process
Product
Raw
materials Preventive
maintenance

Training Distribution

S.O.P's: Standard operating procedures

Figure 23. The elements of validation

standards which are approved by national and local However, a more comprehensive definition sums
regulatory authorities. up the ideas of Validation as:
The Food and Drug Administration (FDA) in the "In today's Pharmaceutical Industry, whether you
USA are generally considered to enforce the highest are thinking about a computer system, a water
standards and here we will use their requirements treatment system or a manufacturing process vali-
as the benchmark. dation means nothing more than well-organised,
well-documented, common sense."
In the United States or in the country where a Ken Chapman, Pfizer, 1985
company is manufacturing pharmaceutical products
for potential sale to the USA, then a FDA inspection Validation has also been defined as the activity
is mandatory and the inspector will wish to see the performed to demonstrate that a given utility, sys-
validation documentation. It should be emphasized tem, process, or piece of equipment does what it
that validation is a total concept. This is represented purports to do. The primary means of accompli-
shing this end is the scientific study designed to
in Figure 23.
specifically determine whether the entity under scru-
It is not only concerned with equipment and the tiny does in fact:
process, but also the facility, personnel, training,
maintenance, automated systems, documentation,
• Meet or exceeds the specifications
of its design.
and analytical procedures.
• Is properly built, shipped, received, stored,
There are many definitions of validation, but the installed, operated and maintained.
one that is universally recognised is:
• Is suitable for its intended application.
"Establishing documented evidence that a sys- • Is in accordance with principles established
tem does what it purports to do". (Loftus - 1977) and generally accepted by the pharmaceutical
and used by the Industry ever since. scientific community.

20
• Conforms to basic cGMP design criteria. Figure 24 shows how for this project’s life cycle
the documentation interacts with the Validation
• Will satisfy the concerns of regulatory bodies. documentation. Some of these activities are self-
• Is capable of consistently producing explanatory but others such as user requirement
a product that is fit for use. require further exploration.
• Will meet the goals established The user requirement should be prepared by the
for productivity, safety, and quality.
“user” to formally document each of the require-
This scientific study is generally detailed in a vali- ments of the “system” to be validated in terms of
dation protocol. A well designed validation protocol the final process requirement. Specifically it relates
properly supported by senior management will to quantity, quality, compatibility, performance, the
accrue considerable benefit to its sponsor. Not only environment and finishes in terms of:
will regulatory obligations be fulfilled, but also pro-
cesses will be optimized, productivity improved, and • materials of construction
downtime reduced. In short, a validation pro- • cleanability requirements
gramme with a sound scientific base and proper
experimental design is simply good business if
• maintenance requirements
taken seriously and executed conscientiously. The • operator interface requirements
strategy can be documented in what is known as a • performance criteria
Master Plan.
• critical parameters
The purpose of the Validation Master Plan is to • operating ranges of critical parameters
convey to the FDA and other regulatory bodies,
understanding of a company's responsibilities
• essential design criteria
concerning the validation and certification of the • requirements of computer systems
facility along with plans to discharge that respon- • training and documentation requirements
sibility. It will also serve as a guide to those adminis- and should make reference to all relevant in-
tering and performing validation activities and as a house standards and regulatory documents.
road map to successful project completion. The
Master Plan may be used as an instrument to define The Master Plan is used to define the boundary
areas of responsibility and accountability to valida- limits and provide a "bible" for all members of the
tion team members, and it contains all the pro- validation team to ensure that they all sing from the
grammes necessary to certify the validation of the same "hymn book".
facility system and processes.
In most companies a validation team or "task
By integrating the pharmaceutical and enginee- force" is assembled under the QA/QC Manager (de-
ring disciplines, the Validation Master Plan des- signated the Validation Manager) and drawn from
cribes the facility and outlines a set of activities appropriate departments e.g.
tailored to that facility providing a cost effective vali-
dation programme that not only minimizes regula- • Analytical Department.
tory exposure but is delivered within the prescribed • Production Department.
time constraints.
• Maintenance/Engineering/Electrical.
The life cycle concept of validation is a recurring • Process Development/Formulation.
theme throughout the Master Plan. Paramount is
the establishment of the infrastructure to ensure • Personnel/Training.
that the facility is supported by sufficient documen- Each department will be able to contribute their
tation throughout its conceptual and functional life- expertise to the Validation Programme.
time. This lifetime includes project inception, design, So what needs to be validated?
engineering, construction through testing, certifica-
tion, maintenance, revalication, and change control. We need to define the limits objectively as valida-
tion is a costly procedure.
For a capsule filling operation, we will only consi-
der process utilities and the facility, in addition to the • Facility
capsule filling equipment required to manufacture The rooms in which the raw materials and product
and fill a powder into hard gelatin capsules. Essen- are stored, manufactured, filled and dispatched.
tially, we are concerned with product contact either
directly or indirectly. • Process Utilities

21
Project Life Cycle and Validation Documentation

Project Life Cycle Validation


Documentation Documentation

User Requirement Validation


Specification Master Plan

Vendor Assessment Standard Operating


Pre-Qualification
& Selection Procedures (SOPs)

Design
Specification
Design
Qualification

Procurement

Construction/
Delivery

Installation
Qualification
Installation

Calibration Calibration
Qualification

Engineering
Commissioning

Operation
Qualification Training
Process
Commissioning
Performance
Qualification

Process
Production
Validation

Figure 24. Project life cycle and validation documentation.

22
Typically compressed air, heating, ventilating and
INSTALLATION QUALIFICATION
air conditioning, (HVAC), vacuum systems, dust OPERATIONAL QUALIFICATION
extraction and collection, purified water and ef- PROCESS VALIDATION
fluent treatment system. FACILITY
(PROCESS ROOMS) x – –
• Manufacturing equipment PROCESS UTILITIES
Mixers, mills, capsule fillers, capsule sorting and HVAC x x x
cleaning equipment, metal detectors, packaging Compressed Air x x x
equipment. Purified Water x x x
Vacuum x x x
• Control systems Dust Extraction x x –
Those devices which record various process Effluent Treatment x x –
operations such as the weight of raw materials EQUIPMENT
used and automatic weight control systems. Blender x x –
Mill x x –
• Process validation Sieve x x –
Each unit operation requires a validation test pro- Capsule selector x x –
gramme. A typical process block flow diagram is Capsule filler x x –
shown in Figure 2. The balances required in the Capsule cleduster x x –
Metal detector x x –
dispensary are considered part of the calibration
Capsule inspection unit x x –
programme. If pneumatic transfer is used, then Capsule counter/filler
this part of the process must be linked in a pro- (containers) x x –
tocol to an item of processing equipment. Capsule blister packer x x –
Table 3 provides a basis for determining the SYSTEMS
number of protocols that need to be produced. It is Material handling system x x –
not an exhaustive list and neither is it a minimal list, Automatic weight control x x x
but indicative of what has to be produced. PROCESS
Mixing – – x
Many companies have a Performance Protocol Milling/sieving – – x
completed before Process or Product Validation is Capsule filling – – x
completed. This specifically tests the equipment and Table 3. Protocols required.
systems within the operation required by the product.
to show the visiting inspector and to be used as a
3.1. Scope of documentation reference source for all members of the validation
team. For example, the table of contents may
It is not proposed to detail here all the validation contain the following:
documentation required. For a more comprehensive 1. Approval page
study other references should be consulted, such 2. Introduction
as the book on the Design of Pharmaceutical Pro- 3. Scope
duction Facilities (3) FDA Code of Federal Regula- 4. Glossary of terms
tions section 21 (4). The Rules Governing Medicinal 5. Preliminary drawings/facility design
Products in the European Community (5) and the 6. Raw material qualification
GMP Regulations of Japan (6). 7. Process description(s)
The outlines for the requirements of the Master 8. Rooms and room classifications
Plan, Installation Qualification (IQ), Operational Qua- 9. Description of utilities
lification (OQ), and Process Validation (PV) are defi- 10. Description of process equipment
ned below and should be compiled as "stand 11. Automated systems
alone" documents. 12. Equipment history files
13. Construction documentation
14. Description of required protocols
3.1.1. Master plan 15. List of standard operating procedures
16. Required document matrices
The Master Plan should contain the following 17. Validation schedule/construction schedule/
sections and can be used as an internal document integrated schedule

23
18. Protocol outlines/summaries Name Signature Date
19. Environmental monitoring programme Manufacturing … …
20. Analytical testing procedures Engineering … …
21. Calibration programme Quality assurance … …
22. Training programme
R&D … …
23. Preventive maintenance programme
Safety … …
24. Change control programme
Site manager … …
25. Document control programme
Regulatory affairs … …
26. Manpower requirements
Validation Manager … …
27. Key personnel
28. Protocol examples
29. Standard operating procedures
(SOP) examples
The following pages or sections will be required:
30. Appendix
Equipment use
• Specification,
3.1.2. Installation Qualification • Materials of construction for product contact
protocol surfaces,

An Installation Qualification protocol (IQ) contains • Inspection check list,


the documented plans and details of procedures • Installation check list,
which are intended to verify specific static attributes • Any relevant drawings eg section through do-
of a facility, utility system, or process equipment. sator and filling hopper,
The Installation Qualification (IQ) when executed is • Manufacturers certification,
also a documented verification that all key aspects • Calibration review,
of the installation adhere to the approved design in-
tentions and that the manufacturer's recommenda-
• Standard operating procedure (SOP),
tions have been implemented. • Cleaning procedure,
• Training required,
• Supporting utilities,
3.1.3. Operation Qualification • Summary and certification.
protocol Appendix: Here any relevant documents should
be referenced eg, purchase order, manuals supplied
An Operation Qualification protocol (OQ) contains for maintenance.
the plan and details of procedures to verify specific
dynamic attributes of a utility system, or the process Similarly an OQ document will be compiled
equipment, throughout its operating range including as follows:
worst case conditions. The Operation Qualification, • Approval page (as for IQ),
when executed, is documented verification that the • Use,
system or subsystem performs as intended throu- • Instrument list:
ghout all anticipated operating ranges. - Critical,
- Convenience,
• Calibration procedure,
3.1.4. Protocol preparation
• Test procedures,
Capsule filling equipment will require two proto- • Acceptance criteria summary,
cols, an IQ and an OQ. An outline of the content of • Summary of test results and certification.
each page of each protocol is given here. The IQ
Appendix - reference documents.
will detail specific specifications of a capsule filler;
for example the approval page may require the par- Process utilities
ticipation of each or some of the following functional IQ and OQ protocols must be produced for each
areas: of the services that will be required by the capsule

24
filling equipment. Usually these are; compressed air, 2. There are two operating systems of a capsule
vacuum, HVAC, and dust extraction. The supply of filler that need to be assessed. These are the cap-
electricity is usually covered in the protocol for the sule powder system, and handling of the empty
facility and detailed on a Room Data Sheet. capsule shell.
Each part can be broken down as follows
3.1.5. Process Validation protocol Capsule Handling System (Sectional drawings
are useful)
The Process Validation protocol (PV) is a docu-
mented plan and details procedures to verify speci- • empty capsule feed hopper
fic capabilities of process equipment and systems • feed tube
through the use of simulation materials such as the • rectification unit
use of a nutrient broth in the validation of an aseptic
filling process, or the use of a placebo formulation in
• transfer system
a capsule filling process. However, three batches of • separation system (all parts that handle the
the product material must be manufactured and cap and capsule body)
sold to comply with the regulatory validation requi- • unification system
rements. • ejection system
It is not proposed to detail this protocol as this Powder Handling System
needs to be treated separately. However, it must be
• bulk powder hopper
remembered that each unit operation of the process
must be validated. For example a series of experi- • powder feed system to dosing hopper
ments must be conducted to demonstrate that un- • powder filling system (if a compression filler is
der the stated conditions a homogenous mixture is being used then each individual dosator must
produced for each batch of product manufactured. be specified eg piston and cylinder)
• the powder dosing or filling hopper
Where stirring devices or augers are used to en-
sure homogenity and improve flow, then these parts
3.2. Validation protocol for a MG2 must have a detailed specification for the validation
document.
G37N capsule filler

3.2.2. Instruments
3.2.1. Objective:
All critical instruments (those that effect product
The validation of this capsule filler requires the quality) should be listed and calibrated against a
development of Installation and Operation Qualifica- known standard eg:
tion documents. For the Installation Qualification do- a. vacuum gauge
cument the following actions are required.
b. pressure control (hardness of the plug)
1. A detailed specification must be written which c. fill weight
highlights all those parts of the machine that are in
d. machine speed
product contact.
Generally these parts will be constructed using
316L stainless steel. (This does not mean that all 3.2.3. Utilities
other materials are unacceptable, but the regulatory
authorities have more knowledge of the use of this Those utilities which are used in the machines
material than any other and demonstrating its ac- operation such as
ceptability will be simplified eg less expensive). - compressed air,
This information can be abstracted from the ma- - vacuum,
nufacturers' literature, drawings and other relevant - dust extraction,
manuals, plus certificates of analysis of the mate- - HVAC system of room (control of temperature
rials used. and humidity),

25
will each require IQ and OQ documentation. In - all the relevant documents are in place, such as
addition the quality of the compressed air will need SOP's and planned maintenance schedules,
to be tested for colony forming units (CFU) hydro- - what tests are required, who can perform them
carbon content, particulates and moisture using a and a record of the results when they have
validated analytical method and ensuring that the air been conducted,
meets the specification of the relevant pharmaco-
- a summary of the calibration schedule on an in-
poeia (USP, BP, EP, etc.).
house programme for monitoring the quality of
the process utilities eg compressed air.
3.2.4. Filling control system
There is a move in many countries (Europe, USA
3.3. Summary
and Japan) for more automation in the operation of The cost of validation is considerable. In the USA
capsule filling equipment. Where these process it has been estimated that it can add as much as 15
control and monitoring systems are in place, then a per cent to the installed capital cost of the project.
separate section is required for their installation and However, validation correctly performed and execu-
operational validation. Computer Validation is a ted can save the company large sums in ensuring
complex subject and needs to be considered at the consistent production, minimised down time and an
onset of the project. avoidance of recalled products from the market
It should be remembered that in addition to the place. In addition it reduces the cost of in-process
capsule filler, its services and the room in which it is control and provides quality assurance for all pro-
located, any ancillary equipment used to handle the ducts.
empty capsules, powder and filled capsules must The following actions need to be conducted by
be treated identically. This would include: the validation team.
- an empty capsule sorter,
1. Collect relevant data
- conveyor of empty shells to filling machine,
- operating manuals,
- bulk storage system for powder
and feed conveyor to filler, - drawings (piping and instrumentation
drawings (P & ID's)),
- filled capsule deduster and sorter.
- calibration documents,
Having established the installation specifications - SOP's,
and produced a document which identifies all the
validation requirements, then this can be used to - maintenance schedules,
verify that the installation is in accordance with re- - pest control procedures,
gulatory requirements, the corporate standards and - quality control procedures,
equipment manufacturers' specification, as certified - training records.
by the Validation Specialist and Manager.
2. Prepare documentation:
- assimilate relevant data,
- define boundary limits,
3.2.5. Operational Qualification (OQ)
- define equipment requirements,
This document is developed in a similar way to - define format,
the IQ, but here the objective is to check that all the - define responsibility,
dynamic attributes of the capsule filler conform to
the required specifications as detailed in the IQ. - define test instruments requirements.

- the machine operates within the desired range 3. Test procedures:


of output, - complete test.
- all the critical instruments operate in their cali- 4. Certification.
brated ranges and the traceable standard
against which they have been calibrated is
identified,

26
4.0. Conclusion
In this paper some concepts have been discus-
sed which provide a framework for the design,
layout and operation of a capsule filling manufactu-
ring facility to ensure compliance with International
GMP requirements and to reduce costs.
There are many possible layout combinations
that meet this criteria and these requirements have
to be assessed depending on the size of the opera-
tion, the equipment and the personnel available.
The use of manual operations are being phased
out in many countries and it is not primarily because
of costs, but additionally because a properly desi-
gned and validated automated system will provide a
greater degree of quality assurance.

5.0. References
1. BAS 195E 1998: Pharmaceutical Technology Europe
May 1998 Volume 10 Number 5.
2. Powder Characteristics for Capsule Filling Chapter 8
G.C. Cole in Hard Capsules ed. K. Ridgway. Published
by British Pharmaceutical Press 1987. ISBN 0-85369-
159 2.
3. Pharmaceutical Production Facilities - Design and Appli-
cations. Chapter 15, Validation G.C. Cole 1990 2nd
Edition 1998 ISBN 0-7484-0438-4 publisher Taylor &
Francis.
4. Code of Federal Regulations (CFR) USA Section 21
Parts 200-299 USA Government April 1 1992.
5. The Rules Coverning Medicinal Products in the Euro-
pean Community. Volume 4 Guide to Good Manufactu-
ring Practice for Medicinal Products 1989 Luxembourg.
Office for Official Publications of the European Commu-
nities. ISBN 92-825-9572-2.
6. GMP Regulations of Japan, 3rd Edition 1987 ISBN 4-
8408-0116-9 Yakuji Nippo Sha, Tokyo.

27
BAS 148 E 1999

You might also like